-
by Deepak Kumar
13 September 2026 8:08 AM
"The language of Section 8 is peremptory in nature. Therefore, in cases where an arbitration clause exists in the agreement, it is obligatory for the court to refer the parties to arbitration in terms of their agreement" Madhya Pradesh High Court, in a ruling dated September 2, 2026, held that an executing court is obligated to refer a dispute to arbitration under Section 8 of the Arbitration and Conciliation Act, 1996, if the underlying compromise decree contains a valid arbitration clause covering the subject matter of the dispute.
Justice Deepak Khot emphasized that the court’s role, once a Section 8 application is moved, is strictly limited to referring the parties to the agreed-upon forum.
The dispute arose from a 2012 compromise decree in an eviction suit, which included stipulations for compensatory payments if the tenant failed to complete construction within a specified timeframe. When the landlord initiated execution proceedings under Order XXI Rule 11 of the CPC to recover these payments, the tenant filed an application under Section 8 of the Arbitration Act, citing a clause in the compromise decree requiring all related disputes to be settled by arbitration. The executing court rejected the application, prompting the current appeal.
The court was tasked with determining whether an executing court is empowered to proceed with the execution of a compromise decree when an application under Section 8 of the Arbitration and Conciliation Act has been filed. Specifically, the court addressed whether a dispute regarding the breach of conditions within a compromise decree must be adjudicated by an arbitrator if the decree itself mandates arbitration for such issues.
The court underscored that the mandate of Section 8 is peremptory, leaving the executing court no discretion once it is satisfied that a valid arbitration agreement covers the dispute. Referencing the Supreme Court’s decision in P. Anand Gajapathi Raju v. P.V.G. Raju, the bench observed that once an application under Section 8 is filed, the original action’s further adjudication by the civil court becomes impermissible.
Peremptory Nature of Section 8
The court reiterated that the primary intent of the Arbitration Act is to prioritize the chosen forum of the parties. By rejecting the Section 8 application, the trial court had effectively ignored the jurisdictional mandate of the arbitration clause. The bench noted that allowing the execution proceedings to continue without resolving the underlying dispute through the mandated arbitration mechanism would render the arbitration agreement entirely otiose.
Court Clarifies Scope of Waiver
In analyzing the objection regarding whether the appellant had waived its right to arbitration, the court relied on Booz Allen & Hamilton Inc. v. SBI Home Finance Ltd. It observed that a party only waives its right to arbitration if it submits to the court’s jurisdiction by filing a statement on the substance of the dispute. Simply contesting execution proceedings to avoid immediate prejudice does not constitute a waiver of the right to seek arbitration for the substantive dispute.
Resolution of Disputed Obligations
The court noted that the current impasse—whether the construction delay was due to the tenant’s lethargy or the landlord’s failure to provide possession—is a question of fact that requires adjudication. This adjudication must occur within the parameters of the arbitration clause. The court clarified that referring the matter to arbitration does not strip the landlord of their rights under the decree, but merely changes the forum where the liability for the compensatory payment is determined.
"If the arbitrator concludes that the delay was due to the fault of the appellant, the respondent would definitely be entitled to the claimed amount along with arrears"
The High Court set aside the order of the executing court and allowed the application under Section 8. The executing court was directed to facilitate the appointment of an independent arbitrator to resolve the dispute within a stipulated timeframe. Once the arbitrator adjudicates the underlying conflict regarding the breach of the compromise conditions, the execution proceedings may proceed in accordance with the arbitrator's findings.
Date of Decision: 02 September 2026