Limitation Period For Specific Performance Starts From Date Of Refusal If No Fixed Date Stipulated In Agreement: Karnataka High Court Pensionary Benefits Not ‘Pecuniary Advantage’, Cannot Be Deducted From Income For Motor Accident Compensation: Punjab & Haryana High Court Propounder Faces Heavy Burden Of Proof When Testator Is Illiterate; Registration Does Not Cure Unexplained Suspicious Circumstances: Supreme Court Mother Killing Minor Children Over Husband's Refusal To Take Her To Workplace Is Murder, Not Culpable Homicide: Andhra Pradesh High Court Specific Performance Of Registered Agreement To Sell Is No Longer Discretionary Post-2018 Amendment: Allahabad High Court Civil Court Has Jurisdiction To Determine If Tenanted Property Belongs To Joint Family Even If Tenancy Order Stands In Individual Karta's Name: Bombay High Court Notice Under Section 107 BNSS Mandatory Before Attaching Property; Right To Property Is A Constitutional Right: Calcutta High Court Post-Cognizance Arrest 'Makes No Sense' If Investigation Completed Without Arrest: Delhi High Court Grants Bail Under BNSS Criminal Courts Cannot Be Used To Settle Civil Inheritance Disputes Over Appreciated Land Values: Gujarat High Court Quashes Fraud Case Accused Must Raise Probable Defence To Rebut Statutory Presumption Under Section 139 NI Act If Signatures Are Undisputed: Himachal Pradesh High Court Passing Departmental Exam Not A Pre-requisite For Grant Of ACP/MACP Benefits: Jharkhand High Court Convenience Of Family And Accused Paramount For Jail Shifting; Trial Court Can't Reject Application Merely For Non-Residency: J&K High Court Litigants Who Attempt To Pollute The Stream Of Justice With Tainted Hands Are Not Entitled To Any Relief: Karnataka High Court Trial Court Must Implement Modified Preliminary Decree In Full: Telangana High Court Directs Partition Of Property Omitted In Final Decree Proceedings If Grievance Is Real But Lies Before Different Forum, Plaint Should Be Returned Under Order VII Rule 10 CPC, Not Rejected: Rajasthan High Court Bail Cannot Be Denied Merely Due To Severity Of Economic Offence If Evidence Is Documentary: Punjab & Haryana High Court Non-Compliance With Mandatory Duty To Inform Grounds Of Arrest Under Section 47 BNSS Is Impermissible: Orissa High Court Grants Bail Land Acquisition Award Finality Under Section 12 Is A Bar To Writ Petitions Challenging 'Public Necessity': Madhya Pradesh High Court State As Eminent Domain Is Obligated To Pay Adequate Compensation, Not Minimum To Suit Its Convenience: Madras High Court Kerala High Court Grants Emergency Parole To Life Convict To Execute Sale Deed, Repay Bank Loan To Prevent Family's Eviction High Court Cannot Act As Court Of First Instance In Service Matters Amenable To CAT Jurisdiction: Delhi High Court Election Tribunal Has No Jurisdiction To Declare Caste Certificate Forged, Authority Vests Solely With Scrutiny Committee: Allahabad High Court Order IX Rule 7 CPC Requires 'Good Cause' Not 'Sufficient Cause'; Trial Court Can't Apply Higher Threshold To Pre-Decree Proceedings: Telangana High Court Victim Cannot Maintain Appeal Seeking Enhancement Of Sentence Under Section 372 CrPC; Such Power Exclusively With State: Rajasthan High Court Disability Pension: Presumption In Favour Of Personnel If Found Fit At Enrollment; Percentage Must Be Rounded Off: Punjab & Haryana HC Employee Entitled To Second Kramonnati Benefit If Promotion To Higher Post Does Not Result In Higher Pay Scale: Madhya Pradesh High Court Borrowers Can Be Granted Opportunity To Clear Loan Overdues In Installments To Prevent Coercive Action Under SARFAESI Act: Kerala High Court

Regulatory Commissions Cannot Rewrite Contractual Terms: Supreme Court Restores Invocation of Bank Guarantee Under PPA in Solar Energy Dispute

26 August 2025 1:29 PM

By: sayum


“KERC and APTEL cannot, under the guise of equity, override the terms agreed by parties through competitive bidding”— Supreme Court of India emphatically held that State Electricity Regulatory Commissions and the Appellate Tribunal for Electricity have no jurisdiction to rewrite or modify binding contractual obligations between parties, especially in agreements concluded through competitive bidding.

