Motor Accident Claim Maintainable Despite Compensation Under Workmen’s Compensation Act – Insurer Liable Despite Fake Licence Allegation: Gujarat High Court Review Is Not a Second Round of Litigation: Orissa High Court Dismisses Plea Seeking Reconsideration of Dropped Contempt in MCL Appointment Case Fresh Ex Parte Relief Cannot Bypass Order 39 Rule 3 – Restoration of Electricity Refused for Tenant Running Cold Storage: Punjab & Haryana High Court Section 498A IPC | Telling Her To Indulge In Prostitution For Dowry Is Most Obnoxious Form Of Harassment: Jharkhand High Court Search Can’t Stretch Time: Gujarat High Court Quashes Income Tax Reopening Beyond 10-Year Limit in Search-Based Reassessment 138 NI Act | Mere Claim of ‘Security Cheque’ No Defence Against Statutory Presumption : Calcutta High Court Rigour of Section 37 NDPS Act Cannot Be Diluted by Bail Pleas Citing Delay or Procedural Defects: Punjab & Haryana High Court Denies Bail in Heroin Recovery Case If Arbitration Clause Itself Bars Larger Claims, Court Cannot Appoint Arbitrator: Bombay High Court Dismisses Section 11 Application Once Arbitration Clause Exists and Proceedings Are Ongoing, Civil Court Must Step Back: Andhra Pradesh High Court Dismisses Suit for Injunction in Partnership Dispute Autonomy of Private Schools Can't Be Crushed in the Name of Fee Regulation: J&K High Court Strikes Down FFRC Chairperson Clause, Upholds Fee Control Law with Caveats Demand and Acceptance of Bribe Must Be Proved as a Fact – Mere Possession of Money Not Enough: Kerala High Court Recovery Alone Can't Prove Bribery Where Legal Fee Is Established Through Official Records: Punjab & Haryana High Court Acquits Patwari Exoneration on Technical Grounds Can’t Quash Criminal Prosecution for Tax Evasion: Kerala High Court Denies Relief to Doctor Accused of Concealment Answer To A Leading Question Cannot Be Sole Basis For Conviction In Serious Offences Like Rape: Bombay High Court NDPS | Mere Absence of Contraband No Ground for Bail When Recovery from Co-Accused Points to Coordinated Drug Network: Punjab & Haryana High Court Allahabad High Court Quashes Ceiling Surplus Land Order Passed Without Spot Inspection, Ignores Rights Acquired Through Adverse Possession Civil Death Cannot Be the Price of Past Mistakes: Orissa High Court Strikes Down Blanket Tender Ban on Previously Blacklisted Bidders Once Supreme Court Cancels Bail for Violation, Subordinate Courts Cannot Reconsider: Karnataka High Court Non-joinder Is a Curable Defect, Not a Death Blow to Appeal: Madhya Pradesh High Court Restores Mutation Appeal Stale Allegations and Closed FIRs Cannot Justify Preventive Detention: J&K High Court Quashes PSA Detention Order for Lack of Proximate Link Employment-Related Separation Cannot Be Labelled as Desertion: Jharkhand High Court Dismisses Husband’s Divorce Appeal “Fair Pre-Estimate” of Damages Valid Even Without Proof of Loss: Delhi High Court Partly Sets Aside Arbitral Award in Carlsberg Dispute Or 39 CPC | Unregistered Will With Single Attesting Witness Cannot Confer Absolute Title: Delhi High Court Grants Injunction Failure To Comply With Mandatory Rent Deposit Directions Under WBPTA Will Invite Striking Off of Tenant’s Defence, Even For Single Default: Calcutta High Court Insistence on Impossible Term Reflects Absence of Readiness: Bombay High Court Denies Specific Performance for Delay and Inflexibility Medical Negligence | Stem Cell Therapy for Autism Is Not Valid Medical Practice: Supreme Court Declares Commercial Use as Medical Negligence Stem Cells Are ‘Drugs’ Under Law, Not Medical Procedures”: Supreme Court Brings Stem Cell Therapy Back Under Drugs Act NGT Can Impose Compensation Without Statutory Formula, Guided By Polluter Pays Principle: Supreme Court Upholds Environmental Penalties On Builders Environmental Compensation Must Not Be Illusory: Supreme Court Upholds NGT’s ₹5 Crore Penalty On Builder For Violating Environmental Laws Section 34 Court Has Limited Power to Modify Arbitral Award — But It Exists: Supreme Court Endorses Judicial Calibration of Damages in Arbitration Delay in Public Utility Projects Is Per Se a Loss: Supreme Court Upholds ₹27 Crore Damages Against Solar Developer Article 21 | Menstrual Health is an Integral Facet of Right to Life & Dignity: Supreme Court RTE Act | Free Sanitary Pads, Vending Machines & Separate Toilets Mandatory for All Schools: Supreme Court Issues Continuing Mandamus No Waiver of Fundamental Rights by Signing a Job Contract: Supreme Court Declares Contractual Clauses Barring Regularization Unenforceable When the State is the Lion, the Employee Cannot Be the Lamb Forever: Supreme Court Slams Jharkhand for Exploiting Contractual Engineers for a Decade Bail Once Granted Should Not Be Cancelled Lightly: Supreme Court Refuses to Revoke Bail of Accused in Daylight Murder Case A Decade of Targeted Persecution Cannot Be Cloaked as Procedure: Supreme Court Slams Department for Systematic Denial of ITAT Appointment Even Presence Of A Single Biased Member Vitiates  Selection Process: Supreme Court Nullifies ITAT Appointment Panel Over Bias Concerns Court Can Prevent Institutional Vacuum Despite Invalid Appointment: Supreme Court Invokes Article 142 to Protect Tenure of Vice-Chancellor in Exceptional Circumstances State Cannot Override Higher Education Standards Set by Parliament: Supreme Court Declares Puducherry VC Appointment Illegal, Upholds Primacy of UGC Regulations

