Mere Allegations of Harassment Do Not Constitute Abetment of Suicide: Punjab & Haryana High Court Grants Bail to Wife in Matrimonial Suicide Case 'Convenience Of Wife Not A Thumb Rule, But Custody Of Minor Child Is A Weighing Aspect': Punjab & Haryana HC Transfers Divorce Case To Rohtak MACT | A Minor Cannot Be Treated as a Non-Earner: Punjab & Haryana High Court Consensual Love Affair Not Cheating Under IPC Section 417: Madras High Court Acquits Man Despite Paternity Confirmation Review Jurisdiction is an Ant-Hole in a Pigeon-Hol: Madras High Court Dismisses Review Plea Against Order Upholding Arbitral Award on Liquidated Damages Bank Can Freeze Guarantor’s Salary Account to Recover Loan Dues: Kerala High Court Clarifies CPC Exemption Does Not Apply to Banker’s Right Revenue Entry Calling Property ‘Ancestral’ Does Not Create Title: Gujarat High Court Upholds Registered Will in Second Appeal Licensee Cannot Resist Resumption Of Railway Land: Gauhati High Court Upholds Eviction For Amrit Bharat Station Scheme Mere Non-Payment of Business Dues Is Not Cheating: Calcutta High Court Protects Traders from Criminal Prosecution in Purely Civil Dispute Prosecution’s Failure to Prove Age of Prosecutrix Beyond Reasonable Doubt Fatal to POCSO Conviction: Rajasthan High Court Judicial Review Is Not A Substitute For Examiner’s Judgment: Delhi High Court Rejects DJSE Candidate’s Plea Over Alteration of Marks Part-Payments Extend Limitation - Each Payment Revives Limitation: Delhi High Court No Title, No Right, No Equity: Bombay High Court Demolishes Claim Over Footpath Stall, Imposes ₹5 Lakh Costs for Abuse of Process Cooperative Society Is A “Veritable Party” To Arbitration Clause In Flat Agreements, Temple Trust Entitled To Arbitrate As Non-Signatory: Bombay High Court State Government Cannot Review Its Own Revisional Orders Under Section 41(3): Allahabad High Court Affirms Legal Bar on Successive Reviews When Several Issues Arise, Courts Must Answer Each With Reasons: Supreme Court Automatic Retention Trumps Lessee Tag: Calcutta High Court Declares Saregama India ‘Raiyat’, Directs Reconsideration of Land Conversion Application Recovery of Valid Ticket Raises Presumption of Bona Fide Travel – Burden Shifts to Railways: Delhi High Court Restores Railway Accident Claim Failure to Frame Issue on Limitation Vitiates Award of Compensation Under Telegraph Act: Gauhati High Court Sets Aside Order, Remands Matter Compassionate Appointment Is Not a Heritable Right: Gujarat High Court Rejects 9-Year Delayed Claim, Orders Re-Issuance of ₹4 Lakh Compensation Court Cannot Rewrite Contracts to Suit Contractor’s Convenience: Kerala High Court Upholds Termination of Road Work Under Risk and Cost Clause Post-Bail Conduct Is Irrelevant in Appeal Against Grant of Bail: Supreme Court Clarifies Crucial Distinction Between Appeal and Cancellation Granting Anticipatory Bail to a Long-Absconding Accused Makes a Mockery of the Judicial Process: Supreme Court Cracks Down on Pre-Arrest Bail in Murder Case Recognition as an Intangible Asset Does Not Confer Ownership: Supreme Court Draws a Sharp Line Between Accounting Entries and Property Rights IBC Cannot Be the Guiding Principle for Restructuring the Ownership and Control of Spectrum: Supreme Court Reasserts Public Trust Over Natural Resources Courts Cannot Convict First and Search for Law Later: Supreme Court Faults Prosecution for Ignoring Statutory Foundation in Cement Case When the Law Itself Stood Withdrawn, How Could Its Violation Survive?: Supreme Court Quashes 1994 Cement Conviction Under E.C. Act Ten Years Means Ten Years – Not a Day Less: Supreme Court Refuses to Dilute Statutory Experience Requirement for SET Exemption SET in Malayalam Cannot Qualify You to Teach Economics: Supreme Court Upholds Subject-Specific Eligibility for HSST Appointments Outsourcing Cannot Become A Tool To Defeat Regularization: Supreme Court On Perennial Nature Of Government Work Once Similarly Placed Workers Were Regularized, Denial to Others Is Discrimination: Supreme Court Directs Regularization of Income Tax Daily-Wage Workers Right To Form Association Is Protected — But Not A Right To Run It Free From Regulation: Supreme Court Recalibrates Article 19 In Sports Governance S. Nithya Cannot Be Transplanted Into Cricket: Supreme Court Shields District Cricket Bodies From Judicially Imposed Structural Overhaul Will | Propounder Must Dispel Every Suspicious Circumstance — Failure Is Fatal: : Punjab & Haryana High Court Electronic Evidence Authenticity Jeopardized by Unexplained Delay and Procedural Omissions: MP High Court Rejects Belated 65B Application Not Answering to the Questions of the IO Would Not Ipso Facto Mean There Is Non-Cooperation: Supreme Court Grants Anticipatory Bail Undertaking to Satisfy Award Is Not Waiver of Appeal: Supreme Court Restores Insurer’s Statutory Right

Court Cannot Rewrite Contracts to Suit Contractor’s Convenience: Kerala High Court Upholds Termination of Road Work Under Risk and Cost Clause

14 February 2026 10:26 AM

By: sayum


“Having Signed the Agreement With Open Eyes, Petitioner Cannot Later Demand ₹3.5 Crores More” — In a crucial ruling impacting public infrastructure contracts, the Kerala High Court upheld the termination of a PWD road work contract under the ‘risk and cost’ clause, dismissing a writ petition filed by contractor Shibu M. George, who had challenged the termination, forfeiture of performance guarantees, and threats of blacklisting.

