Motor Accident Claim Maintainable Despite Compensation Under Workmen’s Compensation Act – Insurer Liable Despite Fake Licence Allegation: Gujarat High Court Review Is Not a Second Round of Litigation: Orissa High Court Dismisses Plea Seeking Reconsideration of Dropped Contempt in MCL Appointment Case Fresh Ex Parte Relief Cannot Bypass Order 39 Rule 3 – Restoration of Electricity Refused for Tenant Running Cold Storage: Punjab & Haryana High Court Section 498A IPC | Telling Her To Indulge In Prostitution For Dowry Is Most Obnoxious Form Of Harassment: Jharkhand High Court Search Can’t Stretch Time: Gujarat High Court Quashes Income Tax Reopening Beyond 10-Year Limit in Search-Based Reassessment 138 NI Act | Mere Claim of ‘Security Cheque’ No Defence Against Statutory Presumption : Calcutta High Court Rigour of Section 37 NDPS Act Cannot Be Diluted by Bail Pleas Citing Delay or Procedural Defects: Punjab & Haryana High Court Denies Bail in Heroin Recovery Case If Arbitration Clause Itself Bars Larger Claims, Court Cannot Appoint Arbitrator: Bombay High Court Dismisses Section 11 Application Once Arbitration Clause Exists and Proceedings Are Ongoing, Civil Court Must Step Back: Andhra Pradesh High Court Dismisses Suit for Injunction in Partnership Dispute Autonomy of Private Schools Can't Be Crushed in the Name of Fee Regulation: J&K High Court Strikes Down FFRC Chairperson Clause, Upholds Fee Control Law with Caveats Demand and Acceptance of Bribe Must Be Proved as a Fact – Mere Possession of Money Not Enough: Kerala High Court Recovery Alone Can't Prove Bribery Where Legal Fee Is Established Through Official Records: Punjab & Haryana High Court Acquits Patwari Exoneration on Technical Grounds Can’t Quash Criminal Prosecution for Tax Evasion: Kerala High Court Denies Relief to Doctor Accused of Concealment Answer To A Leading Question Cannot Be Sole Basis For Conviction In Serious Offences Like Rape: Bombay High Court NDPS | Mere Absence of Contraband No Ground for Bail When Recovery from Co-Accused Points to Coordinated Drug Network: Punjab & Haryana High Court Allahabad High Court Quashes Ceiling Surplus Land Order Passed Without Spot Inspection, Ignores Rights Acquired Through Adverse Possession Civil Death Cannot Be the Price of Past Mistakes: Orissa High Court Strikes Down Blanket Tender Ban on Previously Blacklisted Bidders Once Supreme Court Cancels Bail for Violation, Subordinate Courts Cannot Reconsider: Karnataka High Court Non-joinder Is a Curable Defect, Not a Death Blow to Appeal: Madhya Pradesh High Court Restores Mutation Appeal Stale Allegations and Closed FIRs Cannot Justify Preventive Detention: J&K High Court Quashes PSA Detention Order for Lack of Proximate Link Employment-Related Separation Cannot Be Labelled as Desertion: Jharkhand High Court Dismisses Husband’s Divorce Appeal “Fair Pre-Estimate” of Damages Valid Even Without Proof of Loss: Delhi High Court Partly Sets Aside Arbitral Award in Carlsberg Dispute Or 39 CPC | Unregistered Will With Single Attesting Witness Cannot Confer Absolute Title: Delhi High Court Grants Injunction Failure To Comply With Mandatory Rent Deposit Directions Under WBPTA Will Invite Striking Off of Tenant’s Defence, Even For Single Default: Calcutta High Court Insistence on Impossible Term Reflects Absence of Readiness: Bombay High Court Denies Specific Performance for Delay and Inflexibility Medical Negligence | Stem Cell Therapy for Autism Is Not Valid Medical Practice: Supreme Court Declares Commercial Use as Medical Negligence Stem Cells Are ‘Drugs’ Under Law, Not Medical Procedures”: Supreme Court Brings Stem Cell Therapy Back Under Drugs Act NGT Can Impose Compensation Without Statutory Formula, Guided By Polluter Pays Principle: Supreme Court Upholds Environmental Penalties On Builders Environmental Compensation Must Not Be Illusory: Supreme Court Upholds NGT’s ₹5 Crore Penalty On Builder For Violating Environmental Laws Section 34 Court Has Limited Power to Modify Arbitral Award — But It Exists: Supreme Court Endorses Judicial Calibration of Damages in Arbitration Delay in Public Utility Projects Is Per Se a Loss: Supreme Court Upholds ₹27 Crore Damages Against Solar Developer Article 21 | Menstrual Health is an Integral Facet of Right to Life & Dignity: Supreme Court RTE Act | Free Sanitary Pads, Vending Machines & Separate Toilets Mandatory for All Schools: Supreme Court Issues Continuing Mandamus No Waiver of Fundamental Rights by Signing a Job Contract: Supreme Court Declares Contractual Clauses Barring Regularization Unenforceable When the State is the Lion, the Employee Cannot Be the Lamb Forever: Supreme Court Slams Jharkhand for Exploiting Contractual Engineers for a Decade Bail Once Granted Should Not Be Cancelled Lightly: Supreme Court Refuses to Revoke Bail of Accused in Daylight Murder Case A Decade of Targeted Persecution Cannot Be Cloaked as Procedure: Supreme Court Slams Department for Systematic Denial of ITAT Appointment Even Presence Of A Single Biased Member Vitiates  Selection Process: Supreme Court Nullifies ITAT Appointment Panel Over Bias Concerns Court Can Prevent Institutional Vacuum Despite Invalid Appointment: Supreme Court Invokes Article 142 to Protect Tenure of Vice-Chancellor in Exceptional Circumstances State Cannot Override Higher Education Standards Set by Parliament: Supreme Court Declares Puducherry VC Appointment Illegal, Upholds Primacy of UGC Regulations

