Presumption Of Correctness Of Judicial Records Not Absolute And Can Be Rebutted By Direct Evidence: Kerala High Court on Married Daughter Cannot Challenge Partition After 21-Year Slumber If She Had Knowledge: Madhya Pradesh High Court Kerala High Court Orders Immediate Suspension Of Lakshadweep CJM For Allegedly Forging Witness Deposition To Convict Accused Supreme Court Bars Post-Divorce Maintenance Claims When Wife Voluntarily Waived Maintenance In Settlement Agreement Advocate Is An Officer Of Court, Not Mere Agent Of Client: Allahabad High Court Distinguishes Between Active Concealment & Statement In Ignorance, Slaps Cost On Litigants For Misleading Bench Cannot Summon Accused Mechanically On Protest Petition Without Assigning Justifiable Reasons: Andhra Pradesh High Court Increment Not A Bounty: Allahabad High Court Rules Public Holiday Cannot Delay Pay Hike For Teachers Joining Next Working Day Paying Taxes Or Utility Connections Confer No Legal Ownership Over Govt Land': Andhra Pradesh High Court Orders Demolition Of Encroachment 'Cannot Compel Public Authority To Collect Data From Private Bodies': Bombay High Court Quashes CIC Orders Directing SEBI To Procure BSE Records Under RTI Act Section 10 CPC Cannot Stay Previously Instituted Title Suit Pending Subsequent Probate Case; Inherent Powers Under Section 151 Inapplicable When Probate Dismissed: Calcutta High Court Mere Phone Calls Without Transcripts No Ground For Murder Conspiracy: Delhi High Court Clear Violation Of Section 42 NDPS Act': Gujarat High Court Holds Failure To Record Secret Info In Writing Fatal When Police Officer Had Time To Act JK High Court Quashes Criminal Case Against Cop Accused Of Threatening Advocate Over Phone Call Without Prior Sanction Under Section 197 CrPC Custody Unwarranted For Mere Formalities Once Weapon Is Recovered: Kerala High Court Grants Regular Bail In BNS Axe Attack Case Circumstances Of Crime Can Be Assessed During Trial: High Court Upholds Trial Of Minor As Adult Under JJ Act In Murder Case Statutory Deposit Under Order 21 Rule 89 CPC Is A Sine Qua Non; Litigant Cannot Stall Auction Sale By Merely Blaming Counsel: Madras High Court

Once Delay Is Found Not Attributable To Contractor, Everything Else Must Fall: Bombay High Court Upholds Arbitral Award Against Solapur Municipal Corporation

07 February 2026 8:58 PM

By: sayum


“Strangely enough, instead of extending the period of contract, the contract has been terminated after imposing penalties... The delay is solely attributable to the respondents and not to the claimant.” Bombay High Court

In a landmark judgment that reaffirms the sanctity of arbitral autonomy and the limited scope of judicial intervention, the Bombay High Court dismissed a challenge by the Solapur Municipal Corporation under Section 34 of the Arbitration and Conciliation Act, 1996, against an arbitral award that had granted over ₹32 crores in claims to a contractor joint venture.

Justice Sandeep V. Marne observed that once the arbitral tribunal had returned findings of no delay attributable to the contractor, the consequential imposition of penalties, termination of contract, and blacklisting orders stood automatically vitiated.

The Court’s 67-page judgment, delivered after a meticulous examination of the arbitral award and the 15 sub-heads of alleged delay, reiterates the well-established proposition that a Section 34 court is not an appellate forum and may only interfere where findings are perverse, based on no evidence, or defy logic to a degree that no fair-minded person would accept.

“Admissions by Municipal Officials in Cross-Examination are the Best Evidence”

The dispute arose out of a ₹212 crore sewerage treatment project undertaken by the S.M.C.-G.E.C.P. Ltd. Joint Venture, awarded by the Solapur Municipal Corporation under an agreement dated 2 January 2012. Following a series of penalties and a premature termination on 9 December 2013, the contractor was also blacklisted. The contractor invoked arbitration and was awarded ₹32.15 crores in claims, including certified unpaid bills, refund of security deposit, Local Body Tax (LBT), and damages for loss of profit on unexecuted work.

