Section 32 Arbitration Act | Termination for Non-Payment of Fees Ends Arbitrator’s Mandate; Remedy Lies in Section 14(2): Supreme Court False Allegations of Dowry and Bigamy Amount to Mental Cruelty: Madras High Court Upholds Divorce Plaintiff Must Prove Her Own Title Before Seeking Demolition Of Defendant’s Pre-existing House: Andhra Pradesh High Court Mismatch Between Bullet and Recovered Gun Fatal to Prosecution: Calcutta High Court Acquits Man Convicted for Murder Where the Conduct of the Sole Eye-Witness Appears Unnatural and No Independent Witness Is Examined, Conviction Cannot Stand: Allahabad High Court Fraudulent Sale of Vehicle During Hire Purchase Renders Agreement Void: Gauhati High Court Upholds Decree for Refund of ₹4.90 Lakhs Unsigned Written Statement Can’t Silence a Defendant: Hyper-Technical Objections Must Yield to Substantive Justice: Delhi High Court Default Bail | No Accused, No Extension: Delhi High Court Rules Custody Extension Without Notice as Gross Illegality Under Article 21 Gratuity Can Be Withheld Post-Retirement for Proven Negligence Under Service Rules – Payment of Gratuity Act Does Not Override CDA Rules: Calcutta High Court Cognizance Is of the Offence, Not the Offender: Madras High Court Rejects Challenge to ED’s Supplementary Complaint in PMLA Case Acquittal in Rajasthan No Bar to Trial in Madhya Pradesh: MP High Court Rejects Double Jeopardy Plea in Antiquities Theft Case 20% Deposit Isn’t Automatic in Cheque Bounce Appeals: Right to Appeal Can’t Be Priced Out: Punjab & Haryana High Court Checks Mechanical Use of Section 148 NI Act A Child Is Not a Non-Earner: Punjab & Haryana High Court Sets New Benchmark in Compensation for Minors’ Deaths 90 Days Is Not Sacrosanct – Courts Can Permit Reply to Counter-Claim Even Beyond Prescribed Time in Interest of Justice: Punjab & Haryana High Court Magistrate Can Proceed Only for Offences Committed in India Until Sanction Is Obtained for Acts Outside India: Orissa High Court on International Financial Fraud Award Is Vitiated by Non-Consideration of Material Evidence: Orissa High Court Sets Aside Industrial Tribunal’s Wage Award in IMFA Case POCSO | Absence of Child's Name in Birth Certificate Not Fatal: Kerala High Court No One Has the Right to Impute Illicit Motives to Judges in the Name of Free Speech: Karnataka High Court Jails Man for Criminal Contempt DV Complaint Cannot Be Quashed at Threshold Under Article 227: Madras High Court Refuses to Interfere, Directs Accused to Seek Remedy Before Magistrate Recovery Wasn't From Accused's Exclusive Knowledge — Cylinder Already Marked in Site Plan Before Arrest: Allahabad High Court Acquits Man in Murder Case State Can’t Block SARFAESI Sale by Late Revenue Entries: Secured Creditor’s Charge Prevails Over Tax Dues: Punjab & Haryana High Court Slams Sub-Registrar’s Refusal Providing SIM Card Without Knowledge of Its Criminal Use Does Not Imply Criminal Conspiracy: P&H High Court Grants Bail in UAPA & Murder Case Importer Who Accepts Enhanced Valuation Cannot Later Contest Confiscation and Penalty for Undervaluation: Madras High Court Upholds Strict Liability under Customs Act "Allegations Are Not Proof: Madras High Court Refuses Divorce Without Substantiated Cruelty or Desertion" When FIR Is Filed After Consulting Political Leaders, the Possibility of Coloured Version Cannot Be Ruled Out: Kerala High Court Mere Allegations of Antecedents Without Conviction Can't Defeat Right to Anticipatory Bail: Kerala High Court Section 106 Of Evidence Act Cannot Be Invoked In Vacuum – Prosecution Must First Lay Foundational Facts: Karnataka High Court Acquits Wife And Co-Accused In Husband’s Murder Case Parity Cannot Be Claimed When Roles Are Different: Karnataka High Court Refuses Bail to Youth Accused of Brutal Killing Injured Wife Would Not Falsely Implicate Her Husband: Gauhati High Court Upholds Conviction in Domestic Stabbing Case Disputed Bids, Missing Evidence and No Prejudice: Delhi High Court Refuses to Intervene in Tender Challenge under Article 226 Setting Fire to House Where Only Minors Were Present is a Heinous Offence – No Quashing Merely Because Parties Settled: Calcutta High Court No Exclusive Possession Means Licence, Not Lease: Calcutta High Court Rules City Civil Court Has Jurisdiction to Evict Licensees Defendant's Own Family Attested the Sale Agreement – Yet She Called It Nominal: Andhra Pradesh High Court Upholds Specific Performance Renewal Not Automatic, No Evidence Of Notice Or Mutual Agreement: AP High Court Dismisses Indian Oil’s Appeal Against Eviction

Allottees Cannot Postpone Refund Claims Indefinitely After Possession With Occupation Certificate Is Offered: Bombay High Court Clarifies Scope of Section 18 of RERA

01 August 2025 1:04 PM

By: Deepak Kumar


“Defective Title Grievances Are Distinct and Must Be Pursued Separately Under Section 18(2); Right to Refund Under Section 18(1) Ends Within Two Months After Offer of Possession”, In a significant judgment delivered on 18th July 2025, the Bombay High Court pronounced a crucial clarification on the ambit of refund rights under the Real Estate (Regulation and Development) Act, 2016 (RERA). Justice M.M. Sathaye held that an allottee’s right to claim refund due to delay in possession under Section 18(1) of RERA is not an unending privilege. The Court ruled,

“Where possession is offered along with a valid Occupation Certificate (OC), an allottee cannot indefinitely postpone the decision to withdraw from the project; such a decision must be taken within two months of the offer.”

