Property Allotted In Lieu Of Ancestral Land Left In Pakistan Retains Coparcenary Character; Karta Cannot Gift It Away: Punjab & Haryana HC Bail Applicant Under 'Solemn Obligation' To Disclose Criminal History; Material Suppression Disentitles Discretionary Relief: Orissa High Court Mother Surreptitiously Marrying Away Daughter Without Father’s Knowledge Amount To Mental Cruelty: Madras High Court Grants Divorce Time Is Generally Not The Essence Of Contract In Sale Of Immovable Property; Unilateral Notice Cannot Alter Mutually Agreed Terms: Himachal Pradesh High Court Mere Use Of Surname No Defence If Adoption Is Dishonest & Causes Confusion In Pharma Trade: Delhi High Court Restrains 'Reddy Pharmaceuticals' Complainant’s Failure To Provide Specific Loan Details & Evidence Of Parties' Involvement In Ponzi Scheme Rebuts Section 139 NI Act Presumption: Calcutta High Court Statutory Mandate Of Section 17-B: Payment Of Minimum Wages Means Revised Rates From Time To Time, Not Frozen Amount: Delhi High Court Reporting Court Proceedings & Good Faith Complaints To Authorities Not Defamation: Allahabad High Court Quashes Summoning Order Appointment Obtained Via Fraud Vitiates Initial Entry; Article 311 Protection Not Available To Such Employees: Allahabad High Court Surviving Spouse’s Elevation To Second In Line Of Succession Not ‘Manifestly Arbitrary’: Bombay High Court Upholds Goa Succession Act Amendments Patent Rights Stand Exhausted Once Components Are Sourced From Authorized Market Dealers; Royalty Cannot Be Calculated On Entire Product: Delhi High Court FCI Cannot Unilaterally Reduce Rent Or Recover 'Excess' Payment Without Landlord's Consent & Notice: Punjab & Haryana High Court Judicial Sanctity Cannot Be Given To Adulterous Relationships; No Habeas Corpus For Married Woman Living With Husband: Himachal Pradesh High Court Recoveries From Open Spaces Without Proof Of Concealment Don't Qualify Under Section 27 Evidence Act: Supreme Court Large Time Gap In 'Last Seen Together' Theory Snaps Chain Of Circumstances; Supreme Court Acquits Murder Accused Non-Recovery Of Mobile Phone Or Video Not Fatal To Criminal Intimidation Charge If Victim's Testimony Is Credible: Supreme Court Threat To Upload Private Video Online Violates Woman's Sexual Autonomy, Amounts To 'Imputing Unchastity' Under Sec 506 IPC: Supreme Court Intention To Kill Essential For Section 307 IPC Conviction; Nature Of Injury Not Sole Determinant: Supreme Court Intention To Commit Murder Cannot Be Presumed Merely Because Injury Was Dangerous To Life: Supreme Court Alters Conviction To Section 325 IPC Supreme Court Cancels Bail Of Accused Who Absconded For 42 Days Post-Bail Revocation; Says Contumacious Conduct Bars Fresh Relief High Court Cannot Grant Fresh Bail By Ignoring Supreme Court’s Earlier Order Cancelling Bail Without Change In Circumstances: Supreme Court Mutation Entries Supported By Registered Sale Deeds For Long Period Relevant To Establish Possession: Supreme Court Allegation Of Fraud In Registered Documents Must Be Supported By Foundational Facts; Adverse Inference Drawn If Plaintiff Avoids Witness Box: Supreme Court Commercial Courts Must Assign Reasons For Not Passing Conditional Orders In Summary Judgment Applications: Calcutta High Court Friendly Loan Without Commercial Consideration Not A 'Legally Enforceable Debt' Under Section 138 NI Act: Jharkhand High Court Commercial Courts Act: ₹3 Lakh ‘Specified Value’ Amendment Is Self-Operative; No Separate Govt Notification Required: Andhra Pradesh HC Full Bench Drug Inspector’s Prosecution Voids If Specific Area Of Jurisdiction Is Not Notified In Official Gazette: Kerala High Court Order 41 Rule 27 CPC | Photostat Copies Of Sale Deeds Not Admissible As Additional Evidence To Fill Gaps In Trial Stage: Punjab & Haryana HC