Justice Marne decisively upheld the award, noting that delay was the fulcrum of the case. “Once the JV is absolved of the allegations of delay,” he held, “the termination is automatically rendered invalid.”

Crucially, the Court noted that admissions made by municipal officers in cross-examination before the tribunal were not only binding but decisive. Refusing to accept the argument that the contractor was obliged to prove a negative (i.e., that it was not responsible for delays), the Court cited the law that “an admission is the best evidence that an opposing party can rely upon.”

“A Reasonable Expectation of Profit is Implicit in a Works Contract”

On the issue of damages, particularly the award of 10% of the unexecuted balance contract value as loss of profit, the Court made a crucial legal distinction:

“There is a marked difference between the concepts of ‘loss of profit’ and ‘loss of profitability’. The former claim arises from wrongful termination and does not require proof of actual loss.”

Justice Marne observed that where termination is unjustified, proof of loss through documentary evidence is not a prerequisite, and courts can adopt a broad evaluative approach. The Court found the arbitral tribunal’s approach not only legally sound but also conservative, noting that:

“Though the contract value was ₹212.52 crores, the Tribunal awarded damages based only on a reduced estimate of ₹140 crores, amounting to just 5.5% of the actual unexecuted value.”

“No Evidence of Delay by Contractor; Inaction Entirely Attributable to Municipal Corporation”

The Court painstakingly examined each of the 15 sub-heads of alleged delay—ranging from bhoomi poojan delays, land unavailability, delayed approvals, and lack of coordination between authorities—and upheld the arbitral findings in favour of the contractor on 14 of them.

In one emphatic passage, the Court remarked:

“What the Municipal Corporation has done is to merely issue letters to the Contractor accusing it of causing delay. However, when it came to leading evidence, no substantive proof was led.”

The Court highlighted admissions made by the Engineer-in-Charge, the Municipal Commissioner, and other witnesses, wherein they conceded key facts such as the absence of land acquisition, delayed approvals, and bureaucratic bottlenecks.

“The Tribunal Did Not Re-Write the Contract; It Interpreted It”

On the Corporation’s argument that the arbitral tribunal rewrote the contract by treating bhoomi poojan delay and bar chart approvals as significant, the Court made a clear legal distinction. It held that the Tribunal was entitled to interpret contract terms in light of actual conduct and documentary evidence, and such an interpretation was well within the scope of arbitral authority.

The judgment also noted that the Municipal Corporation failed to justify the blacklisting order, particularly as it was premised on delay, which had already been discredited. The Court agreed with the Tribunal’s conclusion that partial subcontracting was permissible under the contract, rejecting the claim that subcontracting amounted to misconduct.

“Certified RA Bills Cannot Be Withheld After Penalties Are Found Illegal”

The Court further upheld the tribunal’s award of ₹16.45 crores towards the final RA bill, noting that both the Project Management Consultant (Maharashtra Jeevan Pradhikaran) and the Municipal Corporation had accepted the certified amount of ₹19.25 crores. Deduction of VAT and TDS had already been accounted for.

With penalties now set aside, the withholding of RA bill payments stood on no legal footing, and the Court ruled that the Tribunal rightly awarded the sum.

Award Based on Evidence, No Patent Illegality or Perversity

Summing up the decision, Justice Marne held:

“The Award to my mind appears to be unexceptional... The Tribunal has awarded claims in a conservative and reasoned manner, based entirely on documentary evidence and admissions in cross-examination. No case is made out for interference under Section 34.”

The Court dismissed both Arbitration Petitions—the Municipal Corporation’s petition against the award, and the contractor’s limited challenge, which had not been pressed.

It also directed the return of Bank Guarantees furnished by the contractor and encashment of Bank Guarantees deposited by the Corporation. However, it stayed the directions regarding Bank Guarantees for eight weeks, giving time to appeal.

Date of Decision: 6 February 2026

Latest Legal News