Motor Accident Claim Maintainable Despite Compensation Under Workmen’s Compensation Act – Insurer Liable Despite Fake Licence Allegation: Gujarat High Court Review Is Not a Second Round of Litigation: Orissa High Court Dismisses Plea Seeking Reconsideration of Dropped Contempt in MCL Appointment Case Fresh Ex Parte Relief Cannot Bypass Order 39 Rule 3 – Restoration of Electricity Refused for Tenant Running Cold Storage: Punjab & Haryana High Court Section 498A IPC | Telling Her To Indulge In Prostitution For Dowry Is Most Obnoxious Form Of Harassment: Jharkhand High Court Search Can’t Stretch Time: Gujarat High Court Quashes Income Tax Reopening Beyond 10-Year Limit in Search-Based Reassessment 138 NI Act | Mere Claim of ‘Security Cheque’ No Defence Against Statutory Presumption : Calcutta High Court Rigour of Section 37 NDPS Act Cannot Be Diluted by Bail Pleas Citing Delay or Procedural Defects: Punjab & Haryana High Court Denies Bail in Heroin Recovery Case If Arbitration Clause Itself Bars Larger Claims, Court Cannot Appoint Arbitrator: Bombay High Court Dismisses Section 11 Application Once Arbitration Clause Exists and Proceedings Are Ongoing, Civil Court Must Step Back: Andhra Pradesh High Court Dismisses Suit for Injunction in Partnership Dispute Autonomy of Private Schools Can't Be Crushed in the Name of Fee Regulation: J&K High Court Strikes Down FFRC Chairperson Clause, Upholds Fee Control Law with Caveats Demand and Acceptance of Bribe Must Be Proved as a Fact – Mere Possession of Money Not Enough: Kerala High Court Recovery Alone Can't Prove Bribery Where Legal Fee Is Established Through Official Records: Punjab & Haryana High Court Acquits Patwari Exoneration on Technical Grounds Can’t Quash Criminal Prosecution for Tax Evasion: Kerala High Court Denies Relief to Doctor Accused of Concealment Answer To A Leading Question Cannot Be Sole Basis For Conviction In Serious Offences Like Rape: Bombay High Court NDPS | Mere Absence of Contraband No Ground for Bail When Recovery from Co-Accused Points to Coordinated Drug Network: Punjab & Haryana High Court Allahabad High Court Quashes Ceiling Surplus Land Order Passed Without Spot Inspection, Ignores Rights Acquired Through Adverse Possession Civil Death Cannot Be the Price of Past Mistakes: Orissa High Court Strikes Down Blanket Tender Ban on Previously Blacklisted Bidders Once Supreme Court Cancels Bail for Violation, Subordinate Courts Cannot Reconsider: Karnataka High Court Non-joinder Is a Curable Defect, Not a Death Blow to Appeal: Madhya Pradesh High Court Restores Mutation Appeal Stale Allegations and Closed FIRs Cannot Justify Preventive Detention: J&K High Court Quashes PSA Detention Order for Lack of Proximate Link Employment-Related Separation Cannot Be Labelled as Desertion: Jharkhand High Court Dismisses Husband’s Divorce Appeal “Fair Pre-Estimate” of Damages Valid Even Without Proof of Loss: Delhi High Court Partly Sets Aside Arbitral Award in Carlsberg Dispute Or 39 CPC | Unregistered Will With Single Attesting Witness Cannot Confer Absolute Title: Delhi High Court Grants Injunction Failure To Comply With Mandatory Rent Deposit Directions Under WBPTA Will Invite Striking Off of Tenant’s Defence, Even For Single Default: Calcutta High Court Insistence on Impossible Term Reflects Absence of Readiness: Bombay High Court Denies Specific Performance for Delay and Inflexibility Medical Negligence | Stem Cell Therapy for Autism Is Not Valid Medical Practice: Supreme Court Declares Commercial Use as Medical Negligence Stem Cells Are ‘Drugs’ Under Law, Not Medical Procedures”: Supreme Court Brings Stem Cell Therapy Back Under Drugs Act NGT Can Impose Compensation Without Statutory Formula, Guided By Polluter Pays Principle: Supreme Court Upholds Environmental Penalties On Builders Environmental Compensation Must Not Be Illusory: Supreme Court Upholds NGT’s ₹5 Crore Penalty On Builder For Violating Environmental Laws Section 34 Court Has Limited Power to Modify Arbitral Award — But It Exists: Supreme Court Endorses Judicial Calibration of Damages in Arbitration Delay in Public Utility Projects Is Per Se a Loss: Supreme Court Upholds ₹27 Crore Damages Against Solar Developer Article 21 | Menstrual Health is an Integral Facet of Right to Life & Dignity: Supreme Court RTE Act | Free Sanitary Pads, Vending Machines & Separate Toilets Mandatory for All Schools: Supreme Court Issues Continuing Mandamus No Waiver of Fundamental Rights by Signing a Job Contract: Supreme Court Declares Contractual Clauses Barring Regularization Unenforceable When the State is the Lion, the Employee Cannot Be the Lamb Forever: Supreme Court Slams Jharkhand for Exploiting Contractual Engineers for a Decade Bail Once Granted Should Not Be Cancelled Lightly: Supreme Court Refuses to Revoke Bail of Accused in Daylight Murder Case A Decade of Targeted Persecution Cannot Be Cloaked as Procedure: Supreme Court Slams Department for Systematic Denial of ITAT Appointment Even Presence Of A Single Biased Member Vitiates  Selection Process: Supreme Court Nullifies ITAT Appointment Panel Over Bias Concerns Court Can Prevent Institutional Vacuum Despite Invalid Appointment: Supreme Court Invokes Article 142 to Protect Tenure of Vice-Chancellor in Exceptional Circumstances State Cannot Override Higher Education Standards Set by Parliament: Supreme Court Declares Puducherry VC Appointment Illegal, Upholds Primacy of UGC Regulations

