-
by Admin
07 May 2024 2:49 AM
One Who Appropriates Benefits of Acquisition Cannot Later Challenge It – Karnataka High Court in a significant ruling dismissed the challenge to land acquisition proceedings for the establishment of a Mega Market by the Agricultural Produce Marketing Committee (APMC). The case, Jamnalal Bajaj Seva Trust v. State of Karnataka & Others, W.P. No. 37140/2000 (LA-RES) c/w W.P. No. 3884/1999 (LA-RES), involved objections raised by the petitioners on grounds of delay, procedural irregularities, and alleged abandonment of the project.
Justice Krishna S. Dixit, delivering the judgment, observed, “When a party has participated in compensation proceedings and accepted benefits under the acquisition process, they cannot later challenge the same. A party cannot approbate and reprobate.” The Court rejected the argument that the acquisition lapsed under Section 11A of the Land Acquisition Act, 1894, ruling that judicially imposed delays must be excluded from the statutory period. The Court also held that invocation of the urgency clause was justified as the project served an agrarian purpose and that the claim of project abandonment was unsubstantiated.
The Court directed the authorities to pay compensation to the petitioners with 12% per annum interest from the date of the award. If payments were delayed, an additional 1% per month penalty was to be imposed, recoverable from responsible officials.
“Urgency Clause in Land Acquisition Requires No Cartload of Reasons”
The petitioners challenged the invocation of the urgency clause under Section 17(3A) of the Land Acquisition Act, 1894, arguing that it was applied arbitrarily and without fulfilling the statutory requirement of paying 80% compensation before taking possession. The Court, however, held that the urgency clause was properly invoked.
“The very purpose of invoking the urgency clause is to accomplish a task on a fast track, if not on a war footing. The authority need not assign a cartload of reasons for that,” Justice Dixit observed.
The Court noted that the Mega Market project aimed to benefit agriculturists and agrarian trade, making it a valid public purpose. The records showed that several meetings had been conducted at the highest levels of government before the decision was finalized. Rejecting the challenge, the Court ruled, “Steps aimed at agrarian reforms, the term being construed in its widest amplitude, have constitutional support. Therefore, it cannot be gainfully contended that the project does not serve a public purpose.”
On the issue of compensation payment, the Court acknowledged that the State had deposited a substantial portion of the 80% compensation, but a portion was withheld due to pending land ceiling proceedings under the Karnataka Land Reforms Act, 1961. The Court found that this was a valid reason for the delay and held that the petitioners could not claim invalidation of the acquisition based on this ground.
"Judicial Delay Cannot Be a Ground for Lapse of Acquisition"
The petitioners contended that the acquisition had lapsed under Section 11A of the Land Acquisition Act, 1894, since there was an excessive delay between the notification and the award. The Court rejected this argument, holding that periods of judicial stay must be excluded from the computation of statutory timelines.
“If the delay was caused by court-imposed stays, the statutory period excludes such periods,” the Court held.
The Court relied on the Supreme Court’s ruling in First Land Acquisition Collector v. Norodhi Prakash, which held that judicial delays cannot be counted against the State for lapse of acquisition proceedings. Justice Dixit emphasized that acquisition could not be held to have lapsed merely because of prolonged litigation initiated by various parties, including the petitioners themselves.
"Those Who Accept Compensation Cannot Later Challenge the Acquisition"
The petitioners had actively participated in compensation determination meetings and had accepted a substantial portion of the compensation, before returning it years later after a Single Judge erroneously ruled that the acquisition had lapsed under the 2013 Act (a ruling subsequently overturned by the Supreme Court).
“When a party negotiates compensation and accepts payments, it cannot later turn around and challenge the acquisition. The doctrine of acquiescence bars such conduct,” the Court stated.
The Court referred to Delhi Airtech Services Pvt. Ltd. v. State of U.P., where it was held that accepting compensation amounts to consenting to the acquisition. Further reliance was placed on Roy Rodrigues v. Government of Karnataka, where the Court had ruled that seeking compensation precludes the landowner from later challenging the acquisition itself.
The records revealed that the petitioners had engaged in negotiations regarding compensation rates and even executed an indemnity bond in this regard. The Court observed, “One who expects fairness should also reciprocate the same. A party cannot accept compensation for over a decade, only to later argue that the acquisition itself was illegal.”
"No Proof That The Project Was Abandoned"
The petitioners claimed that the APMC had shifted the project elsewhere, rendering the acquisition futile. However, the Court found no judicial finding to support this claim.
“The alleged statement in a collateral proceeding does not constitute a judicial finding of project abandonment. The burden was on the petitioners to prove that the project was formally abandoned, which they failed to do,” the Court held.
Further, the Court noted that the APMC had filed an application for clarification regarding the status of the project, reinforcing the position that the acquisition remained valid.
"Fair Balance Struck: Landowners to Get Just Compensation with Interest, But Public Project to Continue"
Dismissing the writ petitions, the Karnataka High Court upheld the validity of the land acquisition and directed that: “The petitioners shall be paid compensation for the subject lands at the rates agreed to in the meeting held on 24.09.1999, forthwith by formally accomplishing the acquisition proceedings in accordance with law.”
“The official respondents shall pay the petitioners interest at the rate of 12% per annum, in addition to what is payable under the provisions of the 1894 Act, from the date of the award, within three months.”
“If delay is brooked in making the payment, the petitioners shall be entitled to 1% additional interest per month, recoverable from the responsible officials.”
Justice Krishna S. Dixit concluded, "A fair balance has been struck—landowners receive just compensation with interest, while a critical agrarian project is allowed to proceed. The doctrine of eminent domain must be exercised with fairness, but procedural delays caused by litigation cannot be a reason to derail public interest projects.”
Date of Decision: February 3, 2025