Motor Accident Claim Maintainable Despite Compensation Under Workmen’s Compensation Act – Insurer Liable Despite Fake Licence Allegation: Gujarat High Court Review Is Not a Second Round of Litigation: Orissa High Court Dismisses Plea Seeking Reconsideration of Dropped Contempt in MCL Appointment Case Fresh Ex Parte Relief Cannot Bypass Order 39 Rule 3 – Restoration of Electricity Refused for Tenant Running Cold Storage: Punjab & Haryana High Court Section 498A IPC | Telling Her To Indulge In Prostitution For Dowry Is Most Obnoxious Form Of Harassment: Jharkhand High Court Search Can’t Stretch Time: Gujarat High Court Quashes Income Tax Reopening Beyond 10-Year Limit in Search-Based Reassessment 138 NI Act | Mere Claim of ‘Security Cheque’ No Defence Against Statutory Presumption : Calcutta High Court Rigour of Section 37 NDPS Act Cannot Be Diluted by Bail Pleas Citing Delay or Procedural Defects: Punjab & Haryana High Court Denies Bail in Heroin Recovery Case If Arbitration Clause Itself Bars Larger Claims, Court Cannot Appoint Arbitrator: Bombay High Court Dismisses Section 11 Application Once Arbitration Clause Exists and Proceedings Are Ongoing, Civil Court Must Step Back: Andhra Pradesh High Court Dismisses Suit for Injunction in Partnership Dispute Autonomy of Private Schools Can't Be Crushed in the Name of Fee Regulation: J&K High Court Strikes Down FFRC Chairperson Clause, Upholds Fee Control Law with Caveats Demand and Acceptance of Bribe Must Be Proved as a Fact – Mere Possession of Money Not Enough: Kerala High Court Recovery Alone Can't Prove Bribery Where Legal Fee Is Established Through Official Records: Punjab & Haryana High Court Acquits Patwari Exoneration on Technical Grounds Can’t Quash Criminal Prosecution for Tax Evasion: Kerala High Court Denies Relief to Doctor Accused of Concealment Answer To A Leading Question Cannot Be Sole Basis For Conviction In Serious Offences Like Rape: Bombay High Court NDPS | Mere Absence of Contraband No Ground for Bail When Recovery from Co-Accused Points to Coordinated Drug Network: Punjab & Haryana High Court Allahabad High Court Quashes Ceiling Surplus Land Order Passed Without Spot Inspection, Ignores Rights Acquired Through Adverse Possession Civil Death Cannot Be the Price of Past Mistakes: Orissa High Court Strikes Down Blanket Tender Ban on Previously Blacklisted Bidders Once Supreme Court Cancels Bail for Violation, Subordinate Courts Cannot Reconsider: Karnataka High Court Non-joinder Is a Curable Defect, Not a Death Blow to Appeal: Madhya Pradesh High Court Restores Mutation Appeal Stale Allegations and Closed FIRs Cannot Justify Preventive Detention: J&K High Court Quashes PSA Detention Order for Lack of Proximate Link Employment-Related Separation Cannot Be Labelled as Desertion: Jharkhand High Court Dismisses Husband’s Divorce Appeal “Fair Pre-Estimate” of Damages Valid Even Without Proof of Loss: Delhi High Court Partly Sets Aside Arbitral Award in Carlsberg Dispute Or 39 CPC | Unregistered Will With Single Attesting Witness Cannot Confer Absolute Title: Delhi High Court Grants Injunction Failure To Comply With Mandatory Rent Deposit Directions Under WBPTA Will Invite Striking Off of Tenant’s Defence, Even For Single Default: Calcutta High Court Insistence on Impossible Term Reflects Absence of Readiness: Bombay High Court Denies Specific Performance for Delay and Inflexibility Medical Negligence | Stem Cell Therapy for Autism Is Not Valid Medical Practice: Supreme Court Declares Commercial Use as Medical Negligence Stem Cells Are ‘Drugs’ Under Law, Not Medical Procedures”: Supreme Court Brings Stem Cell Therapy Back Under Drugs Act NGT Can Impose Compensation Without Statutory Formula, Guided By Polluter Pays Principle: Supreme Court Upholds Environmental Penalties On Builders Environmental Compensation Must Not Be Illusory: Supreme Court Upholds NGT’s ₹5 Crore Penalty On Builder For Violating Environmental Laws Section 34 Court Has Limited Power to Modify Arbitral Award — But It Exists: Supreme Court Endorses Judicial Calibration of Damages in Arbitration Delay in Public Utility Projects Is Per Se a Loss: Supreme Court Upholds ₹27 Crore Damages Against Solar Developer Article 21 | Menstrual Health is an Integral Facet of Right to Life & Dignity: Supreme Court RTE Act | Free Sanitary Pads, Vending Machines & Separate Toilets Mandatory for All Schools: Supreme Court Issues Continuing Mandamus No Waiver of Fundamental Rights by Signing a Job Contract: Supreme Court Declares Contractual Clauses Barring Regularization Unenforceable When the State is the Lion, the Employee Cannot Be the Lamb Forever: Supreme Court Slams Jharkhand for Exploiting Contractual Engineers for a Decade Bail Once Granted Should Not Be Cancelled Lightly: Supreme Court Refuses to Revoke Bail of Accused in Daylight Murder Case A Decade of Targeted Persecution Cannot Be Cloaked as Procedure: Supreme Court Slams Department for Systematic Denial of ITAT Appointment Even Presence Of A Single Biased Member Vitiates  Selection Process: Supreme Court Nullifies ITAT Appointment Panel Over Bias Concerns Court Can Prevent Institutional Vacuum Despite Invalid Appointment: Supreme Court Invokes Article 142 to Protect Tenure of Vice-Chancellor in Exceptional Circumstances State Cannot Override Higher Education Standards Set by Parliament: Supreme Court Declares Puducherry VC Appointment Illegal, Upholds Primacy of UGC Regulations

