Advocate Holding Vakalatnama Is Competent To Swear Affidavit: Andhra Pradesh High Court Restores Appeal Dismissed For Default Acid Attack Immediate And Proximate Cause Of Death: Allahabad High Court Upholds Conviction In Double Fatal Assault Three Handwriting Reports, Yet No Authorship Fixed: Calcutta High Court Quashes Forgery Case Against University Professor CBI Cannot Keep Searching for an Offender After Filing FIR: Bombay High Court Quashes ₹4760 Crore Loan Diversion Case Against GTL Limited Decision Based On Fake AI-Generated Judgments Is Misconduct, Not Mere Error: Supreme Court Flags Institutional Crisis Labour Court Cannot Sit As An Appellate Authority After Upholding Fair Inquiry: Delhi High Court Restores MTNL Driver’s Termination Administrative Lapse Cannot Rob In-Service Doctors of Reservation Rights: Karnataka High Court Orders First Preference in PG-NEET Mop-Up Round Once CBFC Grants Certificate, Courts Cannot Stall Release On Teaser Clips: Kerala High Court Clears “The Kerala Story 2 Goes Beyond” Section 3 Is Not A Blanket Ban On Fees: Delhi High Court Stays Removal of Difficulties Order Advancing Fee Fixation Timelines Son Has No Legal Right To Reside In Self-Acquired Property Of Mother Against Her Wishes: Orissa High Court Upholds Eviction Of Son And Daughter-In-Law Complaint Cannot Be Returned For Want Of Postal Address: Kerala High Court Opens Digital Door To Cyber Victims Drastic Variations And Material Improvements Render Testimony Unsafe Without Corroboration: Delhi High Court Acquits Two In Gang Rape Case Once the Ex Parte Decree Is Set Aside, Its Fruits Cannot Be Retained — Section 144 CPC Restores the Clock: Madras High Court Right To Education Cannot Be Put On Probation: Punjab & Haryana High Court Clears Way For Distance B.A. By Government Employee Technical Objection Cannot Defeat Substantive Policy Right: Punjab & Haryana High Court Directs Release of Matching Grant to Baba Bakala Bar Fracture Is Grievous — But Not Every Stick Is a ‘Dangerous Weapon’: Calcutta High Court Alters Conviction from Section 326 to 325 IPC Disclosure Statement of Co-Accused Alone Cannot Justify Continued Incarceration in Commercial Quantity NDPS Case: Punjab & Haryana High Court Grants Bail Dead Too Are Entitled to Dignity: Madras High Court Protects 70-Year-Old Burial Ground from Erasure When There Is a Duty to Speak, the Accused Cannot Enjoy Silence: Andhra Pradesh High Court Affirms Conviction Under Section 411 IPC Right To Health Is Not A Bureaucratic Concession: Punjab & Haryana High Court Orders Full Reimbursement In Life-Threatening Emergency

Once Delay Is Found Not Attributable To Contractor, Everything Else Must Fall: Bombay High Court Upholds Arbitral Award Against Solapur Municipal Corporation

07 February 2026 8:58 PM

By: sayum


“Strangely enough, instead of extending the period of contract, the contract has been terminated after imposing penalties... The delay is solely attributable to the respondents and not to the claimant.” Bombay High Court

In a landmark judgment that reaffirms the sanctity of arbitral autonomy and the limited scope of judicial intervention, the Bombay High Court dismissed a challenge by the Solapur Municipal Corporation under Section 34 of the Arbitration and Conciliation Act, 1996, against an arbitral award that had granted over ₹32 crores in claims to a contractor joint venture.

Justice Sandeep V. Marne observed that once the arbitral tribunal had returned findings of no delay attributable to the contractor, the consequential imposition of penalties, termination of contract, and blacklisting orders stood automatically vitiated.

The Court’s 67-page judgment, delivered after a meticulous examination of the arbitral award and the 15 sub-heads of alleged delay, reiterates the well-established proposition that a Section 34 court is not an appellate forum and may only interfere where findings are perverse, based on no evidence, or defy logic to a degree that no fair-minded person would accept.

