Readiness and Willingness Under Section 16(c) Is Not a Ritualistic Phrase — Plaintiff Must Prove It With Substance, Not Just Words: Karnataka High Court FIR in Disproportionate Assets Case Quashed: Patna High Court Slams SP for 'Non-Application of Mind' and 'Absence of Credible Source Information' Ownership of Vehicle Linked to Commercial Quantity of Heroin – Custodial Interrogation Necessary: Punjab & Haryana High Court Denies Anticipatory Bail under Section 482 BNSS Death Caused by Rash Driving Is Not a Private Dispute — No FIR Quashing on Basis of Compromise in Section 106 BNS Cases: Punjab & Haryana High Court No Bank Can Override Court Orders: Rajasthan High Court Slams Axis Bank for Unauthorized Withdrawal from Court-Ordered FD" Indian Courts Cannot Invalidate Foreign Arbitral Awards Passed Under Foreign Law: Madhya Pradesh High Court Enforces Texas-Based Award Despite Commercial Court’s Contrary Decree Sudden Quarrel over Mound of Earth — Not Murder but Culpable Homicide: Allahabad High Court Eligibility Flows from Birth, Not a Certificate Date: Delhi High Court Strikes Down Rule Fixing Arbitrary Cut-Off for OBC-NCL Certificates in CAPF (AC) Recruitment Bar Under Order II Rule 2 CPC Cannot Be Invoked Where Specific Performance Was Legally Premature Due To Statutory Impediments: P&H High Court Calling Wife by Her Caste Name in Public Just Before Suicide is Immediate Cause of Self-Immolation: Madras High Court Upholds Husband’s Conviction Under Section 306 IPC No Work No Pay Is Not a Universal Rule: Punjab & Haryana High Court Dock Identification Without Prior TIP Is Absolutely Useless: P&H High Court Upholds Acquittal in Attempt to Murder Case Filing Forged Court Pleadings in Union Government’s Name is Criminal Contempt: Karnataka High Court Sentences Litigant to Jail Execution of Will Proved, But Probate Justly Denied Due to Concealment of Property Sale: Delhi High Court Mere Designation Doesn’t Establish Criminal Liability: Bombay High Court Quashes Proceedings Against ICICI Officials in Octroi Evasion Case Fraud on Power Voids the Order: Supreme Court Quashes FIR Against Karnataka BJP Leader R. Ashoka, Slams Politically Motivated Prosecution Cause of Fire Is Immaterial If Fire Itself Is Insured Peril: Supreme Court Rebukes Insurer’s Repudiation Dragging a Trained Army Officer Up 20 Steps Without Resistance? The Story Lacks Credence: Supreme Court Upholds Acquittal in Army Officer’s Murder Semen Stains Alone Do Not Prove Rape: Supreme Court Acquits Doctor Accused of Rape No Mortgage, No SARFAESI: Supreme Court Rules Against NEDFi, Says Recovery Action in Nagaland Without Security Agreement Was Illegal Parity Cannot Be Denied by Geography: Supreme Court Holds Jharkhand Bound by Patna HC's Judgment, Orders Pay Revision for Industries Officer Once Power Flows Continuously from a Synchronized Turbine, It Is No Longer Infirm: Supreme Court Orders TANGEDCO to Pay Fixed Charges to Penna Electricity

Debarment Amounts to Civil Death: Delhi High Court Upholds MCD's Five-Year Debarment of Contractor for Delayed Project

14 December 2024 6:49 PM

By: sayum


The Delhi High Court has dismissed a writ petition challenging the Municipal Corporation of Delhi's (MCD) decision to debar R. Krishnamurthy and Co. from participating in any tender for five years. The bench, led by Justice Subramonium Prasad, upheld the MCD's debarment order, emphasizing the significant delay in completing the construction of underground multi-level car parkings, which caused inconvenience to the public.

The case stems from a contractual agreement between MCD and Pratibha Industries Ltd. for constructing underground multi-level car parkings at New Friends Colony, Jangpura, and Kalkaji, which was supposed to be completed within 15 months. Disputes arose, leading to a Memorandum of Understanding between Pratibha Industries Ltd. and R. Krishnamurthy and Co., assigning the project to the latter with a 120-day completion deadline. Despite extensions and a conciliated agreement, the project remained incomplete, prompting MCD to issue a show-cause notice and subsequently debar the petitioner.

The court found that the MCD had sufficient grounds for debarment. "The petitioner had to complete the work by December 2018, and there was no explanation for the delay beyond August 2021," Justice Prasad noted, emphasizing the prolonged public inconvenience due to non-completion of the project.

The court addressed the principle of proportionality, asserting that the debarment was neither unduly harsh nor disproportionate to the misconduct. Justice Prasad highlighted the petitioner’s significant delay and lack of substantial reasons for non-completion, stating, "The punishment imposed does not warrant any interference as it is neither shocking nor disproportionate to the infraction."

The judgment reiterated the limits of judicial review in contractual disputes, stressing that courts should not delve into factual thickets requiring evidence. The court cited precedents where factual disputes in contract breaches were deemed inappropriate for adjudication under Article 226 of the Constitution.

The court's decision leaned heavily on established legal principles surrounding debarment and contractual obligations. It referenced previous judgments, asserting that while reasons for administrative actions must be recorded, their communication to the blacklisted entity is not mandatory if the decision-making process is sound. "Judicial review generally speaking, is not directed against a decision, but against the decision-making process," the court observed, citing Ranjit Thakur v. Union of India.

Justice Subramonium Prasad remarked, "The punishment imposed by Respondent No.1, therefore, does not warrant any interference as the same is neither shocking nor is it disproportionate to the infraction on the part of the Petitioner."

The dismissal of the writ petition underscores the judiciary's stance on maintaining strict adherence to contractual timelines and the proportionality of punitive measures. The decision reinforces the principle that significant project delays causing public inconvenience justify severe administrative actions like debarment. This judgment is likely to influence future cases involving contractual compliance and administrative fairness.

Date of Decision: 19th January 2024

Latest Legal News