NGT Can Impose Compensation Without Statutory Formula, Guided By Polluter Pays Principle: Supreme Court Upholds Environmental Penalties On Builders

31 January 2026 1:15 PM

By: sayum


“Project Cost or Turnover Can Be A Valid Yardstick – Law Doesn’t Require Mathematical Formula For Environmental Damage”, In a landmark decision strengthening environmental jurisprudence, the Supreme Court upheld the National Green Tribunal’s power to impose environmental compensation on errant builders even in the absence of a statutory formula, holding that discretion under the NGT Act must be exercised in line with constitutional principles and judicial reasoning.

The Court dismissed two civil appeals filed by real estate developers—M/s. Rhythm County and M/s. Keystone Properties—who had challenged penalties of ₹5 crores and ₹4.47 crores respectively imposed by the NGT for undertaking large-scale construction in Pune without mandatory environmental clearances and continuing operations despite regulatory stop-work orders.

Delivering a detailed 75-page judgment, the Bench comprising Justice Dipankar Datta and Justice Vijay Bishnoi ruled that the NGT is legally empowered to enhance or quantify environmental compensation based on the economic scale of the project, including its cost or turnover, as long as such yardsticks are applied reasonably and proportionately.

No Straightjacket Formula Needed To Enforce Environmental Accountability

The Supreme Court firmly rejected the contention that the NGT lacked jurisdiction to quantify compensation in the absence of codified rules or delegated legislation.

“The appellants’ arguments that the NGT is denuded of authority to quantify compensation in the absence of a legislatively prescribed formula… falters when tested against the plain statutory text,” the Court observed, invoking Sections 15 and 20 of the National Green Tribunal Act, 2010.

The Court reminded that the NGT is guided by broader constitutional principles of environmental justice, especially the ‘polluter pays’, ‘sustainable development’ and ‘precautionary’ principles, all explicitly codified in Section 20 of the NGT Act.

“Environmental compensation must rest on a foundation of rationality, proportionality and reasoned assessment. The NGT’s powers are wide, flexible and principle-oriented.”

The Court held that rigid formulas were neither necessary nor appropriate in the field of environmental regulation, which often requires expert evaluation and flexible remedies tailored to individual cases.

