A District Survey Report Without Replenishment Study Is Untenable in Law – Supreme Court Reiterates Sand Mining Can’t Be Legalised Through Administrative Convenience

23 August 2025 3:55 PM

By: sayum


“Regulatory Authority Cannot Compromise Its Duty by Limiting Mining Depth in Absence of Scientific Replenishment Study” – Supreme Court Upholds NGT’s Cancellation of Sand Mining Clearances in J&K; Reinforces Mandatory Nature of Replenishment Study Under Environmental Law

Supreme Court of India, in a significant environmental law judgment, dismissed appeals filed by the UT of J&K, the NHAI, and the private project proponent, thereby upholding the National Green Tribunal's (NGT) order quashing environmental clearances (ECs) for riverbed sand mining in three blocks of Shaliganga Nallah. The Court held that District Survey Reports (DSRs) prepared without replenishment studies are invalid, and clearances granted on the basis of such defective reports are void in law.

“It is compelling to hold that a DSR is valid and tenable only when a proper replenishment study is conducted.” — observed the Bench of Justice Pamidighantam Sri Narasimha and Justice Atul S. Chandurkar.

ECs Granted Despite Incomplete Reports, Ignoring Replenishment Data

The controversy stemmed from environmental clearances granted on 19 April 2022 by the J&K State Environment Impact Assessment Authority (SEIAA) for sand mining in Blocks 1, 2 and 4 of Shaliganga Nallah. The clearances were recommended by the J&K Expert Appraisal Committee (EAC) despite explicit acknowledgment that the District Survey Report (DSR) lacked replenishment data—a mandatory scientific prerequisite under the EIA Notification, 2006 (as amended in 2016), the Sustainable Sand Mining Guidelines, 2016, and the Enforcement and Monitoring Guidelines, 2020.

Notably, the J&K EAC initially rejected the proposals in its meeting dated 03.01.2022 but later approved them merely after the project proponent obtained a ‘Fit for Mining’ certificate from the Geology Department.

“The J&K EAC committed a serious error in proceeding with the DSR once it realised it was not formulated as per the MoEF&CC Notification, 2016 and lacked replenishment data.” — Supreme Court [Para 35].

Without Replenishment Study, DSR Has No Legal Sanctity

In an unambiguous affirmation of existing environmental jurisprudence, the Supreme Court declared:

“A District Survey Report without a proper replenishment study is equally untenable.” [Para 33]

The Court observed that both the 2016 and 2020 guidelines make it imperative to calculate the annual replenishment rate of sand deposits before granting EC. The attempt to substitute scientific inquiry with administrative restriction on mining depth (e.g., 1 metre) was rejected as a statutorily impermissible shortcut.

“The compromise sought to be achieved by permitting restricted mining in view of non-availability of replenishment data is unacceptable.” [Para 37]

Regulatory Abdication: Appraisal Authorities Failed in Their Statutory Duties

The Supreme Court was sharply critical of both the J&K EAC and SEIAA for abdication of their statutory responsibility. While SEIAA granted clearance citing “maximum 1 metre mining depth,” the EAC had expressly admitted that the DSR needed revision due to lack of replenishment data.

“This is how regulatory failure occurs.” – the Court remarked, condemning the “half-hearted approach” of the regulatory authorities. [Para 37]

No Exception to Replenishment Study—Even For Limited Mining Depth

The Supreme Court rejected arguments that restricting mining depth to one metre could compensate for the absence of replenishment data.

“There is no provision whereunder, if mining for one metre depth is allowed, the requirement of preparation of DSR or replenishment study can be dispensed with.” — NGT finding, endorsed by the Supreme Court [Para 38]

Heavy Machinery Use in Violation of EC Conditions – Action to Follow

The Court also upheld the NGT’s direction to the J&K Pollution Control Board to take action against the project proponent for using heavy machinery like JCBs and excavators, which were prohibited under Condition 53 of the EC.

“Mining shall be done manually, minimally supported by semi-mechanized methods… Heavy machinery like JCBs should not be allowed.” – Condition 53 of the EC

The Pollution Control Board has been directed to act after giving the proponent an opportunity to present its case. [Para 42]

“Effective environmental protection cannot be compromised by administrative convenience.” – Supreme Court [Para 44]

The Supreme Court’s judgment in Union Territory of Jammu & Kashmir v. Raja Muzaffar Bhat & Ors. stands as a landmark reaffirmation of environmental due process, particularly in the domain of riverbed sand mining. It clarifies that no mining clearance is legally sustainable unless grounded in a scientifically valid District Survey Report, supported by a replenishment study. The Court categorically rejected regulatory leniency, reaffirming that ecological safeguards under the Environment Protection Act, 1986, and EIA Notifications are non-negotiable.

“We have no hesitation in upholding the decision of the NGT and dismissing the civil appeals… The parties shall bear their own costs.” — Supreme Court [Para 44]

Date of Decision: August 22, 2025

Latest Legal News