Sold Property During Pending Appeal, Defied Court Order: Andhra Pradesh High Court Sends Man To Jail For Contempt Hostile Witness Cannot Erase a Bribe Demand Already Made on Record: Supreme Court Restores Conviction of Ration Officer Three Decades of Unpaid Wages: Supreme Court Strips Gannon Dunkerley of Control Over Sick Company's Assets, Appoints Administrator to Pay Workers by August 2026 Gram Nyayalaya Cannot Touch Family Court's Maintenance Orders — Allahabad High Court Draws the Line Caste Abuse Allegation at Village Jatra Is Counter-Blast to Earlier Machete Attack: Karnataka High Court Grants Anticipatory Bail Despite SC/ST Act Bar Contributory Negligence | Not Wearing a Helmet Does Not Mean the Victim Caused the Accident: Madras High Court Air Force Can't Punish Officer After Criminal Court Sets Him Free: Supreme Court Overturns 30-Year-Old Dismissal Written Statement Without Affidavit of Admission/Denial: Non-Est Filing or Curable Defect? Delhi High Court Refers Conflicting Views to Larger Bench Bank's Negligence Killed Cheque Bounce Case Before It Could Begin: Supreme Court Rules Section 138 Remedy Lost Due to Stale Cheques Bank Letting Your Cheques Go Stale Is Deficiency in Service: Supreme Court Victim Has Locus To Request Court To Summon Witnesses Under Section 311 CrPC In State Prosecution: Allahabad High Court Benefit Of Probation Act Available Even If Offender Is Sentenced Solely To Fine: Supreme Court Reporting Registration Of FIR Based On Public Records Does Not Violate Right To Privacy: Sikkim High Court CBSE Cannot Cancel Class XII Results Based on Similar MCQ Answers Alone Without Any Report of Malpractice From Examination Centre: Orissa High Court

Payment of Money Claims Arising Out of Contractual Obligations Should Not Be Entertained By A Writ Court: Calcutta High Court Allows Appeals Against Payment To Contractors

07 May 2024 8:19 AM

By: Admin


In a significant judgment rendered on May 2, 2024, the Calcutta High Court delved deep into the maintainability of writ petitions in disputes arising out of contractual obligations. The bench, comprising The Hon’ble The Chief Justice T.S. Sivagnanam and The Hon’ble Justice Hiranmay Bhattacharyya, reversed a previous decision which had directed the Ghani Khan Choudhury Institute of Engineering and Technology to pay M/s. Malda Construction Company for completed contractual work, emphasizing the non-maintainability of such petitions on contractual money claims.

The core legal issue addressed was whether writ petitions involving payment disputes under contractual obligations are maintainable, especially when entities amenable to Article 226 of the Constitution are involved.

The appellants, Ghani Khan Choudhury Institute, were previously ordered by a Single Judge to make outstanding payments to the respondents, M/s. Malda Construction and others, for construction work completed satisfactorily. The appellants challenged the writ petitions’ maintainability, citing delays and disputed contractual and financial issues.

Contractual Nature and Writ Jurisdiction: The court extensively reviewed the Supreme Court precedents, noting that writ jurisdiction is generally reserved for public law remedies and should not extend to disputes lying entirely within private contractual realms, unless the actions of public bodies are arbitrary or capricious.

Maintainability and Delay: The court pointed out that the writ petitions were filed seven years after the last billing, a delay deemed unreasonable. It highlighted that filing a writ petition after the expiration of a reasonable time established by analogous civil suits under the Limitation Act undermines the need for prompt legal action.

Disputed Financial Liabilities: The court observed genuine disputes over financial liabilities, including the invocation of the Comptroller and Auditor General’s report, which questioned the procedural legitimacy of the expenditures by the institute.

Decision: Concluding its evaluation, the court allowed the appeals by the Institute, reversing the decision of the Single Judge, and dismissed the writ petitions as non-maintainable based on the grounds of procedural lapses, delay, and the nature of the contractual and financial disputes. The court directed the parties to seek remedies in appropriate forums, ensuring that observations in the judgment do not prejudice future proceedings.

Date of Decision: 2nd May 2024

The Ghani Khan Choudhury Institute of Engineering and Technology & Ors. vs. M/s. Malda Construction Company & Ors.