Victim Has Locus To Request Court To Summon Witnesses Under Section 311 CrPC In State Prosecution: Allahabad High Court Order 2 Rule 2 CPC Cannot Be Ground to Reject a Plaint: Supreme Court Draws Crucial Distinction Between Bar to Sue and Bar by Law No Right to Lawyer Before Advisory Board in Preventive Detention — Unless Government Appears Through Legal Practitioner: Supreme Court Wife's Dowry Statement Cannot Be Used to Prosecute Her for 'Giving' Dowry: Supreme Court Upholds Section 7(3) Shield Husband's Loan Repayments Cannot Reduce Wife's Maintenance: Supreme Court Raises Amount to ₹25,000 From ₹15,000 Prisoners Don't Surrender Their Rights at the Prison Gate: Supreme Court Issues Binding SOP to End Delays in Legal Aid Appeals A Judgment Must Be a Self-Contained Document Even When Defendant Never Appears: Supreme Court on Ex Parte Decrees Court Cannot Dismiss Ex Parte Suit on Unpleaded, Unframed Issue: Supreme Court Sets Aside Specific Performance Decree Denied on Title Erroneous High Court Observations Cannot Be Used to Stake Property Claims: Supreme Court Steps In to Prevent Misuse of Judicial Observations No Criminal Proceedings Would Have Been Initiated Had Financial Settlement Succeeded: Supreme Court Grants Anticipatory Bail In Rape Case Directors Cannot Escape Pollution Law Prosecution by Claiming Ignorance: Allahabad High Court Refuses to Quash Summons Against Company Directors Order 7 Rule 11 CPC | Court Cannot Peek Into Defence While Rejecting Plaint: Delhi High Court Death 3½ Months After Accident Doesn't Break Causal Link If Doctors Testify Injuries Could Cause Death: Andhra Pradesh High Court LLB Intern Posed as Supreme Court Advocate, Used Fake Bar Council Card and Police Station Seals to Defraud Victims of Rs. 80 Lakhs: Gujarat High Court Rejects Anticipatory Bail Husband Who Travels to Wife's City on Leave, Cohabits With Her, Then Claims She 'Never Lived With Him' Cannot Prove Cruelty: Jharkhand High Court Liquor Licence Is a State Privilege, Not a Citizen's Right — No Vested Right of Renewal Survives a Change in Rules: Karnataka High Court Sets Aside Stay on E-Auction Policy Court Holiday Cannot Save Prosecution From Default Bail: MP High Court No Search At Your Premises, No Incriminating Document, No Case: Rajasthan HC Quashes Rs. 18 Crore Tax Assessment Under Section 153C Limitation Act | Litigant Cannot Be Punished For Court's Own Docket Load: J&K High Court

Supplemental Agreement Signed Under Threat Of Contract Termination Cannot Negate Contractor's Claim For Extra Expenditure: Kerala High Court

20 March 2026 7:50 PM

By: sayum


"Agreements executed under compelling circumstances cannot be foisted upon the plaintiff to negate the additional expenditure incurred during the extended period", Kerala High Court on March 19, 2026 partly allowed an appeal filed by the State of Kerala against a decree granted to a contractor for extra expenditure incurred due to delay in completing an irrigation canal construction work.

A Division Bench of Justice Sathish Ninan and Justice P. Krishna Kumar held that supplemental agreements executed under threat of contract termination are not binding to defeat legitimate claims, that the expert's calculation was erroneous in adding tender excess over market rates, and that since both parties shared responsibility for the delay, the contractor was entitled to only one-half of the extra expenditure assessed.

The respondent-contractor was awarded the work of constructing the MVIP Kuravilangad distributory under an agreement dated October 5, 2007, with a completion deadline of October 7, 2008. The work was completed only on July 31, 2009, due to public agitation against blasting of rocks, a Panchayat stop memo, police interference, and interim injunctions obtained by local residents in two suits before the Munsiff's Court, Pala. The contractor filed a suit claiming extra expenditure incurred during the extended period. The trial court decreed ₹60,70,071/- with 6% interest based on an expert report.

Whether the contractor was responsible for the delay; whether supplemental agreements precluded the claim for enhanced rates; whether the expert's calculation of extra expenditure was correct; and whether the Supreme Court's ruling in General Manager, Northern Railway v. Sarvesh Chopra barred the claim.

Shared Responsibility for Delay — Neither Party Wholly to Blame

The Court found that the contractor could not entirely escape responsibility for the delay by sheltering behind the suits and Panchayat proceedings — the injunctions only restrained blasting operations not sanctioned under law and did not impose an absolute prohibition. However, the Court held equally that the contractor could not be held solely responsible. Critically, there was no evidence that the State made any attempt to intervene and ensure smooth execution of the work. "It cannot be said that the plaintiff was solely responsible for the delay — the defendants also failed to take any steps to ensure that the work was smoothly carried out." On the totality of facts, the Court awarded one-half of the assessed extra expenditure.

Expert's Calculation Erroneous — Tender Excess Cannot Be Added to Market Rate

The expert had assessed extra expenditure at market rates prevailing during 2008-09 and then added a 40% tender excess on top. The Court found this calculation plainly erroneous. The tender excess of 40% over PAC was a feature of the original 2004 schedule of rates — it reflected the contractor's premium over the schedule at the time of tendering. Once the expert had already assessed costs at actual 2008-09 market rates, adding the tender excess amounted to double-counting. "When the expert had assessed the cost at the market rate that prevailed during the period 2008-09, the tender excess could not have been added to it — such calculation is apparently erroneous."

Supplemental Agreements Under Compulsion Not Enforceable

The State relied on supplemental agreements wherein the contractor had undertaken to carry out extended work at the original contract rates. The trial court had found — and the High Court affirmed — that refusal to execute these agreements would have resulted in termination of the contract, leaving the contractor with no choice. Agreements wrested under such compelling circumstances and threat of termination cannot be used to defeat a contractor's legitimate claim for additional expenditure actually incurred during the extended period. The Court declined to follow General Manager, Northern Railway v. Sarvesh Chopra on the facts, holding that pinning the contractor to 2004 schedule of rates for work completed in 2008-09 would be harsh and inequitable.

The Court accordingly modified the decree to ₹24,53,677/- — comprising ₹20,09,108/- being one-half of the corrected extra expenditure and ₹4,44,569/- being the retained amount — with interest at 6% per annum from the date of suit till realisation, along with proportionate costs.

Date of Decision: March 19, 2026

 

Latest Legal News