“Admissions by Municipal Officials in Cross-Examination are the Best Evidence”

The dispute arose out of a ₹212 crore sewerage treatment project undertaken by the S.M.C.-G.E.C.P. Ltd. Joint Venture, awarded by the Solapur Municipal Corporation under an agreement dated 2 January 2012. Following a series of penalties and a premature termination on 9 December 2013, the contractor was also blacklisted. The contractor invoked arbitration and was awarded ₹32.15 crores in claims, including certified unpaid bills, refund of security deposit, Local Body Tax (LBT), and damages for loss of profit on unexecuted work.

Justice Marne decisively upheld the award, noting that delay was the fulcrum of the case. “Once the JV is absolved of the allegations of delay,” he held, “the termination is automatically rendered invalid.”

Crucially, the Court noted that admissions made by municipal officers in cross-examination before the tribunal were not only binding but decisive. Refusing to accept the argument that the contractor was obliged to prove a negative (i.e., that it was not responsible for delays), the Court cited the law that “an admission is the best evidence that an opposing party can rely upon.”

“A Reasonable Expectation of Profit is Implicit in a Works Contract”

On the issue of damages, particularly the award of 10% of the unexecuted balance contract value as loss of profit, the Court made a crucial legal distinction:

“There is a marked difference between the concepts of ‘loss of profit’ and ‘loss of profitability’. The former claim arises from wrongful termination and does not require proof of actual loss.”

Justice Marne observed that where termination is unjustified, proof of loss through documentary evidence is not a prerequisite, and courts can adopt a broad evaluative approach. The Court found the arbitral tribunal’s approach not only legally sound but also conservative, noting that:

“Though the contract value was ₹212.52 crores, the Tribunal awarded damages based only on a reduced estimate of ₹140 crores, amounting to just 5.5% of the actual unexecuted value.”

“No Evidence of Delay by Contractor; Inaction Entirely Attributable to Municipal Corporation”

The Court painstakingly examined each of the 15 sub-heads of alleged delay—ranging from bhoomi poojan delays, land unavailability, delayed approvals, and lack of coordination between authorities—and upheld the arbitral findings in favour of the contractor on 14 of them.

In one emphatic passage, the Court remarked:

“What the Municipal Corporation has done is to merely issue letters to the Contractor accusing it of causing delay. However, when it came to leading evidence, no substantive proof was led.”

The Court highlighted admissions made by the Engineer-in-Charge, the Municipal Commissioner, and other witnesses, wherein they conceded key facts such as the absence of land acquisition, delayed approvals, and bureaucratic bottlenecks.

“The Tribunal Did Not Re-Write the Contract; It Interpreted It”

On the Corporation’s argument that the arbitral tribunal rewrote the contract by treating bhoomi poojan delay and bar chart approvals as significant, the Court made a clear legal distinction. It held that the Tribunal was entitled to interpret contract terms in light of actual conduct and documentary evidence, and such an interpretation was well within the scope of arbitral authority.

The judgment also noted that the Municipal Corporation failed to justify the blacklisting order, particularly as it was premised on delay, which had already been discredited. The Court agreed with the Tribunal’s conclusion that partial subcontracting was permissible under the contract, rejecting the claim that subcontracting amounted to misconduct.

“Certified RA Bills Cannot Be Withheld After Penalties Are Found Illegal”

The Court further upheld the tribunal’s award of ₹16.45 crores towards the final RA bill, noting that both the Project Management Consultant (Maharashtra Jeevan Pradhikaran) and the Municipal Corporation had accepted the certified amount of ₹19.25 crores. Deduction of VAT and TDS had already been accounted for.

With penalties now set aside, the withholding of RA bill payments stood on no legal footing, and the Court ruled that the Tribunal rightly awarded the sum.

Award Based on Evidence, No Patent Illegality or Perversity

Summing up the decision, Justice Marne held:

“The Award to my mind appears to be unexceptional... The Tribunal has awarded claims in a conservative and reasoned manner, based entirely on documentary evidence and admissions in cross-examination. No case is made out for interference under Section 34.”

The Court dismissed both Arbitration Petitions—the Municipal Corporation’s petition against the award, and the contractor’s limited challenge, which had not been pressed.

It also directed the return of Bank Guarantees furnished by the contractor and encashment of Bank Guarantees deposited by the Corporation. However, it stayed the directions regarding Bank Guarantees for eight weeks, giving time to appeal.

Date of Decision: 6 February 2026

Latest Legal News