-
by Admin
05 December 2025 4:19 PM
“Statutory obligations grounded in public interest cannot be waived by any individual or authority” – On 24 September 2025, the Supreme Court of India in a significant decision in Divyagna kumari Harisinh Parmar & Others v. Union of India & Others (2025 INSC 1145) upheld the authority of the Collector of Dadra and Nagar Haveli to rescind Portuguese-era land grants known as "Alvaras", originally issued between 1923 and 1930, on the ground of non-cultivation, despite the considerable lapse of time.
Rejecting claims of waiver, delay, acquiescence and estoppel, the Court emphasized that public lands held for cultivation cannot be retained indefinitely without fulfilling the purpose for which they were granted. The three-judge bench, comprising Justices Surya Kant, Dipankar Datta and Nongmeikapam Kotiswar Singh, ruled:
“The doctrine of waiver finds no application in matters concerning public interest or public policy... There can be no estoppel against the Government in the exercise of its legislative, sovereign, or executive powers.”
The decision ends a nearly 50-year legal battle and affirms the validity of rescission orders passed in 1974, shortly before the enforcement of the Dadra and Nagar Haveli Land Reforms Regulation, 1971, which abolished such grants and sought to create uniformity in land rights post-liberation from Portuguese rule.
“Party May Not Sleep On Land and Still Claim Title”: Non-Cultivation Justifies Rescission of Alvaras Even After Decades
“No statutory period of limitation is prescribed for rescinding an Alvara under Article 12 of the Organizacao Agraria” – Supreme Court holds Alvaras remain subject to condition of cultivation
At the heart of the dispute lay the nature and validity of “Alvaras” – land grants made under the Portuguese Land Grant Law, 1917, and specifically governed by the Organizacao Agraria (OA) of 1919, which applied exclusively to the Dadra and Nagar Haveli region.
The appellants claimed heritable and perpetual rights over agricultural lands granted under these Alvaras and challenged the 1974 rescission orders passed by the Collector under Article 12 of the OA, arguing that:
The government had "waived" its right by not acting for nearly five decades;
The failure to cultivate was due to “impossibility” or poor soil conditions;
Rescission should have followed formal legal proceedings;
The 1971 Regulation superseded the OA and entitled them to occupancy rights.
Rejecting all these contentions, the Court declared:
“The Alvaras were not granted for speculative or ornamental possession. They were conditional grants for cultivation. Non-cultivation, even decades later, constitutes valid ground for rescission.”
The Court found that Article 12 of the OA created a statutory right of rescission in favour of the Government, without the requirement of elaborate procedure. It was held that no separate adjudicatory process or limitation period is stipulated under the OA, and therefore the Collector’s action in 1974 was lawful, even if initiated nearly 40 years after the original grants.
“The mandate of Article 12 of the OA is clear – the grant may be rescinded without compensation in case of failure to cultivate... Neither waiver nor delay could override this express statutory power.”
“Inaction Does Not Amount to Intentional Waiver”: No Estoppel Against Sovereign Where Public Resources Are at Stake
“Public duty cannot be surrendered by conduct or delay… Doctrine of acquiescence has no application where public land is involved” – Supreme Court slams lower court findings
One of the key planks of the appellants’ case was that the Portuguese administration had effectively ‘waived’ the condition of cultivation, and that the Indian authorities had acquiesced in this position by remaining inactive for decades.
The Court unequivocally held that statutory duties—especially in relation to public land—cannot be waived either by government officials or by administrative inaction. It ruled:
“Waiver requires the intentional relinquishment of a known right… There is no evidence of such intentional act here.”
The Court cited its earlier rulings including Waman Shriniwas Kini v. Ratilal Bhagwandas and Lalchoo Mal v. Radhey Shyam, holding that mere delay or bureaucratic inaction does not amount to waiver or abandonment of statutory rights. The Bench stated:
“Mere long inaction will not amount to abandonment of right. Only on the basis of a finding that there was long delay in taking action, inference of acquiescence could not have been drawn.”