Supplemental Agreement Signed Under Threat Of Contract Termination Cannot Negate Contractor's Claim For Extra Expenditure: Kerala High Court

20 March 2026 7:50 PM

By: sayum


"Agreements executed under compelling circumstances cannot be foisted upon the plaintiff to negate the additional expenditure incurred during the extended period", Kerala High Court on March 19, 2026 partly allowed an appeal filed by the State of Kerala against a decree granted to a contractor for extra expenditure incurred due to delay in completing an irrigation canal construction work.

A Division Bench of Justice Sathish Ninan and Justice P. Krishna Kumar held that supplemental agreements executed under threat of contract termination are not binding to defeat legitimate claims, that the expert's calculation was erroneous in adding tender excess over market rates, and that since both parties shared responsibility for the delay, the contractor was entitled to only one-half of the extra expenditure assessed.

The respondent-contractor was awarded the work of constructing the MVIP Kuravilangad distributory under an agreement dated October 5, 2007, with a completion deadline of October 7, 2008. The work was completed only on July 31, 2009, due to public agitation against blasting of rocks, a Panchayat stop memo, police interference, and interim injunctions obtained by local residents in two suits before the Munsiff's Court, Pala. The contractor filed a suit claiming extra expenditure incurred during the extended period. The trial court decreed ₹60,70,071/- with 6% interest based on an expert report.

Whether the contractor was responsible for the delay; whether supplemental agreements precluded the claim for enhanced rates; whether the expert's calculation of extra expenditure was correct; and whether the Supreme Court's ruling in General Manager, Northern Railway v. Sarvesh Chopra barred the claim.

Shared Responsibility for Delay — Neither Party Wholly to Blame

The Court found that the contractor could not entirely escape responsibility for the delay by sheltering behind the suits and Panchayat proceedings — the injunctions only restrained blasting operations not sanctioned under law and did not impose an absolute prohibition. However, the Court held equally that the contractor could not be held solely responsible. Critically, there was no evidence that the State made any attempt to intervene and ensure smooth execution of the work. "It cannot be said that the plaintiff was solely responsible for the delay — the defendants also failed to take any steps to ensure that the work was smoothly carried out." On the totality of facts, the Court awarded one-half of the assessed extra expenditure.

Expert's Calculation Erroneous — Tender Excess Cannot Be Added to Market Rate

The expert had assessed extra expenditure at market rates prevailing during 2008-09 and then added a 40% tender excess on top. The Court found this calculation plainly erroneous. The tender excess of 40% over PAC was a feature of the original 2004 schedule of rates — it reflected the contractor's premium over the schedule at the time of tendering. Once the expert had already assessed costs at actual 2008-09 market rates, adding the tender excess amounted to double-counting. "When the expert had assessed the cost at the market rate that prevailed during the period 2008-09, the tender excess could not have been added to it — such calculation is apparently erroneous."

Supplemental Agreements Under Compulsion Not Enforceable

The State relied on supplemental agreements wherein the contractor had undertaken to carry out extended work at the original contract rates. The trial court had found — and the High Court affirmed — that refusal to execute these agreements would have resulted in termination of the contract, leaving the contractor with no choice. Agreements wrested under such compelling circumstances and threat of termination cannot be used to defeat a contractor's legitimate claim for additional expenditure actually incurred during the extended period. The Court declined to follow General Manager, Northern Railway v. Sarvesh Chopra on the facts, holding that pinning the contractor to 2004 schedule of rates for work completed in 2008-09 would be harsh and inequitable.

The Court accordingly modified the decree to ₹24,53,677/- — comprising ₹20,09,108/- being one-half of the corrected extra expenditure and ₹4,44,569/- being the retained amount — with interest at 6% per annum from the date of suit till realisation, along with proportionate costs.

Date of Decision: March 19, 2026

 

Latest Legal News