Plaintiff In Title Suit Must Prove Own Case On Independent Evidence, Cannot Rely On Weakness Of Defence: Supreme Court Advocate Commissioner's Failure To Localize Land Per Title Deeds Fatal To Encroachment Claim: Andhra Pradesh High Court Enmity Is A Double-Edged Weapon, Can Be Motive For False Implication As Much As For Crime: Allahabad High Court Parity In Bail: Karnataka High Court Grants Relief To Accused In Robbery Case As Mastermind & Main Offenders Were Already Enlarged Specific Performance Denied If Buyer Fails To Prove Continuous Readiness With Funds; Part-Payment Can't Be Forfeited Without Specific Clause: Delhi High Court Seized Vehicles Shouldn't Be Kept In Police Stations For Long, Courts Must Judiciously Exercise Power To Release On Supurdagi: Madhya Pradesh High Court Prolonged Incarceration Militates Against Article 21, Constitutional Principles Must Override Section 37 NDPS Rigors: Punjab & Haryana High Court Onus On Individual To Prove Claim Of 'Fear Of Religious Persecution' For Exemption Under Foreigners Act: Calcutta High Court Direct Recruits Cannot Claim Seniority From A Date Prior To Their Entry Into The Cadre: Orissa High Court Sale Deed Executed After Land Vests In State Confers No Title; Post-Vesting Purchaser Can’t Claim Compensation: Calcutta High Court No Right To Blanket Regularization For Contractual Staff; State Must Timely Fill Sanctioned Vacancies Under Reserved Quota: Supreme Court Non-Signatory Collaborator Under 'Deed Of Joint Undertaking' Can Invoke Arbitration Clause As A 'Veritable Party': Supreme Court Insolvency Proceedings Cannot Be Used As Coercive Recovery Mechanism For Complex Contractual Disputes: Supreme Court Legal Heirs Who Were Parties To Sale Cannot Challenge Transfer Under PTCL Act After Long Delay: Supreme Court SC/ST Act | Proceedings To Annul Sale Illegal If Initiated By Legal Heirs Who Were Parties To The Transaction: Supreme Court Consumers Cannot Be Burdened With Tariff Charges Beyond Period Of Service Delivery: Supreme Court Mere Non-Production Of Old Selection Records Or Non-Publication Of All Candidates' Marks No Ground To Direct Appointment: Supreme Court Bombay High Court Dismisses Appeals Against Acquittal In Sohrabuddin Shaikh Encounter Case; Says Prosecution Failed To Prove Conspiracy Dishonour Of Cheque Due To Signature Mismatch Or Incomplete Signature Attracts Section 138 NI Act: Supreme Court 138 NI Act | High Court Cannot Let Off Accused In NI Act Case By Ordering Only Cheque Amount Payment Without Interest Or Penalty: Supreme Court

Non-Signatory Collaborator Under 'Deed Of Joint Undertaking' Can Invoke Arbitration Clause As A 'Veritable Party': Supreme Court

08 May 2026 12:06 PM

By: sayum


"Contract by itself necessitated the execution of joint undertaking by the Contractor and the Collaborator who had the ‘joint and several’ liability for the due completion of the contract. The arbitration clause applied both to the Collaborator and the Contractor in so far as the disputes with the Employer, " Supreme Court, in a significant ruling dated May 07, 2026, held that a technical collaborator who executes a 'Deed of Joint Undertaking' (DJU) and assumes "joint and several liability" for a project becomes an inextricable part of the contract.

A bench of Justice Sanjay Kumar and Justice K. Vinod Chandran observed that such a collaborator is a "veritable party" to the arbitration agreement, even if they were not a formal signatory to the primary contract. The Court emphasized that when an Employer calls upon a collaborator to fulfill obligations due to a contractor's default, they cannot later plead lack of privity to deny arbitration.

The dispute arose from a contract for a Coal Handling Plant at the Nabinagar Thermal Power Project. The 2nd Respondent (Contractor) had collaborated with Elecon Engineering (Appellant/Collaborator) to meet technical eligibility criteria, executing a Deed of Joint Undertaking (DJU) in favor of the Employer (1st Respondent). Following the Contractor's liquidation in 2020, the Employer demanded the Collaborator take full responsibility for the project. However, when the Collaborator sought arbitration under Section 11(6) of the Arbitration and Conciliation Act, 1996, the High Court rejected the plea citing a lack of privity of contract.

The primary question before the Court was whether a collaborator, essential for the technical qualification of a contractor and bound by a DJU, qualifies as a "veritable party" to the arbitration agreement. The Court also examined whether the subsequent tripartite agreement and communications from the Employer established an inextricable connection between the parties that would allow a non-signatory to invoke arbitration.

Non-Signatories Can Invoke Arbitration As Veritable Parties

The Supreme Court began by noting the established legal principle that even non-signatories to an agreement containing an arbitration clause can invoke it if they are found to be a "veritable party" to the agreement. The bench observed that the High Court had acknowledged this trite principle but erred in its application by failing to find an "inextricable connection" in the notice issued under Section 21 of the Act of 1996.

Collaborator Was Inseparable From Contractual Execution

The Court highlighted that the initial bid documents specifically required the bidder to satisfy eligibility through collaborations, necessitating a DJU for the successful performance of the relevant system. The bench noted that without the Appellant's expertise in design and commissioning, the Contractor would not have qualified for the project.

"The DJU was executed by the Collaborator with the Contractor, in favour of the Employer which clearly indicates that the Collaborator was an inseparable part of the contract and its execution."

Employer Reaffirmed Obligations Despite Contractor's Liquidation

The bench scrutinized the conduct of the Employer following the Contractor’s liquidation in 2020. It was noted that the Employer had issued communications threatening to execute balance work at the "risk and cost of the Collaborator." The Court found that these demands were a direct reaffirmation of the Collaborator's obligations under the original contract and the DJU.

Tripartite Agreement Did Not Eclipse Arbitration Clause

The Court addressed the argument that a subsequent tripartite agreement between the parties lacked an arbitration clause. The bench held that the tripartite agreement was merely a measure to ensure direct payments to the Collaborator and did not "wipe out" the earlier contract. It observed that the tripartite agreement specifically authorized payments to the Collaborator for outstandings, further cementing their status as a primary stakeholder in the project's completion.

Joint And Several Liability Triggers Arbitration Clause

The Court placed heavy reliance on the nature of the liability assumed by the Appellant. It noted that the contract necessitated a joint undertaking where the Contractor and the Collaborator held "joint and several" liability for the due completion of the project. This legal standing, the Court reasoned, made the arbitration clause applicable to both entities in their disputes with the Employer.

"The communications addressed to the collaborator to take up his responsibility as per the DJU makes the Collaborator a veritable party to the contract who is also entitled to invoke the arbitration clause as available in the contract."

Finding that the High Court had "wrongly declined" the prayer for arbitration, the Supreme Court set aside the impugned judgment. Exercising its powers under Section 11(6) of the Act of 1996, the Court appointed Justice (Retd.) Chakradhari Sharan Singh, former Chief Justice of the Orissa High Court, as the sole Arbitrator. The Court directed the Arbitrator to proceed in accordance with the law and make a declaration in terms of Section 12 of the Act within 15 days of receiving the judgment.

The ruling reinforces the "Group of Companies" and "Veritable Party" doctrines in Indian arbitration law. It establishes that where a party’s participation is essential for a contract’s technical qualification and they assume joint liability via secondary undertakings like a DJU, they cannot be excluded from the dispute resolution framework of the main contract.

Date of Decision: May 07, 2026

 

Latest Legal News