Importantly, the Court found that the Collector's rescission orders were not mala fide, but were part of a consistent administrative action that began with investigations and proceedings initiated in 1969, and followed through even after judicial remand orders in 1973. The bench held:
“There is no infirmity in the reasoning assigned by the Collector. It appears to have been rendered after due deliberation, consideration of the relevant circumstances, and following the applicable rules and regulations.”
“Article 12 Remained Fully Enforceable Despite Later Land Reforms”: 1971 Regulation Did Not Affect Collector’s Power to Rescind
“Section 57 of the 1971 Regulation saves all actions initiated under repealed Portuguese laws” – Supreme Court upholds continuity of law
Another serious argument pressed by the appellants was that once the Dadra and Nagar Haveli Land Reforms Regulation, 1971 came into force, Alvaras stood abolished, and only rights created under the new legislation could prevail.
However, the Collector’s rescission order was passed on 30 April 1974, just a day before the 1971 Regulation came into force on 1 May 1974. The appellants alleged that this timing showed mala fides and was aimed at pre-empting their claim to statutory occupancy rights under the new law.
The Court rejected this argument entirely, noting that proceedings had begun well before the Regulation came into force, and were protected by the savings clause under Section 57(2)(d). It was held:
“The applicability of the 1971 Regulation, in this scenario, is therefore a moot question. The Collector’s powers and actions fall squarely within the savings clause.”
The Bench observed that there was no conflict between the rescission under the OA and the rights potentially available under the 1971 Regulation, but that the Collector acted lawfully and within his jurisdiction under the then-prevailing law
“Concurrent Findings of Fact Can Be Reversed Where They Defeat Public Interest”: Supreme Court Backs High Court’s Intervention
“Findings based on misapplication of law or irrelevant considerations must be reversed in second appeal” – Court vindicates Bombay High Court’s judgment
The Trial Court (1978) and First Appellate Court (1983) had accepted the appellants’ contentions, holding the Alvaras to be heritable, perpetual and enforceable, and that the Portuguese and Indian administrations had both waived the condition of cultivation.But the Bombay High Court, in its 2005 judgment on second appeal, reversed those findings, declaring them legally unsustainable and contrary to public policy. The Supreme Court fully endorsed this view, holding:
“The High Court was justified in exercising its jurisdiction under Section 100 CPC to overturn perverse findings which ignored binding statutory provisions and principles of public interest.”The Court found that both the Trial and First Appellate Courts had misunderstood the Overseas Council judgment of Lisbon, and wrongly applied the 1917 General Portuguese Land Law, which had been superseded in Dadra and Nagar Haveli by the Organizacao Agraria of 1919.
“The High Court correctly applied the law governing the territory, namely the OA of 1919, and rightly found that the claimants had failed to fulfill the statutory conditions of their land grants.”
Cultivation Was the Condition, Not Just Possession – Title Cannot Survive Without Purpose
“Vigilantibus non dormientibus jura subveniunt – The law helps those who are vigilant, not those who sleep on their rights” – Supreme Court closes 50-year-old litigation
In a detailed and historically significant ruling, the Supreme Court has now closed the chapter on colonial Alvaras, at least for those who failed to cultivate the lands granted to them. The ruling underscores the principle of conditionality in land tenure, and the unwavering primacy of public interest over private delay.
However, showing a measure of equity and flexibility, the Court granted liberty to the appellants to apply afresh for occupancy rights under the 1971 Land Reforms Regulation, despite the passage of time:“If some of the Appellants have not been considered for occupancy rights under the 1971 Regulation, they may approach the Collector within six weeks. Such applications shall be entertained, notwithstanding the expiry of limitation.”
With that, the Supreme Court brings finality to a century-old dispute rooted in colonial legacy, by reaffirming that land titles cannot subsist without purpose, and statutory duties owed to the public cannot be waived by inaction or oversight
Date of Decision: 24 September 2025