Advocates Cannot Threaten Judges With Corruption Allegations To Force Favourable Orders: Bombay High Court Holds Lawyers Guilty Of Criminal Contempt Co-Sharer Cannot Transfer Specific Portion Of Joint Land; Sale Operates Only As Transfer Of Undivided Share: Himachal Pradesh High Court Companies Act 2013 | Amount Due For Refund Post-Capital Reduction Does Not Qualify As Unclaimed Application Money For IEPF Transfer: Delhi High Court Seniority Cannot Be Claimed By Ad Hoc Or Temporary Employees Over Regularly Appointed Candidates: Supreme Court Supreme Court Directs Deposit Of Entire Enhanced Compensation In Land Acquisition Appeals To Balance Financial Liability And Landowners' Rights Succession To Bhumidhari Rights By Hindu Women Governed By Personal Law As It Stands On Date Of Demise: Supreme Court Hindu Widow’s Limited Life Interest In Agricultural Land Becomes Absolute Upon Enactment Of HSA 1956, Governs Devolution Under Delhi Land Reforms Act: Supreme Court Bodily Injury Under Section 165 MV Act Covers Both Temporary And Permanent Injuries Irrespective Of Disability Certification: Bombay High Court Testimony Of An Injured Witness Is A 'Sterling Witness' With A Built-In Guarantee Of Presence At The Scene Of Crime: Allahabad High Court Scrutiny Committee Has Inherent Power To Direct Re-Examination Of Documents During Caste Verification, Does Not Need To Discard Entire Vigilance Report: Bombay High Court Tender Cancellation Orders Must Be Reasoned; Affidavit Cannot Supplement Missing Reasons: Allahabad High Court Section 9 Of Arbitration Act Allows Interim Orders Against Non-Signatories To Preserve Subject Matter: Delhi High Court Order VII Rule 11 CPC | Parsi Matrimonial Suit Can Be Dismissed At Threshold If Jurisdictional Fact Of Marriage Solemnisation In India Is Absent: Bombay High Court Section 125 CrPC | Maintenance Is A Social Welfare Measure To Prevent Destitution, Not A Tool For Financial Enrichment: Allahabad High Court Locus Standi To Challenge Tenancy Orders | Person With Registered Agreement For Sale Is An 'Aggrieved Person' Under BTAL Act: Bombay High Court

Review Jurisdiction Cannot Be Used To Introduce New Factual Foundations Or Reopen Concluded Arbitral Awards: Karnataka High Court

14 September 2026 1:05 PM

By: sayum


"A review petition cannot be utilized to introduce a new factual foundation and thereby reopen the substantive rights that have already stood concluded. The jurisdiction of review is limited and cannot be converted into appellate jurisdiction so as to enable a party to raise a new case." Karnataka High Court, in a judgment dated 02 September 2026, held that a review petition cannot be invoked to reopen a concluded arbitral award by introducing fresh factual contentions that were never raised during the original adjudication.

A division bench comprising Chief Justice Vibhu Bakhru and Justice K.S. Hemalekha observed that once a statutory award under the National Highways Act, 1956 (NH Act) attains finality, the acquiring authority cannot seek to modify it through administrative communications or by litigating new claims within a review proceeding.

The appellant, an owner of land measuring approximately 2021 square meters in Mandya District, saw his property acquired for the widening of NH-275. Following a dispute over compensation, a statutory Arbitrator passed an award on 21 September 2019, which recognized the converted residential nature of the land and enhanced the compensation payable. While the National Highways Authority of India (NHAI) initially sought to reopen the award via administrative communications to reduce their financial liability, the High Court had previously quashed these attempts in a writ petition. The NHAI then filed a review petition, successfully convincing the Single Judge to exclude 400 square meters of the acquired land from the compensation based on a condition in the original land conversion order.

The court was primarily called upon to determine whether the scope of review jurisdiction under the Code of Civil Procedure (CPC) permits a party to introduce new factual pleas to challenge a final arbitral award. It also addressed whether an administrative body can circumvent the finality of an arbitral determination by withholding compensation on grounds not raised during the statutory arbitration process.

Limited Scope of Review

The bench emphasized that the jurisdiction of review is strictly limited and cannot be conflated with appellate jurisdiction. By permitting the respondents to exclude 400 square meters of land based on a conversion order condition that was never presented before the Arbitrator, the Single Judge had essentially allowed a new case to be built. The court noted that if the respondents were aggrieved by the inclusion of this land, their remedy lay in challenging the arbitral award under the Arbitration and Conciliation Act, 1996 (A&C Act), which they failed to do.

Finality of Arbitral Awards

"Once the statutory Arbitrator had adjudicated the dispute and determined the compensation payable in respect of the acquired land and such determination had attained finality, the acquiring authority could not thereafter assume to itself the power to reopen or reconsider the determination by issuing an administrative communication."

The court underscored that the statutory scheme of the NH Act provides for a specific process of adjudication. Once the Arbitrator determines the compensation and that award attains finality, it is binding upon the parties. Allowing the NHAI to re-calculate compensation through administrative orders or belated review contentions would undermine the rule of law and the sanctity of arbitral proceedings.

Binding Precedent on Modification of Awards

"The Supreme Court in Project Director, National Highways Vs. M. Hakeem held that the Court exercising jurisdiction under Section 34 of the A&C Act does not possess a general power to modify an arbitral award, which reinforces the limited nature of jurisdiction available in respect of a concluded arbitral determination."

Citing the Supreme Court’s ruling in M. Hakeem, the bench clarified that even a court under Section 34 of the A&C Act cannot modify an award, let alone an administrative authority. Consequently, the High Court set aside the order passed in the review petition and restored the original mandate for the NHAI to disburse the full compensation as determined by the Arbitrator.

The High Court allowed the appeal, effectively reinforcing that finality in land acquisition compensation must be respected. Parties cannot be permitted to use the review process as a mechanism to rectify their own strategic failures to raise issues during the initial arbitral proceedings.

Date of Decision: 02 September 2026

Latest Legal News