If Arbitration Clause Itself Bars Larger Claims, Court Cannot Appoint Arbitrator: Bombay High Court Dismisses Section 11 Application

31 January 2026 6:43 PM

By: Admin


“Party Autonomy Means Freedom to Arbitrate — and Freedom Not to Arbitrate Certain Claims” —  In a significant ruling interpreting the scope of arbitration agreements and party autonomy, the Bombay High Court held that courts have no jurisdiction under Section 11 of the Arbitration and Conciliation Act, 1996 to appoint an arbitrator when the very arbitration clause excludes arbitrability of claims exceeding a specified threshold.

Commercial arbitration application under Section 11(6) of the Arbitration Act was dismissed by Justice Sandeep V. Marne, after the Court found that the contract between the parties only allowed arbitration for claims up to 20% of the contract value, and explicitly excluded arbitration for any higher-value claims.

“There Is No Arbitration Agreement for Rs.3 Crore Claim When Contractual Arbitration Cap Is Rs.16.9 Lakhs”

The case revolved around a dispute arising out of a contract dated 7 May 2018, under which the applicant, M/s. Sowil Limited, was awarded work by the Central Railways for a contract value of ₹84.52 lakhs. After termination of the contract, the applicant sought arbitration for an estimated claim of ₹3 crores, nearly 400% of the contract value.

However, Clause 39 of the contract specifically provided: “The provisions of Clauses 63 and 64 of the GCC will be applicable only for settlement of claims or disputes between the parties for values less than or equal to 20% of the value of the contract... arbitration will not be a remedy for settlement of such disputes [exceeding that limit].”

Justice Marne held:

“The parties have expressly agreed that only claims up to 20% of the contract value would be adjudicated through arbitration. The applicant’s claim being 400% of the contract value, there exists no arbitration agreement in respect of the claim sought to be referred.”

“Party Autonomy Does Not Mean Every Dispute Must Be Arbitrated”

Rejecting the applicant’s argument that the restrictive clause was arbitrary and violative of Article 14, the Court ruled: “Party autonomy is the foundation of arbitration. If parties agree to resolve only a subset of disputes through arbitration, courts cannot compel them to arbitrate beyond what is agreed.”