Section 34 Court Has Limited Power to Modify Arbitral Award — But It Exists: Supreme Court Endorses Judicial Calibration of Damages in Arbitration

31 January 2026 1:16 PM

By: sayum


“Modification of Arbitral Award Within Contractual Boundaries Is Not Judicial Overreach”, In a significant reaffirmation of the evolving jurisprudence on judicial intervention in arbitral awards, the Supreme Court of India clarified that while courts do not sit in appeal over arbitral awards, Section 34 of the Arbitration and Conciliation Act, 1996 does permit a limited power of modification — provided such intervention is narrowly tailored, principled, and consistent with the terms of the contract.

“We are of the opinion that the Section 34 Court can apply the doctrine of severability and modify a portion of the award while retaining the rest,” the Supreme Court held, applying the principles laid down in the 2025 Constitution Bench decision in Gayatri Balasamy v. ISG Novasoft Technologies Ltd.

The Court was dealing with a challenge to an arbitral award arising from delays in the commissioning of a solar power plant under a Power Purchase Agreement (PPA) executed under the Jawaharlal Nehru National Solar Mission (JNNSM).

“Judicial Intervention Is Legitimate When It Furthers the Ends of Justice”: Supreme Court Clarifies Section 34 Purpose

The core legal dispute revolved around the extent to which a court exercising jurisdiction under Section 34 can go in altering an arbitral award. In this case, the Arbitral Tribunal by majority awarded only ₹1.2 crores as damages to NTPC Vidyut Vyapar Nigam Ltd. (NVVNL), despite admitted delay in project commissioning by M/s Saisudhir Energy Ltd. (SEL).

The Delhi High Court’s Single Judge interfered with the award, observing that the damages awarded were disproportionately low given the contractual formula under Clause 4.6 of the PPA. Exercising what it termed a “reasonable compensation” standard, the court modified the award and granted ₹27.06 crores, amounting to 50% of the pre-estimated damages.

This was challenged by SEL on the ground that Section 34 permits only setting aside of awards, not modification.

Rejecting this contention, the Supreme Court categorically held:

“The modification is in exercise of jurisdiction under Section 34… without undertaking any examination of the merits of the dispute.”

It clarified that where a part of the arbitral award deviates from the fundamental policy of Indian law or ignores material contractual provisions, courts are not helpless.

“To Deny Courts the Authority to Modify Would Defeat the Raison d’être of Arbitration”: Supreme Court Warns Against Mechanical Interpretation

Relying on Gayatri Balasamy, the Bench consisting of Justice P.S. Narasimha and Justice Atul S. Chandurkar observed:

“If we were to decide that courts can only set aside and not modify awards, then the parties would be compelled to undergo an extra round of arbitration… This would render the arbitration process more cumbersome than even traditional litigation.”

The Court noted that Section 34 does not expressly prohibit modification and should be interpreted purposively:

“The power cannot contradict the essence or language of Section 34. The court would not exercise appellate power… but a nuanced and limited power of modification remains available.”

In other words, the judiciary is not rewriting the contract, but realigning the award with the contract, particularly when the award undermines agreed terms or results in manifest injustice.

“Majority Award Granting ₹1.2 Crores Was a Perversion of Clause 4.6”: Court Found Justification for Modification

The Supreme Court noted that Clause 4.6.2 of the PPA had a clear formula for computing liquidated damages at ₹1,00,000 per MW per day of delay. Given that SEL had admitted to delays ranging from two to five months, the Tribunal’s award of ₹1.2 crores was held to be incongruent with the contractual scheme.

“The learned Single Judge having determined the amount of reasonable compensation by relying upon Clause 4.6 of the PPA and thereafter awarding 50% of such amount… no interference with such determination was called for.”

The Court agreed that while courts cannot re-evaluate evidence, they can apply the contract to undisputed facts, which in this case included admitted delays and the existence of a liquidated damages clause.

“Section 37 Is Not an Avenue for Substitution of Views”: Apex Court Restricts Appellate Interference in Modified Awards

The judgment also addressed the Division Bench’s interference under Section 37, which had reduced the damages from ₹27.06 crores to ₹20.70 crores by reworking the calculation method. The Supreme Court was clear:

“Such a course of taking a different view… would be beyond the scope of Section 37 of the Act of 1996.”

The Court explained that unless the Section 34 court’s decision is shown to be perverse, arbitrary, or ultra vires the contract, the appellate court has no jurisdiction to substitute its reasoning or re-calculate figures.

Striking the Balance Between Arbitral Finality and Contractual Fidelity

This judgment contributes significantly to Indian arbitration law by carving out a middle ground: arbitration must be respected, but not at the cost of contractual sanctity or legal reasonableness.

The Court's holding can be summed up as follows:

“The power of judicial review under Section 34… includes a limited power to modify the award within the confines of Section 34.”

The ruling is particularly relevant in the context of public-private contracts, where strict enforcement of agreed clauses, balanced with judicial calibration, is critical to maintaining fairness, certainty, and rule of law.

The Supreme Court upheld the ₹27.06 crore compensation awarded by the Single Judge, dismissed SEL’s objection to the modification under Section 34, and held that the limited judicial power to modify an award is essential to maintain faith in arbitration while ensuring justice.

Date of Decision: January 30, 2026

 

Latest Legal News