-
by sayum
28 May 2026 6:50 AM
"The ends of justice would be met if the plaintiff is awarded a sum of ₹62,00,000/- towards its claim as made so as to put an end to the entire litigation that has continued for almost three decades, " Supreme Court, in a recent order dated May 26, 2026, held that long-standing disputes spanning several decades should be put to "quietus" in the interest of justice rather than undergoing a fresh, detailed appreciation of evidence.
A bench of Justice J.K. Maheshwari and Justice Atul S. Chandurkar observed that when litigation has survived for nearly thirty years, the court may award a consolidated sum to ensure full satisfaction of a decree and bring an end to the dispute.
The matter arose from a 1992 contract between the Madhya Pradesh Electricity Board and M/s Shivhare Roadlines Pvt. Ltd. for the hire of two tractor-trailers. Following a dispute over outstanding hire charges and the return of the vehicles, the Board instituted a recovery suit in 1998. The Trial Court decreed the suit in 2011, ordering the defendants to pay the depreciated value of the vehicles, outstanding rent, and monthly compensation, a decision that was later upheld by the Madhya Pradesh High Court.
The primary question before the Court was whether it should engage in a detailed re-appreciation of rival submissions and evidence in a dispute originating from a 1992 contract. The Court also considered whether a consolidated monetary award could serve the ends of justice to terminate nearly three decades of litigation.
Disputes To Be Put To Quietus Given The Nature Of Long-Standing Litigation
The Supreme Court noted that the litigation between the parties had survived for almost three decades, originating from a contract dated April 22, 1992. During the hearing, the Senior Counsel appearing for both sides submitted to the orders of the Court after it was suggested that the dispute needed to be put to "quietus." The bench emphasized that the longevity of the case necessitated a resolution that would provide finality to the parties.
Court Avoids Detailed Re-appreciation Of Evidence In Old Matters
The bench observed that the vehicles in question were manufactured in 1979 and 1982, and their fitness certificates had expired as far back as 1991 and 1992. Rather than delving into the minutiae of the rival legal submissions or re-evaluating the depreciated value and rent calculations, the Court took an "overall view" of the matter. It held that a detailed appreciation was unnecessary to meet the ends of justice in such a dated dispute.
"Taking an overall view of the matter and without entering into detailed appreciation of the rival submissions, in our view, the ends of justice would be met if the plaintiff is awarded a sum... so as to put an end to the entire litigation."
Consolidated Award To Substitute Trial Court Decree Calculations
While the Trial Court had directed payment of ₹23.02 lakh as vehicle value, ₹23.56 lakh as rent, and ₹90,000 per month as compensation with interest, the Supreme Court opted for a lump sum settlement. The Court determined that a total payment of ₹62,00,000/- would constitute full satisfaction of the decree. This approach was adopted to bypass further execution complexities and provide an immediate resolution.
Adjustment Of Amounts Already Deposited By Defendants
The Court took into account that the defendants had already deposited ₹12,00,000/- before the High Court and a further ₹50,00,000/- with the Registry of the Supreme Court pursuant to interim orders. The bench directed that these amounts, totaling ₹62 lakh along with any accrued interest, be released to the respondent Electricity Board. This move was intended to effectively settle the dispute arising from the 1992 contract without further litigation.
"These amounts with accrued interest can be made over to the plaintiff so as to end dispute between the parties that arose pursuant to the contract dated 22.04.1992."
The Supreme Court disposed of the Special Leave Petition by holding the respondent entitled to a total sum of ₹62,00,000/-. By substituting the specific heads of the Trial Court's decree with a consolidated amount, the Court emphasized the judicial priority of ending decades-old commercial disputes over the technical re-evaluation of evidence at the appellate stage.
Date of Decision: May 26, 2026