A Bench of Justices Sanjay Kumar and Satish Chandra Sharma reversed the orders of both the Karnataka Electricity Regulatory Commission (KERC) and the Appellate Tribunal for Electricity (APTEL), which had restrained the State electricity distribution company—Chamundeshwari Electricity Supply Company Ltd. (CESC)—from invoking the performance bank guarantee furnished by the private solar developer for failing to commission a 10 MW power project within the stipulated period.

“Delay by Another Government Entity Does Not Excuse the Obligation to Perform Without Invoking Force Majeure”

The case revolved around a Power Purchase Agreement (PPA) dated 30 August 2012, executed between CESC and the respondent-developer, Saisudhir Energy, for supply of power from a 10 MW solar plant. The PPA required commissioning within 12 months and included specific conditions precedent and timelines for obtaining connectivity, land, and other approvals.

According to the developer, the delay in evacuation infrastructure—the 220 kV line to be constructed by KPTCL, another government entity—was the sole reason for its failure to commission the plant on time. This, it argued, constituted a force majeure event, and hence, CESC’s action of invoking the performance bank guarantee was illegal.

Rejecting this, the Supreme Court observed:

“Even if the delay in completion of the evacuation system was beyond the developer’s control, the appropriate provision for relief was Article 5.7. But crucially, no Force Majeure notice was issued as required under Article 14.5.”

The Court underlined that the contract mandated a written notice within 7 days of becoming aware of the force majeure event, which the developer failed to comply with:

“This requirement is not merely directory; it is a condition precedent.”

“Regulators Cannot Reallocate Risk Contrary to What the Parties Have Agreed in the PPA”

The Karnataka Electricity Regulatory Commission had, in 2015, directed CESC to refund the encashed bank guarantee and allow the developer to operate at the higher tariff originally agreed in the PPA (Rs. 8.49/unit), rather than the reduced rate applicable to delayed projects (Rs. 2.39/unit). The APTEL upheld this in 2018.

However, the Supreme Court held that such directions amounted to judicial rewriting of the contract, observing:

“To permit otherwise would be to allow the State Commission or the APTEL to override the parties' own allocation of risk under the contract.”

The judgment reaffirmed the principle that State Commissions and tribunals cannot exercise equitable jurisdiction to override express contractual terms:

“The directions of the State Commission, affirmed by the APTEL, requiring restoration of the performance security, extension of contractual timelines, and renegotiation of tariff, transgress the limits of that jurisdiction.”

The Court added that the PPA had been executed pursuant to a competitive bidding process and received regulatory approval, making it binding in both letter and spirit.

“The PPA Must Be Enforced As It Stands—Not As Regulators Wish It Had Been Drafted”

The Court firmly restored the commercial sanctity of the contract, clarifying that the obligation to achieve commissioning by the Scheduled Commissioning Date (SCD) was not contingent upon evacuation readiness unless parties had provided for such interdependence in the agreement.

“The PPA being the product of a competitive bidding process and having received regulatory approval, must be construed and enforced strictly in accordance with its express stipulations.”

On the issue of CESC’s invocation of the bank guarantee, the Court held:

“CESC was fully justified in invoking the performance security under Article 4.4 of the PPA. To deny such invocation would be to disregard the allocation of risk embodied in the PPA.”

The Court also clarified that the invocation took place prior to any restraining order, making it procedurally lawful.

“Judicial Interference in Contractual Enforcement Is Impermissible in Commercial Agreements Approved by Regulators”

Ultimately, the Court declared the orders passed by the KERC on 28 January 2015 and by APTEL on 21 March 2018 to be unsustainable in law and fact. Both were accordingly set aside.

The appeal was allowed, with the Supreme Court reinstating CESC’s contractual remedies as originally agreed under the PPA.

Date of Decision: 25 August 2025

 

Latest Legal News