Summoning Accused A Serious Matter, Vexatious Proceedings Must Be Weeded Out: Calcutta High Court Quashes 'Counterblast' Complaint Lessee Mutating Own Name As Owner & Mortgaging Property Amounts To Denial Of Title Leading To Lease Forfeiture: Bombay High Court Tenant Has No Indefeasible Right To Insist On Separate Trial Of Maintainability Objections In Summary Rent Proceedings: Allahabad High Court Morality Must Be Kept Separate From Offence While Dealing With Individual's Liberty: Delhi High Court Grants Bail To Gym Trainer In Rape Case Parking Truck On Highway At Night Without Indicators Is Gross Violation Of MV Act; Driver Solely Negligent For Accident: Gujarat High Court Injured Eyewitness Testimony Carries 'Built-In Guarantee' Of Presence: Jharkhand High Court Upholds Murder Conviction Despite Lack Of Independent Witnesses Rajasthan High Court Initiates Suo Motu Contempt Against Litigant & Driver For Unauthorised Recording Of Court Proceedings On Mobile Phone General Apprehension Of Weapon Snatching By Maoists Not A Ground To Refuse Arms License Renewal To Law-Abiding Citizen: Telangana High Court Plaint Cannot Be Rejected Under Order VII Rule 11 If Authority To Sue Is A Disputed Fact; Undervaluation Is A Curable Defect: Uttarakhand High Court Vacancies Arising Under Repealed Rules Don't Confer Vested Right To Promotion; Candidate Governed By 'Rule In Force': Supreme Court No Need For Fresh Final Decree Application To Execute Auction If Preliminary Decree Already Determines Mode Of Division: Supreme Court Partition Suit: Supreme Court Sets Aside HC Order Staying Execution, Says Preliminary Decree Can Be Executable If It Determines Mode Of Partition 3-Judge Bench Ratio In 'K.A. Najeeb' Cannot Be Diluted By Smaller Benches To Deny UAPA Bail: Supreme Court 'Bail Is Rule, Jail Exception' Applies Even Under UAPA; Section 43-D(5) Is Subordinate To Article 21: Supreme Court Section 304-A IPC: Supreme Court Extends Benefit Of Probation Of Offenders Act To Driver, Orders Release After Admonition Upon Payment Of ₹5 Lakh Compensation Section 304-A IPC: Supreme Court Grants Probation To Driver, Says Conviction Under Probation Of Offenders Act Won't Affect Service Career Intermittent Daily Wage Earnings Not 'Gainful Employment' Under Section 17-B ID Act: Delhi High Court

Sole Liability Falls on Lead Developer Under Connection Agreement; No Privity Exists With Co-Generators: Supreme Court Clarifies Contractual Obligations in Bay Cost Dispute

19 May 2025 1:24 PM

By: sayum


“Doctrine of Privity Must Prevail – A Party Cannot Be Made Liable Without Being a Signatory to the Contract”: - In a landmark decision Supreme Court of India ruled in favour of HP Power Transmission Corporation Ltd. (HPPTC Ltd.) in a contractual dispute involving shared transmission infrastructure. The Court overturned the Appellate Tribunal for Electricity’s (APTEL) judgment, restoring the decision of the Himachal Pradesh Electricity Regulatory Commission (State Commission) which had held M/s Brua Hydrowatt Pvt. Ltd. (BHP Ltd.) solely liable for the construction cost of a 66kV Bay at Urni.

“This Court cannot dilute the doctrine of privity merely because the performance of a contract benefits third parties,” observed a Bench comprising Justices Abhay S. Oka and Augustine George Masih, emphatically reiterating the importance of contract law fundamentals in infrastructure and energy sector agreements.

The case arose from a transmission infrastructure agreement between HPPTC Ltd. and BHP Ltd., who was developing the Brua Hydro Electric Project along with two other private generators: Darjeeling Power Pvt. Ltd. and Roura Non-Conventional Energy Pvt. Ltd..

