Mere Absence of Landowners’ Signatures on MOU Not Fatal When They Received Benefits Under Agreement: Bombay High Court Grants Injunction in Specific Performance Suit Involving Pre-Allotment Sale Election Certificate Has No Legal Sanctity Under Societies Act; Authority To Function Flows Only From Registered List Under Section 4(1): Allahabad High Court Silence After Legal Notice Fatal: Andhra Pradesh High Court Upholds Decree for Specific Performance Despite Allegation of Loan Transaction State Cannot Hijack Compensation for National Highways – Only Centre Can Decide Multiplier: Bombay High Court Quashes Maharashtra’s Attempt to Dilute Landowners’ Rights Recognition Of Trade Unions Is Not A Fundamental Right: Calcutta High Court Rejects Writ Seeking Bargaining Status Without Approaching Registrar Economic Offences Are Not Trivial Disputes—They Threaten National Integrity: Delhi High Court Rejects Anticipatory Bail in ₹65 Crore Crypto-Laundering Cyber Scam State Cannot Rewrite Recruitment Rules: Gujarat High Court Slams Denial of Applications Based on Misreading of Experience Requirement for Head Teacher Post Sanction Once Refused Under PC Act Cannot Be Overruled by Another Authority: Madhya Pradesh High Court Lex Non Cogit Ad Impossibilia – Law Does Not Compel Performance of Impossibility: Orissa High Court Quashes Rejection of Contractor's Claim for Price Escalation Due to Quarry Closure Uniformity in Compensation Must Prevail: Once Market Value Fixed by Common Judgment, It Can't Be Reopened or Reduced: Madras High Court Section 223 BNSS | Notice to Accused Only After Complainant's Oath: Gauhati High Court Clarifies New BNSS Mandate Nationality Alone Cannot Deny Bail: Karnataka High Court Grants Bail to Bangladeshi National Accused of Forged Passport and Aadhaar Creation Sole Eyewitness Not of “Sterling Quality”, Medical Evidence Contradicts Ocular Version: Kerala High Court Acquits Accused in 2015 Thodupuzha Murder Case Failure to Prove Victim's Age and Delay in FIR Fatal to Prosecution Under POCSO Act: Madras High Court Acquits Director Cannot Be Prosecuted Without Making Company an Accused: Calcutta High Court Failure to Explain Possession of Looted Items Strengthens Inference of Guilt: Calcutta High Court Upholds Life Sentence in Double Murder Dacoity Case Once Common Object to Commit Murder is Established, Individual Role Becomes Irrelevant: Allahabad High Court Plea of Non-Service Cannot Override Statutory Limitation When Dealer Sleeps Over Rights: Andhra Pradesh High Court Writ Against VAT Appellate Rejection Mutation Proceedings Not the Forum to Undo a Civil Court Decree: Bombay High Court Slams Revenue Authorities for Deleting Mutation Despite Registered Consent Decree Interpretation of Contract Is For The Arbitrator To Decide Unless No Fair-Minded Person Could Accept That View: Delhi High Court Identification Must Be Beyond Doubt, Not Beyond Hope: Delhi High Court Acquits Man Convicted for Attempt to Murder Owner-Driver Accused in NDPS Case Can’t Seek Vehicle Custody Till Trial: MP High Court Declines Supurdnama Plea Discretionary Powers Cannot Be Invoked to Cure Litigant’s Lapses: Andhra Pradesh High Court Refuses Reopening of Evidence After 3-Year Delay Section 38-B Expressly Excludes Res Juicata; Past Findings Cannot Bar Re-Trial Under Amended Ceiling Law: Allahabad High Court Ceiling Law Can Revisit the Past: 1964 Discharge Not a Shield Against Mandatory Re-Determination: Allahabad High Court High Courts Can’t Pick and Choose from Precedents: Supreme Court Reiterates Binding Force of Constitution Bench in Motor Accident Compensation Future Prospects Are Not Charity, They Are Law: Supreme Court Enhances Fatal Accident Compensation, Rejects ‘Love and Affection’ as Separate Head No Estoppel Against Statute, No Equity Against Vesting: Supreme Court Rejects ‘Amicable Settlement’ to Undo Land Reform Vesting Power Of Review Is Not Inherent; Executive Directions Cannot Confer Jurisdiction: Supreme Court Strikes Down Four-Decade Review as Unconstitutional “Expertise Over Formal Titles: Supreme Court Strengthens Transgender Rights Advisory Committee, Adds CLPR Representative Data Needs Science, Not Guesswork:  Supreme Court Brings Former Chief Statistician into National Task Force Once Parity is Statutorily Guaranteed, Government Cannot Withdraw Benefits Through Executive Memos: Andhra Pradesh High Court Even A Single Crime Is Sufficient To Invoke Gangster Act: Allahabad High Court Upholds Proceedings Despite Challenge Based On Solitary Case Non-Consummation Can’t Be Raised As Afterthought To Defeat Maintenance:  Madras High Court Cuts Quantum But Upholds Wife & Child’s Right Failure to Examine Who Actually Weighed the Paddy is Fatal—Stock Discrepancy Alone Cannot Sustain Conviction: Calcutta High Court on Essential Commodities Act Prosecution Net Salary is Not the Sole Determinant — Deductions Can’t Defeat Maintenance Obligations: Andhra Pradesh High Court Clarifies in Maintenance Appeal Order 7 Rule 11 CPC | Mere Designation as Director Does Not Create Civil Liability: Bombay High Court Rejects Suit Against Nominee Directors Once Witnesses Admit Signing Blank Papers and No Actual Seizure Is Proved, Conviction Cannot Stand : Calcutta High Court Admissions Made in Cross-Examination Are the Best Evidence: Bombay High Court Baseless Allegations on Fidelity Justify Wife Living Separately – Maintenance Cannot Be Denied on Grounds of Character Attacks Unsubstantiated by Evidence: Andhra Pradesh High Court Once Delay Is Found Not Attributable To Contractor, Everything Else Must Fall: Bombay High Court Upholds Arbitral Award Against Solapur Municipal Corporation