Delay in Public Utility Projects Is Per Se a Loss: Supreme Court Upholds ₹27 Crore Damages Against Solar Developer

31 January 2026 1:16 PM

By: sayum


“The Burden Is On the Defaulter to Prove No Loss — Not On the Government to Prove Loss in Public Contracts”, In a landmark pronouncement Supreme Court of India restoring the ₹27.06 crore compensation earlier awarded for delayed commissioning of a 20 MW solar power project under the Jawaharlal Nehru National Solar Mission (JNNSM).

“This was not merely a commercial breach, but a failure in a public utility project committed to the nation’s clean energy transition,” held a Division Bench comprising Justice Pamidighantam Sri Narasimha and Justice Atul S. Chandurkar, reinforcing the enforceability of liquidated damages clauses in public contracts, even in the absence of direct proof of financial loss.

“Clause 4.6 Gets Triggered on Admitted Delay”: Court Reinstates Single Judge’s Finding on Commissioning Failure

The dispute stemmed from a Power Purchase Agreement (PPA) signed on January 24, 2012, between SEL and NVVNL, under which SEL was obligated to commission 20 MW of solar power by February 26, 2013. However, SEL only commissioned 10 MW after a two-month delay and the remaining 10 MW after five months, leading NVVNL to invoke Clause 4.6 of the PPA and initiate arbitration proceedings for liquidated damages.

Noting that the delay was admitted, the Supreme Court categorically held,

“Clause 4.6 of the PPA that provides for liquidated damages for delay in commencement of supply of power gets attracted.”

The Arbitral Tribunal, in a split award, had awarded only ₹1.2 crores. This was substantially modified by the Delhi High Court’s Single Judge under Section 34 of the Arbitration and Conciliation Act, 1996, who granted ₹27.06 crores, amounting to 50% of the liquidated damages stipulated in Clause 4.6, to be recovered monthly from SEL’s sale proceeds.