Builders Cannot Claim Immunity Just Because Exact Harm Is Hard To Measure

The judgment addressed an important and recurring defence taken by real estate developers: that unless direct, measurable environmental harm is proven, no compensation can be levied.

“To say that mere violation of the law in not observing the norms would result in degradation of environment would not be correct,” the developers had argued, citing Deepak Nitrite Ltd. v. State of Gujarat.

However, the Court categorically clarified:

“Such a submission is fallacious. Environmental harm is not always measurable in laboratory terms. Violation of mandatory safeguards, especially continued construction without consent-to-establish or operate, itself triggers the application of the ‘polluter pays’ principle.”

The Court emphasised that the scale of operations—i.e., the project's total cost or revenue—could justifiably be taken as a proxy for environmental impact, especially in urban construction zones where the stress on air, water, waste and traffic systems is high.

“Linking scale to impact sends a message that bigger players need to play by greener rules,” the Court said.

CPCB Guidelines Not Binding, But Can Be Used When Applied Rationally

One of the contentious issues in the appeals was the use of Central Pollution Control Board (CPCB) guidelines for computing environmental compensation, which had been employed by the NGT in the Keystone case.

The developers argued that these guidelines were designed for polluting industrial units—not residential projects—and lacked statutory backing.

While accepting that the CPCB formula is not mandatory, the Court held:

“The CPCB framework operates as a facilitative and indicative tool, not a rigid or exhaustive code… The NGT remains empowered to adopt such scientifically informed mechanisms while applying its independent mind.”

The Court distinguished the present case from Benzo Chem Industrial Pvt. Ltd., where the NGT had imposed arbitrary penalties based on unverifiable turnover estimates. In contrast, the current case involved verified material, expert reports, site inspections, and considered hearings.

Judicial Independence and Expert Committees: No Abdication of Adjudicatory Role

Another key issue was whether the NGT had “outsourced” its decision-making to expert committees. The developers alleged that the NGT merely rubber-stamped Joint Committee reports.

The Court decisively rejected this:

“To characterise the NGT’s exercise as abdication would be to conflate reliance on technical assistance with absence of independent application of mind—a proposition that finds no support either in law or on the facts of the present case.”

In Rhythm’s case, the NGT consciously enhanced the recommended compensation from ₹2.39 crores to ₹5 crores based on project cost of ₹335 crores, applying the principle laid down in Goel Ganga Developers v. Union of India, where 5% of project cost was upheld as a general benchmark.

In Keystone’s case, the NGT distinguished between regularised violations and separate infractions of continuing work without consent and occupancy without clearances—awarding ₹4.47 crores using a computation methodology that was transparently reasoned.

Builders Must Bear Responsibility For Breach Of Environmental Norms, Regardless Of Subsequent Regularisation

The Supreme Court was clear that post-facto approvals under violation windows or conditional environmental clearances do not whitewash prior breaches.

In Keystone’s case, although a one-time violation window EC was obtained in 2020, the Court noted:

“Construction without CTE from 2013 to 2020, continuation of work during closure directions, and handover of possession without CTO—these constitute distinct and serious statutory violations.”

The NGT was justified in treating these as independent infractions deserving separate compensation.

Similarly, in Rhythm’s case, despite later compliance and regularisation, the Court noted that construction continued in violation of a stop-work notice, and that clubhouses and buildings had been raised beyond sanctioned limits.

A Resounding Endorsement of NGT’s Role and the Principle of Environmental Accountability

Upholding both NGT orders in full, the Supreme Court held:

“We find no ground to interfere with the impugned computation of environmental compensation in both appeals… The NGT proceeded on contemporaneous material, expert inputs, and applied its independent mind in a manner consistent with the polluter pays principle.”

The Court extended the time for payment of compensation by three months and ordered that parties bear their own costs.

This ruling is expected to have far-reaching consequences in shaping environmental accountability in the real estate and infrastructure sectors and affirms the NGT’s central role in enforcing non-negotiable environmental safeguards.

Date of Decision: January 30, 2026

 

Latest Legal News