Once Delay Is Found Not Attributable To Contractor, Everything Else Must Fall: Bombay High Court Upholds Arbitral Award Against Solapur Municipal Corporation

07 February 2026 12:51 PM

By: sayum


“Strangely enough, instead of extending the period of contract, the contract has been terminated after imposing penalties... The delay is solely attributable to the respondents and not to the claimant.” Bombay High Court

In a landmark judgment that reaffirms the sanctity of arbitral autonomy and the limited scope of judicial intervention, the Bombay High Court dismissed a challenge by the Solapur Municipal Corporation under Section 34 of the Arbitration and Conciliation Act, 1996, against an arbitral award that had granted over ₹32 crores in claims to a contractor joint venture.

Justice Sandeep V. Marne observed that once the arbitral tribunal had returned findings of no delay attributable to the contractor, the consequential imposition of penalties, termination of contract, and blacklisting orders stood automatically vitiated.

The Court’s 67-page judgment, delivered after a meticulous examination of the arbitral award and the 15 sub-heads of alleged delay, reiterates the well-established proposition that a Section 34 court is not an appellate forum and may only interfere where findings are perverse, based on no evidence, or defy logic to a degree that no fair-minded person would accept.

“Admissions by Municipal Officials in Cross-Examination are the Best Evidence”

The dispute arose out of a ₹212 crore sewerage treatment project undertaken by the S.M.C.-G.E.C.P. Ltd. Joint Venture, awarded by the Solapur Municipal Corporation under an agreement dated 2 January 2012. Following a series of penalties and a premature termination on 9 December 2013, the contractor was also blacklisted. The contractor invoked arbitration and was awarded ₹32.15 crores in claims, including certified unpaid bills, refund of security deposit, Local Body Tax (LBT), and damages for loss of profit on unexecuted work.