“Proof of Actual Loss Not Necessary in Public Utility Contracts”: Supreme Court Reaffirms Public Interest Exception Under Section 74

Rejecting SEL’s contention that NVVNL was not entitled to liquidated damages in the absence of evidence of actual loss, the Supreme Court upheld the public interest character of the JNNSM scheme.

“The PPA… was entered into for the purpose of enabling the sale of bundled up power… This activity was definitely in public interest and with a view to promote green energy.”

The Court held that Section 74 of the Indian Contract Act, 1872, which permits recovery of reasonable compensation even without proof of actual loss, applies squarely in such public utility contexts.
Referring to the binding precedent in Construction and Design Services v. DDA, the Court reiterated,

“In such cases, the burden would be on the party committing the breach to show that no loss was caused by the delay or that the amount stipulated as liquidated damages was in the nature of penalty.”

The attempt by SEL to distinguish the public character of the contract was categorically dismissed. “The commissioning of the solar plant by SEL was with a view to satisfy and take the solar mission forward. This activity involves public interest and the environment at large.”

“Courts Can Modify Awards Under Section 34 Without Rewriting the Merits”: Supreme Court Backs Limited Judicial Power

On the issue of whether the Section 34 court had the jurisdiction to modify the arbitral award, the Supreme Court referred to its Constitution Bench ruling in Gayatri Balasamy v. ISG Novasoft Technologies Ltd. and decisively held:

“The modification was only with a view to apply Clause 4.6.2 of the PPA to the facts of the case… not a jurisdictional error.”

Dismissing SEL’s claim that courts could only set aside and not modify awards, the Bench observed,

“To deny courts the authority to modify an award—particularly when such a denial would impose significant hardships, escalate costs, and lead to unnecessary delays—would defeat the raison d'être of arbitration.”

The Court clarified that the Single Judge had not re-appreciated evidence, but merely applied the contractually agreed formula under Clause 4.6 to determine reasonable compensation.

“Section 37 Is Not a Forum for Reworking Compensation Already Decided”: Division Bench Faulted for Excess of Jurisdiction

The Supreme Court held that the Delhi High Court’s Division Bench had exceeded its jurisdiction under Section 37 when it reduced the compensation to ₹20.70 crores by recalculating damages based on its own interpretation of delay metrics.

“The modification in the amount of reasonable compensation by the Division Bench is merely a substitution of its view in place of the plausible view taken by the learned Single Judge. Such course… would be beyond the scope of Section 37.”

Citing its own decision in AC Chokshi Share Broker Pvt. Ltd. v. Jatin Pratap Desai, the Court reiterated:

“The Section 37 court must only determine whether the Section 34 Court had exercised its jurisdiction properly and rightly, without exceeding its scope.”

Since the Single Judge had computed the liquidated damages strictly under Clause 4.6, and awarded 50% as a discretionary measure, there was no perversity or arbitrariness that would warrant interference.

“A Commercial Contract Serving Public Purpose Is Not Just a Private Bargain”: Supreme Court Clarifies the Interplay Between Contractual Freedom and Public Duty

In what will likely become a key precedent for renewable energy contracts, infrastructure projects, and public-private partnerships, the Court made a broader observation:

“A person who enters into a contract with Government does not necessarily thereby undertake any public duty… but in cases like the present, the entire project is rooted in public interest, and default undermines that very purpose.”

The Court reminded parties dealing with public infrastructure:

“Having agreed to incorporate Clause 4.6 in the PPA, SEL cannot now contend that NVVNL had failed to prove exact loss. The right to reasonable compensation flows from the agreement itself.”

The Supreme Court allowed NVVNL’s appeals, dismissed SEL’s appeals, and restored the judgment of the Single Judge awarding ₹27.06 crores as liquidated damages, with monthly recovery from SEL’s earnings. No costs were awarded.

Date of Decision: January 30, 2026

Latest Legal News