The Court clarified that arbitration is a contractual remedy, not a constitutional right:

“If there was no arbitration clause at all, could the applicant have insisted on arbitration? The answer is obviously no. The same logic applies when the clause restricts arbitrability to claims of a certain value.”

The judgment noted that Section 7 of the Arbitration Act requires a valid arbitration agreement, and the jurisdiction of the Court under Section 11 is limited to enforcing that agreement, not expanding it.

“No Violation of Article 14 — Clause Applies Equally to Both Parties”

The applicant argued that the clause was discriminatory as it limited the contractor’s right to arbitrate but not the Railways’. The Court found this contention “misplaced and speculative”, observing:

“Clause 39 applies to disputes ‘between the parties’ — not just the contractor. Whether Railways will raise counterclaims exceeding 20% is speculative. At Section 11 stage, the Court only looks at the applicant’s claim.”

Justice Marne further held: “The clause does not bar legal remedies — it merely directs higher-value claims to the civil court. There is no embargo on the contractor’s right to sue.”

“No Arbitrator Can Be Appointed Where Arbitration Agreement Does Not Cover the Dispute”

The applicant urged the Court to appoint an arbitrator and leave the issue of arbitrability to the tribunal under Section 16 (Kompetenz-Kompetenz doctrine). The Court flatly rejected this:

“Section 16 assumes an existing arbitration agreement. Where the agreement itself excludes certain disputes, the Court under Section 11 must decide jurisdiction. This is not a question the arbitrator can rule upon.”

The Court cited its own earlier ruling in Railtech Infraventure Pvt. Ltd. v. Union of India, which had upheld the same 20% ceiling for arbitrability under similar clauses.

“Clause Not Arbitrary Like Pre-Deposit Clauses in ICOMM Tele Case”

The applicant relied heavily on the Supreme Court’s landmark ruling in ICOMM Tele Ltd. v. Punjab State Water Supply Board, where a clause requiring 10% pre-deposit was held arbitrary and unconstitutional under Article 14.

Justice Marne, however, distinguished ICOMM, observing:

“In ICOMM, a claimant was barred from arbitration unless it deposited 10% of claim value — with risk of forfeiture. In contrast, here the contractor is not barred from enforcing claims exceeding 20%; he is only required to go to civil court.”

“Unlike ICOMM, this clause does not deter, penalize, or restrict legal enforcement — it only limits the forum of adjudication.”

“Courts Cannot Rewrite Arbitration Agreements”

Rejecting arguments based on Shin Satellite Public Co. Ltd. v. Jain Studios Ltd., where the Supreme Court upheld severability of contractual clauses, the Court said:

“Doctrine of severability applies only where part of the agreement is invalid. Here, the 20% cap is neither invalid nor unconstitutional. Hence, there is no question of severance.”

“Contractual Limitations on Arbitration Are Valid — Precedents Affirm This”

The Court relied on multiple precedents — Deepak Kumar Bansal (SC), Seth Mohanlal Hiralal Construction (MP HC), Railtech Infraventure (Bom HC), and State of A.P. v. Obulu Reddy (SC) — all of which recognised the validity of arbitration clauses restricting claims by monetary threshold.

In Deepak Kumar Bansal, the Supreme Court did not invalidate the 20% ceiling; instead, it held that additional work orders must be counted to determine total contract value — a factual point not applicable in the present case.

“Railways Cannot Be Forced to Arbitrate Where It Has Not Agreed To”

In a resounding affirmation of contractual freedom, Justice Marne concluded:“When the parties have agreed to arbitrate only claims up to a defined value, the Court cannot compel arbitration of higher-value disputes. Such intervention would overstep judicial jurisdiction under Section 11.”

The Court also clarified: “Encouraging arbitration does not mean enforcing it beyond its agreed limits. Courts must respect contractual boundaries — party autonomy includes freedom not to arbitrate certain disputes.”

Accordingly, the Section 11 application was dismissed, with the Court holding that no arbitration agreement existed in respect of the ₹3 crore claim, and therefore no arbitrator could be appointed.

Date of Decision: 28 January 2026

Latest Legal News