Initially, the power evacuation was to occur via a 33kV line at Karcham but was later rerouted to a jointly-used 66kV Bay at Urni, constructed by HPPTC Ltd. A Connection Agreement (CA) was signed on 02.07.2021 exclusively between HPPTC Ltd. and BHP Ltd., designating the latter as the sole applicant.

Though the three generating companies had earlier entered into an Internal Tripartite Agreement (ITA) on 27.12.2019 for sharing Bay costs, HPPTC Ltd. was not a party to this agreement. When HPPTC Ltd. raised a demand of ₹3.42 crore towards Bay construction, BHP Ltd. sought to divide the cost, which HPPTC Ltd. rejected.

The State Commission, in its order dated 27.12.2022, upheld the demand against BHP Ltd., noting its lead role and exclusive contractual responsibility. On appeal, APTEL reversed the ruling on 17.03.2023, holding that costs should be shared. This prompted HPPTC Ltd. to approach the Supreme Court.

“Contractual Privity Is Not a Mere Technicality but the Foundation of Enforceable Obligations”

The Supreme Court examined the Connection Agreement (CA) dated 02.07.2021, particularly Clause 2, which details payment liabilities for construction, operation and maintenance of Bay infrastructure.

“The applicant shall pay charges to the STU on mutually agreed terms,” reads Clause 2.4, with “applicant” being BHP Ltd. alone.

The Court decisively held:

“These terms make it clear that the sole liability was that of BHP Ltd., not only in its individual capacity but also on behalf of Respondent No. 2 and Respondent No. 3.”

The Bench emphasized that the other generators—Darjeeling Power and Roura Energy—were not signatories to the CA and hence not contractually bound to HPPTC Ltd.

“HPPTC Cannot Enforce a Private Internal Arrangement It Was Not Party To”

BHP Ltd. argued that the Internal Tripartite Agreement (ITA) established shared responsibility among the three generators. The Supreme Court rejected this, stating:

“The HPPTC Ltd… cannot place reliance on the said ITA for its benefit without being a party therein… nor does it govern the payment of Bay charges.”

Reinforcing this, the Court invoked the Doctrine of Privity, citing Tweddle v. Atkinson (1861) and the Indian precedent in Essar Oil Ltd. v. Hindustan Shipyard Ltd. (2015):

“If the contentions of BHP Ltd. are accepted, HPPTC Ltd. would technically have no legal remedy to recover its dues or charges from Respondent No. 2 and 3, as they are not under any contractual obligation.”

“Lead Developer Must Bear Liability and Recover Internally”

The Court recognized the internal arrangement among the three generators but maintained it was irrelevant to HPPTC Ltd.’s rights:

“BHP Ltd. had taken up the responsibility to be the joint nominee… and thereafter recover the proportionate amount… from the other two generating companies.”

It concluded that:

“The right, if any, of claim and recovery… from Respondent No. 2 and 3 would be only with BHP Ltd. The HPPTC Ltd. has rightly put forth its claim to BHP Ltd.”

The Court restored the State Commission’s order dated 27.12.2022, holding BHP Ltd. solely responsible for:

  • Construction cost of Bay: ₹3.42 crore

  • Operation and Maintenance Charges

  • Compliance with Connection Agreement obligations

The Supreme Court declared the APTEL judgment unsustainable, observing:

“The Impugned Judgment of the APTEL is based upon wrong assumptions and misreading of the terms of agreement ignoring the basic principle that a party not privy to the agreement cannot be made liable.”

The appeal by HPPTC Ltd. was allowed, and the APTEL’s ruling was set aside.

 

The Supreme Court’s decision affirms a vital tenet of contract law: “Only parties to a contract can enforce or be held accountable under it.” It sends a clear message to infrastructure and energy sector stakeholders to ensure precise and inclusive drafting of contracts, particularly when joint use or shared facilities are involved.

In a sector increasingly reliant on collaborative development, the ruling underscores the risks of informal or internal agreements without ensuring proper contractual safeguards with third parties.

Date of Decision: May 14, 2025

 

Latest Legal News