-
by sayum
15 September 2026 7:25 AM
"Equities can be balanced by denying the appellants' interest for the period for which they did not approach the court." Bombay High Court, in a significant ruling dated September 8, 2026, held that while Section 5 of the Limitation Act, 1963 does not grant an independent power to alter statutory interest, a court may, as a condition for condoning delay in land acquisition appeals, require the claimant to waive interest on enhanced compensation for the specific period attributable to the delay.
A bench of Justice Amit Borkar observed that while the right to fair compensation must be protected, the state exchequer should not be burdened with interest liabilities arising solely from the claimant’s failure to approach the court in a timely manner.
Balancing Equities in Compulsory Acquisition
The matter arose from a group of appeals and applications where the court was tasked with determining the extent of its discretionary power when condoning delays in land acquisition matters. The primary concern was whether courts could impose "waiver of interest" conditions upon claimants seeking parity with other landowners who had already received higher compensation, effectively balancing the right to compensation against the state's liability for interest during the period of the claimant's inaction.
The court addressed five core questions regarding the interplay between Section 5 of the Limitation Act, the Land Acquisition Act, and the power of the appellate court. Specifically, the bench examined whether the court can condition condonation of delay upon an undertaking to waive interest, whether such conditions are permissible under Section 5, and whether these principles equally apply to cross-objections under Order XLI Rule 22 of the CPC.
Court Explains Scope Of Section 5 Discretion
The court clarified that Section 5 of the Limitation Act does not empower the court to cancel or alter statutory interest payable under Sections 28 or 34 of the Land Acquisition Act. However, the discretion to condone delay carries with it the power to regulate the relief granted to balance equities between the parties. Justice Borkar emphasized that the exclusion of interest must not be viewed as a penalty, but as a necessary regulatory measure to prevent the state from being held liable for interest during a period where the claimant failed to prosecute their rights.
"The object of Section 5 is not to punish a party merely because the proceeding was filed late. The object is to enable the Court to do substantial justice when there is a proper reason for the delay."
No Absolute Rule For Waiver
The court rejected the notion that the state should be categorically exempt from interest burdens. Instead, the exclusion must be confined to the specific period of delay. The court stressed that an undertaking obtained from a claimant must be precise and not a blanket waiver of all statutory benefits. The judicial order must clearly identify the period of delay and the specific interest (Section 28 or 34) being excluded, ensuring that the claimant is not deprived of interest for periods during which they were actively pursuing their legal remedies.
Equitable Principles Apply To Cross-Objections
The court further held that the principles governing appeals apply to cross-objections and cross-appeals. While noting that Order XLI Rule 22 provides a different procedural framework for cross-objections, the bench ruled that the appellate court, under its powers to extend time, may similarly exclude interest for the duration of the delay in filing the cross-objection if the facts of the case warrant such a course.
"The Court shall consider the length and reason for the delay, the conduct of the claimant, the stage of the proceedings, the nature of the claim, the claim for parity with similarly situated landowners, the circumstances in which the claimant approached the Court and the financial consequence of the delay to the acquiring authority."
The High Court concluded that no fixed duration of delay triggers a mandatory waiver of interest. Instead, the court must adopt a pragmatic approach, examining whether the claimant is seeking parity with similarly situated landowners and identifying the precise period of inaction. By ensuring the exclusion is limited to the period of delay, the court achieves a balance between ensuring just compensation for landholders and protecting public funds from unmerited interest accruals.
Date of Decision: 08 September 2026