Disciplinary Authority Cannot Override Enquiry Officer’s Clean Chit Without Hearing the Employee: Madhya Pradesh High Court Remands Termination for Procedural Lapse Appointment Secured by Misstating Marks Is Void Ab Initio; Human Error No Excuse Where Advantage Gained: Allahabad High Court Appeal Maintainable Despite Modified MACT Award — Kerala High Court Clarifies Scope of Appellate Review in Motor Accident Claims No Notice, No Blacklist: Calcutta High Court Quashes Debarment Over Breach of Natural Justice Prosecution Must Elevate Its Case From Realm Of ‘May Be True’ To Plane Of ‘Must Be True: Orissa High Court Strict Compliance Is the Rule, Not Exception: Himachal Pradesh High Court Dismisses Tenant's Plea for Late Deposit of Rent Arrears When Accused Neither Denies Signature Nor Rebuts Presumption, Conviction Must Follow Under Section 138 NI Act: Karnataka High Court A Guardian Who Violates, Forfeits Mercy: Kerala High Court Upholds Natural Life Sentence in Stepfather–POCSO Rape Case Married and Earning Sons Are Legal Representatives Entitled to Compensation: Punjab & Haryana High Court Enhances Motor Accident Award to ₹14.81 Lakh Driver Must Stop, Render Aid & Report Accident – Flight from Scene Is an Offence: Madras High Court Convicts Hit-And-Run Accused Under MV Act Delay May Shut the Door, But Justice Cannot Be Locked Out: Gauhati High Court Admits Union of India’s Arbitration Appeal Despite Time-Bar Under Section 30 PC Act | Mere Recovery of Money Is Not Enough—Demand and Acceptance Must Be Proved Beyond Reasonable Doubt: Delhi High Court Allahabad High Court Slams Bar Council of U.P. for Ex Parte 10-Year Suspension of Advocate Supreme Court Invokes Article 142 to End Discrimination Against Ad-Hoc Employees in Allahabad High Court: Orders Reinstatement and Regularizationi Supreme Court Declares CSR a Constitutional Duty to Protect Environment: Orders Undergrounding of Powerlines in Great Indian Bustard Habitat A Minor’s Sole Testimony, If Credible, Is Sufficient for Conviction: Supreme Court Upholds Child Trafficking Conviction Under IPC and ITPA You Can’t Invent Disqualifications After the Bid: Supreme Court Holds Joint Venture Experience Can’t Be Ignored in Tenders High Court Can't Re-Appreciate Evidence or Rewrite Contract to Set Aside Arbitral Award: Supreme Court Reinstates Award Under Quantum Meruit Once Arbitration Invoked, Criminal Prosecution Cannot Be Weaponised in Civil Disputes: Supreme Court Quashes FIR Against Former Director in Rent Row Section 319 CrPC | Pursuing Legal Remedies in Higher Forums Is Not ‘Evasion of Trial’; Custody Not Required for Summoned Accused: Supreme Court Order 21 Rule 90 CPC | Undervaluation or Procedural Lapses Constitute ‘Material Irregularity’, Not ‘Fraud’; Separate Suit to Bypass Limitation Impermissible: Supreme Court Order 21 CPC | Separate Suit Challenging Auction Sale Barred for Pendente Lite Transferees; Remedy Lies in Execution Proceedings: Supreme Court Non-Signatories Cannot Force Arbitration: Supreme Court Blocks Claim by Sub-Contractor Against HPCL Resignation Forfeits Pension Rights, But Gratuity Is Statutory: Supreme Court Partly Allows Appeal of DTC Employee’s Legal Heirs Appellate Courts Can’t Blanket-Exempt Convicted Directors from Deposit under NI Act Merely Because Company Wound Up: Supreme Court Refers Interpretation of Section 148 to Larger Bench Agreement to Sell Does Not Create Any Right in Property, Hence No Right to Compensation on Acquisition: Allahabad High Court

“Had the Oberoi MoU Been Fully Disclosed, Tribunal Would Not Have Ruled the Way It Did” – Bombay High Court Quashes Section 17 Order, Sends Dispute Back for Reconsideration

27 July 2025 11:11 AM

By: Deepak Kumar


“The Tribunal Was Deprived of a Full Picture” – High Court Faults Summary Dismissal of Development Rights Amid Withheld Evidence and Misreadings on Land Title. In a significant judgment Bombay High Court (Justice Somasekhar Sundaresan) set aside an arbitral tribunal’s refusal to grant interim relief under Section 17 of the Arbitration and Conciliation Act, 1996 in the case of Atul Projects India Pvt. Ltd. v. Nima Developers Pvt. Ltd. & Ors. The Court ruled that the tribunal’s decision was based on “summary findings”, rendered without access to critical documents, particularly the highly redacted Oberoi MoU.

Noting that the tribunal had overlooked key legal and factual elements — including the ongoing effect of a revived 2002 government Show Cause Notice (SCN) restricting alienation of the land — the High Court remanded the matter for a fresh adjudication on interim measures.

Calling attention to the strategic suppression of evidence, the Court emphatically observed: “If this document [the Oberoi MoU] had been called for by the Learned Arbitral Tribunal just like my predecessor had called for it, the Tribunal would have taken a significantly different view of the matter.”

