Patta Without SDM’s Prior Approval Is Void Ab Initio And Cannot Be Cancelled – It Never Legally Existed: Allahabad High Court Natural Guardian Means Legal Guardian: Custody Cannot Be Denied to Father Without Strong Reason: Orissa High Court Slams Family Court for Technical Rejection Affidavit Is Not a Caste Certificate: Madhya Pradesh High Court Sets Aside Zila Panchayat Member's Election for Failing Eligibility Under OBC Quota Confession Recorded By DCP Is Legally Valid Under KCOCA – Bengaluru DCP Holds Rank Equivalent To SP: Karnataka High Court Difference of Opinion Cannot End in Death: Jharkhand High Court Commutes Death Sentence in Maoist Ambush Killing SP Pakur and Five Policemen Mere Presence Of Beneficiary During Execution Does Not Cast Suspicion On Will: Delhi High Court Contempt | Power to Punish Carries Within It the Power to Forgive: Supreme Court Sets Aside Jail Term for Director Who Criticised Judges Over Stray Dog Orders Seizure and Attachment Are Not Twins: Supreme Court Holds Police Can Freeze Bank Accounts in PC Act Cases Using CrPC Section 102 IBC | Pre-Existing Dispute Must Be Real, Not Moonshine: Supreme Court Restores Insolvency Proceedings, Says Admission Cannot Be Rejected Based on Spurious Defence Summons Under FEMA Are Civil in Nature – Section 160 CrPC Has No Role to Play: Delhi High Court Denies Exemption to Woman Petitioner from Personal Appearance Before ED Clear Admission in Ledger Is Sufficient for Summary Judgment: Delhi High Court Decrees ₹16.77 Cr in Favour of MSME Supplier Mere Allegation Under SC/ST Act Doesn’t Bar Bail When No Public Abuse Is Made Out: Karnataka High Court Grants Anticipatory Bail in Caste Atrocity Case Consent Of Girl Aged Above 16 Is Legally Valid Under Pre-2013 Law: Karnataka High Court Sets Aside Rape Conviction Insurer Entitled to Recover Compensation from Owner When Driver Has No Licence or Fake Licence: Punjab & Haryana High Court Applies ‘Pay and Recover’ Doctrine Courts Cannot Rewrite Contracts Where Parties Have Failed to Clearly Define Property Terms: Punjab & Haryana High Court Dismisses Appeal in Specific Performance Suit Even Illegal Appointments Cannot Be Cancelled Without Hearing: Patna High Court Quashes Mass Termination Of Absorbed University Staff

The Arbitral Tribunal’s construction of contract terms is binding unless no fair-minded or reasonable person could do so," Supreme Court Upholds Arbitral Award

07 May 2024 8:19 AM

By: Admin


The Supreme Court today dismissed a series of appeals by the National Highways Authority of India (NHAI) against the Hindustan Construction Company Ltd. concerning payment disputes under the Allahabad Bypass Project contract, emphasizing the sanctity of arbitral tribunal decisions in contractual interpretations unless they manifest patent illegality.

The primary legal issue addressed was the application of Sections 34 and 37 of the Arbitration and Conciliation Act, 1996, concerning challenges to and the appellate review of an arbitral award. The Supreme Court deliberated on whether the arbitral award and the subsequent judgments by the lower courts fell within the permissible scope of judicial intervention as prescribed under the said Act.

The case arose from a contract awarded by NHAI to Hindustan Construction for the Allahabad Bypass Project. Disputes referred to the arbitral tribunal included claims for additional costs due to legislative changes affecting royalties and taxes, and payment for specific construction works. The arbitral award favored the construction company, which was upheld by both the single judge and a division bench of the High Court.

Contractual Interpretation and Limited Judicial Interference: The Court underscored the principle of minimal judicial interference in arbitral awards, stating that "the construction of the terms of a contract is primarily for an Arbitrator to decide unless the Arbitrator construes the contract in such a way that it could be said to be something that no fair-minded or reasonable person could do." The Court found that the tribunal’s interpretation was within the bounds of reasonableness and did not merit judicial interference.

Specific Claims on Increased Costs and Tax Changes: On the claims involving increased royalty rates and associated taxes due to legislative changes, the Court noted that such costs are to be considered separate from general price adjustments under the contract. The tribunal’s decision was seen as consistent with previous precedents and the specific contractual clauses which provide for separate compensation over and above general price adjustment mechanisms.

Embankment Construction Payments: Regarding payments for embankment construction, the Court highlighted that the majority of the tribunal recognized these costs as separate from other categorized works under the contract, which was a specialized assessment by the technical experts of the tribunal. The Court upheld the arbitral award stating that the tribunal's expert interpretation should be respected unless shown to be patently unreasonable.

Decision: The appeals were dismissed, affirming the arbitral award and the decisions of the lower courts, reinforcing the principle that judicial interference in arbitral decisions is limited to cases of evident illegality or irrationality.

Date of Decision: May 7, 2024

National Highways Authority of India vs. M/s Hindustan Construction Company Ltd.

Latest Legal News