Justice Marne decisively upheld the award, noting that delay was the fulcrum of the case. “Once the JV is absolved of the allegations of delay,” he held, “the termination is automatically rendered invalid.”

Crucially, the Court noted that admissions made by municipal officers in cross-examination before the tribunal were not only binding but decisive. Refusing to accept the argument that the contractor was obliged to prove a negative (i.e., that it was not responsible for delays), the Court cited the law that “an admission is the best evidence that an opposing party can rely upon.”

“A Reasonable Expectation of Profit is Implicit in a Works Contract”

On the issue of damages, particularly the award of 10% of the unexecuted balance contract value as loss of profit, the Court made a crucial legal distinction:

“There is a marked difference between the concepts of ‘loss of profit’ and ‘loss of profitability’. The former claim arises from wrongful termination and does not require proof of actual loss.”

Justice Marne observed that where termination is unjustified, proof of loss through documentary evidence is not a prerequisite, and courts can adopt a broad evaluative approach. The Court found the arbitral tribunal’s approach not only legally sound but also conservative, noting that:

“Though the contract value was ₹212.52 crores, the Tribunal awarded damages based only on a reduced estimate of ₹140 crores, amounting to just 5.5% of the actual unexecuted value.”

“No Evidence of Delay by Contractor; Inaction Entirely Attributable to Municipal Corporation”

The Court painstakingly examined each of the 15 sub-heads of alleged delay—ranging from bhoomi poojan delays, land unavailability, delayed approvals, and lack of coordination between authorities—and upheld the arbitral findings in favour of the contractor on 14 of them.

In one emphatic passage, the Court remarked:

“What the Municipal Corporation has done is to merely issue letters to the Contractor accusing it of causing delay. However, when it came to leading evidence, no substantive proof was led.”

The Court highlighted admissions made by the Engineer-in-Charge, the Municipal Commissioner, and other witnesses, wherein they conceded key facts such as the absence of land acquisition, delayed approvals, and bureaucratic bottlenecks.

“The Tribunal Did Not Re-Write the Contract; It Interpreted It”

On the Corporation’s argument that the arbitral tribunal rewrote the contract by treating bhoomi poojan delay and bar chart approvals as significant, the Court made a clear legal distinction. It held that the Tribunal was entitled to interpret contract terms in light of actual conduct and documentary evidence, and such an interpretation was well within the scope of arbitral authority.

The judgment also noted that the Municipal Corporation failed to justify the blacklisting order, particularly as it was premised on delay, which had already been discredited. The Court agreed with the Tribunal’s conclusion that partial subcontracting was permissible under the contract, rejecting the claim that subcontracting amounted to misconduct.

“Certified RA Bills Cannot Be Withheld After Penalties Are Found Illegal”

The Court further upheld the tribunal’s award of ₹16.45 crores towards the final RA bill, noting that both the Project Management Consultant (Maharashtra Jeevan Pradhikaran) and the Municipal Corporation had accepted the certified amount of ₹19.25 crores. Deduction of VAT and TDS had already been accounted for.

With penalties now set aside, the withholding of RA bill payments stood on no legal footing, and the Court ruled that the Tribunal rightly awarded the sum.

Award Based on Evidence, No Patent Illegality or Perversity

Summing up the decision, Justice Marne held:

“The Award to my mind appears to be unexceptional... The Tribunal has awarded claims in a conservative and reasoned manner, based entirely on documentary evidence and admissions in cross-examination. No case is made out for interference under Section 34.”

The Court dismissed both Arbitration Petitions—the Municipal Corporation’s petition against the award, and the contractor’s limited challenge, which had not been pressed.

It also directed the return of Bank Guarantees furnished by the contractor and encashment of Bank Guarantees deposited by the Corporation. However, it stayed the directions regarding Bank Guarantees for eight weeks, giving time to appeal.

Date of Decision: 6 February 2026

Latest Legal News