Justice N. Nagaresh, sitting in civil writ jurisdiction, held that once a contractor signs a detailed public works contract, he is bound to execute the work as agreed and cannot later seek judicial intervention to revise estimates or avoid contractual consequences.

“After signing the agreement agreeing to execute the work for ₹2,78,70,165.66, the petitioner cannot be heard to contend that an additional ₹3.5 Crores is required to complete the work,” the Court observed.

The ruling comes amidst mounting disputes in Kerala’s ambitious Rebuild Kerala Initiative (RKI) infrastructure programme and serves as a clear assertion of the limits of judicial review in contractual matters involving the State.

“Risk and Cost Termination Is Contractual Consequence for Persistent Delay, Not Arbitrary State Action”

The case arose from a road improvement contract awarded under the RKI in Mananthavady, Wayanad, where the petitioner, an A-Class PWD contractor, was awarded the work for a reduced tendered amount. Despite a 9-month deadline, and two extensions granted by the State, the petitioner failed to complete even 50% of the work, prompting authorities to invoke Clause 2116.2 of the PWD Manual, terminating the contract at the contractor’s risk and cost, and initiating recovery of ₹66,02,497.68, apart from forfeiting the Performance and Additional Performance Guarantees.

The contractor alleged that post-agreement site conditions differed materially from the Detailed Project Report (DPR), requiring additional retaining walls, revised culvert designs, and rigid pavements, with an estimated extra burden of ₹3.5 crores. He contended that design discrepancies, non-removal of electric posts, and administrative inaction were responsible for delays, not default on his part.

The Court was not persuaded.

“The petitioner has executed the agreement knowing fully well the scope of the work. Ext.P1 was executed consensually. It is the obligation of the petitioner to complete the work as required by the agreement,” held the Court, refusing to accept post-facto demands for revised scope or cost adjustments.

“Judicial Review Doesn’t Extend to Rewriting Commercial Terms” — High Court Cautions Against Using Article 226 to Escape Contractual Obligations

While the petitioner urged the Court to invoke Article 226 citing arbitrariness and violation of Article 14, the Court reiterated the well-settled principle that judicial review in contractual matters is limited, and unless State action is perverse or violates fundamental rights, courts will not interfere.

“Writ jurisdiction is not an avenue to rewrite contracts or adjudicate disputed facts unless State action is arbitrary or perverse,” Justice Nagaresh affirmed, citing Subodh Kumar Singh Rathour v. CEO, M.P. Power Management v. Sky Power Southeast Solar India, and Noble Resources v. State of Orissa.

The Court emphasised that the petitioner was not compelled to enter into the agreement and had opportunities to inspect site conditions, estimate quantities, and raise concerns prior to contract execution. Having failed to do so, he cannot now plead hardship due to alleged site challenges.

“Sanctioned Width Is 3.75 Metres — Contractor’s Claim of 6 Metres Based on Local Demands Has No Contractual Basis”

Rejecting claims that 24 electric posts blocked the construction due to an alleged requirement of 6–7 metre width, the Court noted:

“The petitioner is bound by Ext.P1 agreement and sanctioned estimate. The duty and obligation of the petitioner are to construct the road as per the agreed terms... Any demand from local citizens need not be heard by the petitioner.”

The Court recorded that the sanctioned width was only 3.75 metres, and the respondents had already shifted seven electric posts. The Court categorically stated that remaining 24 posts did not hinder construction within sanctioned specifications, and the contractor’s claims were an afterthought.

“Ext.P10 Site Report Was Only a Recommendation — It Did Not Alter the Contractual Scope”

A pivotal argument raised by the petitioner was based on Ext.P10—a site inspection report by officials indicating water-logging, need for rigid pavement, and additional retaining walls. The Court held that this document did not alter the agreement or create enforceable rights.

“Ext.P10 can be taken only as a recommendation or opinion given by the Assistant Executive Engineer... it does not absolve the petitioner of his contractual obligations,” the Court ruled.

Limited Relief Granted — Contractor Entitled to Hearing on Final Risk and Cost Liability

While the Court dismissed the writ petition, it granted the petitioner a limited procedural safeguard, holding that before finalising the contractor’s monetary liability under the risk and cost clause, the authorities must grant him an opportunity of hearing.

“While computing the cost element as per the risk and cost clause in the agreement, the petitioner will be given an opportunity of hearing,” Justice Nagaresh ordered.

The direction ensures minimum due process, without undermining the core principle that contractual discipline must be maintained, especially in public works with budgetary implications.

Date of Decision: 02 February 2026

Latest Legal News