The judgment provides a vital precedent for balancing rights of allottees and promoters, emphasizing that indefinite delay in decision-making by homebuyers causes undue financial burden on developers and contradicts the principle of fairness embedded within RERA.

Flat Buyers Claimed Refund Years After Possession Was Offered

The appeals before the High Court arose from four refund orders passed by the Maharashtra Real Estate Appellate Tribunal in favour of allottees of four flats in the Aaryavarta project in Nashik. The appellant developer, Linker Shelter Pvt. Ltd., had agreed to hand over possession by December 2017 but obtained an Occupation Certificate (OC) only in July 2018.

Despite being offered possession via letters in December 2018 and September 2019, the allottees did not respond until February 2020 when they demanded a full refund, alleging defective land title. The MahaRERA dismissed their complaints, but the Appellate Tribunal directed the developer to refund the entire amount with prolonged interest. Challenging this decision, the developer approached the High Court arguing that such belated claims defeat the objectives of RERA.

 “Right to Refund Is Not a Perpetual Right After OC”

Justice Sathaye, after an extensive review of RERA provisions, Supreme Court precedents including Newtech Promoters (2021) and Imperia Structures (2020, 2022), and the legislative scheme of RERA, held:

“While Section 18(1) confers an unqualified right on an allottee to withdraw in case of delay, it cannot be stretched beyond the statutory framework… Once possession with Occupation Certificate is offered, Section 19(10) comes into play and the allottee must take a decision within two months.”

The Court further observed that allowing open-ended refund claims, even after valid possession is offered,

“would amount to an absurd interpretation and result in frustration of the balance and standardisation that the RERA Act intends to achieve.”

Justice Sathaye reasoned that such prolonged claims not only create liability for developers for an undefined period but also deprive them of the opportunity to sell the unsold units in a rising market.

“Defective Title Grievance Cannot Be Mixed With Delay in Possession”: Court Differentiates Between Section 18(1) and 18(2)

The Court made a crucial distinction between two different remedies under RERA: “Grievances about defective title of land squarely fall under Section 18(2), which provides for compensation without limitation… They cannot be invoked to prolong the right to refund under Section 18(1) related to delay in possession.”

Justice Sathaye emphasized: “Once possession is offered with OC and there is no injunction preventing such possession, objections regarding title defects cannot be used to indefinitely postpone possession or claim continued interest on refunds.”

The Court clarified that aggrieved allottees are free to pursue compensation for defective title separately under Section 18(2), without conflating it with Section 18(1) withdrawal rights.

“Offer of Possession Remains Valid Despite Litigation if OC Is Obtained”: Court Interprets RERA’s Scheme on Pending Land Disputes

A key contention from the allottees was that pending litigation over title invalidated the offer of possession. The Court, however, firmly rejected this notion by holding:“Possession offer remains valid if the developer obtains Occupation Certificate (OC) and there is no subsisting court injunction. Mere pendency of title litigation does not vitiate the possession offer.”

Referring to Section 4(2) of RERA and MahaRERA’s Circular No. 28 of 2021, Justice Sathaye highlighted: “RERA obliges disclosure of litigations but does not prohibit possession merely due to litigation pendency.”

Refund Allowed Only with Limited Interest Period

Summing up the legal conclusions, Justice Sathaye ordered: “Allottees are entitled to withdraw from the project and obtain a refund, but interest is limited to two months from the date of the valid possession offer along with OC… beyond this, no interest shall accrue.”

The Court set aside the Appellate Tribunal’s direction to grant prolonged interest and instead confined interest liability to the period ending two months after the first offer of possession (i.e., up to 21 February 2019).

Moreover, it granted liberty to allottees to initiate separate proceedings for compensation under Section 18(2) regarding title defects, thus preserving their right to compensation without permitting double advantage through prolonged interest.

Judgment Establishes Balanced Approach Under RERA Between Developers and Allottees

The Bombay High Court’s judgment in Linker Shelter Pvt. Ltd. v. Charmaine Chougule & Ors. provides an important precedent in real estate litigation, drawing a clear line between delay-related refund rights and title-related compensation claims under RERA. By affirming that refund rights under Section 18(1) must be exercised within two months of a valid OC offer, the Court has strengthened legal certainty and prevented misuse of RERA’s protective mechanisms.

As Justice Sathaye rightly summed up: “Standardisation under RERA is achieved when rights are exercised timely, and developers are not subjected to indefinite uncertainty. The balance must be preserved, ensuring justice both to homebuyers and promoters.”

Date of Decision: 18 July 2025