“NDZ Classification Is Not the End of the Road for Residential Development” – Court Corrects Tribunal’s View on Land Use

The tribunal had denied interim relief to Atul Projects partly on the ground that the project land was now classified as No Development Zone (NDZ), making residential development impossible. The High Court disagreed, holding that the Development Control and Promotion Regulations, 2034 expressly allowed for residential use as part of IT/ITES projects.

The Court noted: “Development of an IT park in NDZ also entails ‘allied services’ and ‘support services’, which include the need for those working in the IT park to have access to residential accommodation… The Oberoi MoU itself dealt with this very facet.”

Highlighting that the tribunal had not been given access to the complete Oberoi MoU, the Court found the analysis on NDZ classification “flawed and inaccurate”.

“Termination Took Effect Only in December 2023 – Not in 2020 as Claimed”

A major plank of the respondents’ argument was that Atul’s rights under the 2014 MoU had been terminated via letters in July and September 2020, and hence, no relief could be granted. The tribunal agreed. But the High Court saw things differently.

“It cannot be reasonably held with the certitude found in the Impugned Order that there had been a termination… on July 28, 2020,” the Court stated.

Justice Sundaresan highlighted that subsequent correspondence from the respondent (letter dated 7 September 2020) indicated continued willingness to perform, and therefore, “the threat of legal action if wiser counsel did not prevail… could point to potential action for specific performance being initiated by the Respondents not being ruled out.”

The Court conclusively held: “The clear and comprehensive termination took place only on December 18, 2023, when a cheque for refund of Rs. 5.51 crores was enclosed.”

This timeline was crucial: it meant that the Oberoi MoU, signed on 16 October 2023, had been executed while Atul’s contractual rights were still in force.

“Redacted Oberoi MoU Deprived the Tribunal of Vital Evidence” – Court Orders Full Disclosure

At the heart of the judgment lies the withholding of the full Oberoi MoU, which the Court called “a serious miscarriage of procedural fairness.”

“What was a 33-page document was presented as a six-page document… This deprived the Tribunal of a full picture,” Justice Sundaresan observed.

He continued: “Had the Oberoi MoU been available to the Learned Arbitral Tribunal, I have no doubt in my mind that it would not have returned the findings that it did…”

The Court directed that the entire Oberoi MoU must now be disclosed to the arbitral tribunal and Atul, with limited redactions only for financial figures, percentage terms, and select commercial specifics.

“Absolute and Clear Title Was Not Achieved — Payment Obligation Had Not Arisen”

The tribunal had accepted the respondents’ claim that clear title to the land had been established following the Division Bench judgment (DB Judgment) of October 2019, which revived the 2002 SCN. The tribunal therefore concluded that Atul was in breach for not making a ₹12 crore payment.

The High Court disagreed, holding that the revived SCN itself restricted land alienation and constituted a legal fetter.

“The DB Judgement… revived the 2002 SCN, which was not merely a show cause notice but also a direction prohibiting dealing with the Larger Land without government approval. This is clearly not consistent with a position of absolute and clear title,” the Court clarified.

It emphasized: “It would not be possible to concur that the DB Judgement led to conferment of absolute and clear title on Nima.”

Indeed, the Court traced the true clearing of title to a Revenue Minister's Order dated 31 October 2023, which occurred after the Oberoi MoU was executed and just before the actual termination on 18 December 2023.

“The Tribunal Must Decide Anew – This Time With the Full Picture”

Calling the arbitral tribunal’s findings “summary in character”, the High Court concluded:

“I have been persuaded that the Impugned Order deserves to be set aside by way of a remand… The Oberoi MoU must necessarily be handed over in an appropriately redacted form.”

The Court gave the respondents four weeks to provide the properly redacted Oberoi MoU to both the tribunal and Atul. It also preserved the existing interim protection in Atul’s favour for six more weeks to allow it to seek fresh relief before the tribunal.

“Oberoi Realty’s Involvement Cannot Be Ignored” – Tribunal to Decide on Impleadment of Non-Signatory

Although Oberoi Realty is not a party to the original arbitration, the High Court noted that Oberoi voluntarily sought impleadment, and that its agreement with India Farmers — signed during the subsistence of Atul’s rights — directly impacts the subject matter of the arbitration.

Referring to the Supreme Court's ruling in ASF Buildtech, the Court observed:

“The Oberoi MoU makes many references to the Atul Transaction Documents… making Oberoi a party would meet the ends of justice and would also not hurt Atul.”

While stopping short of ordering impleadment itself, the Court remitted that issue for the arbitral tribunal to decide afresh.

Justice Sundaresan’s detailed judgment represents a robust reaffirmation of procedural fairness, contractual interpretation, and substantive rights in commercial arbitration. By holding that “the summary nature of many critical findings” warranted judicial intervention, the Bombay High Court has ensured that arbitral discretion must rest on a complete and candid record.

The Court also reminded parties that attempts to suppress material documents — such as redacted MoUs — would not be tolerated in private commercial disputes, particularly where significant developmental and financial stakes are involved.

 

Date of Decision: 23 July 2025

Latest Legal News