-
by Admin
08 January 2026 5:25 AM
“Section 21 is procedural rather than jurisdictional—it does not condition or limit the Tribunal’s jurisdiction to adjudicate claims not specifically referred at the threshold” — Supreme Court
In a powerful reaffirmation of arbitral autonomy and contractual interpretation, the Supreme Court of India on 5 January 2026 delivered a landmark ruling in M/s Bhagheeratha Engineering Ltd. v. State of Kerala, holding that a party cannot use the absence of a separate Section 21 notice as a tool to undermine an arbitral award when its own conduct effectively waived such objections. The Court set aside the Kerala High Court’s 2025 judgment that had nullified an arbitral award of ₹1.99 crore in favour of a road contractor, and emphatically reinstated the tribunal’s authority to decide all disputes referred under a broad arbitration clause.
“Conduct Is Louder Than Objections”: Supreme Court Finds Kerala State Had Waived Procedural Claims
The Court sharply criticized the State for raising objections that were never pressed before the arbitral tribunal or the district court, holding:
“The conduct of the respondent clearly precluded it from relying on Clause 24, 24.1, and 25 to contend that the appellant was foreclosed from raising the entire dispute before the Arbitrator.”
Rejecting the High Court’s view that only one dispute (relating to price adjustment for bitumen) had been validly referred to arbitration, the Bench observed that the respondent itself had reopened all four disputes by questioning the Adjudicator’s decision in entirety. In fact, it was the State which invited arbitration, nominated its arbitrator, and sought the appellant’s cooperation to constitute the tribunal—actions that the Supreme Court found incompatible with a restrictive interpretation of the reference.
Justice Viswanathan, authoring the decision, remarked:
“It will be a travesty of justice if the appellants, for the fault of the respondents, are denied the right to have recourse to arbitration.”
“Notice Under Section 21 Is Not a Jurisdictional Precondition to Raise Additional Claims”
At the heart of the dispute was whether the contractor was barred from raising three other claims (Disputes 2–4) before the Arbitral Tribunal due to absence of individual notices under Section 21 of the Arbitration and Conciliation Act, 1996.
In a sweeping clarification, the Court held:
“Section 21 is concerned only with determining when arbitration is deemed to have commenced for the specific dispute mentioned in the notice... it does not serve to create or validate the arbitration agreement itself, nor is it a precondition for the existence of the Tribunal’s jurisdiction.”
Drawing from its own ruling in ASF Buildtech v. Shapoorji Pallonji (2025), the Court reiterated that Section 21 is purely procedural and cannot be elevated into a barrier that restricts the Tribunal from deciding all disputes contemplated under a comprehensive arbitration clause.
The Bench cautioned against reading jurisdictional limitations into procedural mechanisms and stated:
“Any restriction on the nature or content of claims, counterclaims, or set-offs in arbitration must be sourced solely from the express language of Section 23 and not from Section 21.”
“Waiver Under Section 4 Applies When Party Participates Without Objection”
The Court was also emphatic that the State of Kerala had waived any procedural irregularity under Section 4 of the Arbitration Act by its active and continued participation in the arbitral process without timely objections.
It noted that:
The Supreme Court saw no procedural defect in the tribunal’s constitution and found that the State was estopped from raising belated technical objections. As held in M.K. Shah Engineers v. State of M.P., the Court reminded:
“No one can be permitted to take advantage of their own wrong... The party at fault cannot be permitted to set up the bar of non-performance of a prerequisite obligation so as to exclude the applicability and operation of the arbitration clause.”
“Arbitration Clause Is Not a Straitjacket”: Broad Arbitration Agreement Allowed Tribunal to Decide Entire Dispute
Interpreting Clause 25.3 of the contract, the Supreme Court noted that it allowed reference of “any dispute or difference arising between the parties relating to any matter arising out of or connected with the agreement”. This, the Court held, was broad enough to cover all four disputes, irrespective of whether they were expressly mentioned in the initial notice.
The Court invoked the authority of State of Goa v. Praveen Enterprises and explained:
“The claimant is not bound to restrict his statement of claim to the claims already raised by him by notice, unless the arbitration agreement expressly requires such limitation.”
It also clarified that Section 23(3) of the Arbitration Act permits both parties to amend or supplement their claims, and Section 2(9) extends all procedural rights to counterclaims as well.
Thus, the respondent’s argument that the contractor could not be a “claimant” for lack of notice was termed “completely untenable”.
“Award Restored, Costs Denied”: Supreme Court Reinstates Tribunal’s Findings in Full
The Arbitral Tribunal had, in its final award dated 29 June 2006, ruled in favour of the contractor on all four disputes and awarded a total of ₹1,99,90,777, along with post-award interest at 18% p.a.. That award had been struck down by the District Judge in 2010 and later affirmed by the High Court in 2025, on the premise that the tribunal exceeded its jurisdiction.
Terming this approach as legally flawed and factually baseless, the Supreme Court ruled:
“The award dated 29.06.2006 stands restored in its entirety. The appeal is allowed. No order as to costs.”
The Court also refused to entertain any argument on merits of the award, as none had been urged.
Date of Decision: 5 January 2026