Lessee Cannot Challenge Lease Expiry Date After Voluntarily Signing Supplementary Deed: Orissa High Court NDPS | Investigation Into Cognizable Offences Cannot Be Interdicted At Nascent Stage Based On Co-Accused Confession: Telangana High Court Section 300 CrPC | Subsisting Judgment Of Acquittal Cannot Be Rendered Non-Est By Subsequent Re-Investigation: Punjab & Haryana High Court Right Of Way | Electricity Transmission Projects Do Not Require Prior Consent Of Landowner; Prior Intimation And Statutory Compensation Suffice: Telangana High Court Section 6(2)(b) CGST Act | Statutory Bar Against Concurrent Proceedings Applies Only To Identical Subject Matter, Not Just Same Assessee Or Period: Delhi High Court Electricity Act | Subsequent Regulatory Exemption Does Not Automatically Extinguish Accrued Liability For Excess Consumption: Telangana High Court AP Co-operative Societies Act: Prior Notice Not Mandatory To Appoint Person-In-Charge When Managing Committee Loses Quorum: Andhra Pradesh High Court Full Bench Cannot Infer Intent Under Section 366 IPC Based On Uncharged Offence Of Rape: Allahabad High Court Acquits Accused Section 482 BNSS | Anticipatory Bail Cannot Be Granted Simply Because Custodial Interrogation Is Not Required Or If Prima Facie Case Exists: Andhra Pradesh High Court Section 100 CPC | High Court Can Interfere In Second Appeal If Concurrent Findings Are Result Of Total Non-Application Of Mind: Punjab & Haryana High Court Secretary's Loosely Worded Police Statement Cannot Invalidate Sanction Order Issued In Governor's Name: Madras High Court Kerala Anti-Social Activities (Prevention) Act | Unexplained Inordinate Delay In Externment Proceedings Snaps 'Live Link', But Procedural Steps Justify Timely Orders: High Court Punjab & Haryana High Court Slaps ₹25,000 Cost On Petitioner For Concealing Previous Bail Rejection Section 113-A Indian Evidence Act | Statutory Presumption Of Abetment Cannot Be Invoked Without Cogent Evidence Of Cruelty: Gujarat High Court Section 482 CrPC | Criminal Prosecution Cannot Be Initiated For Civil Disputes Already Closed As 'Mistake Of Fact' By Previous Investigations: Madras High Court Candidates Cannot Resile After Participating: Bombay High Court Refuses To Fill Vacant Teacher Posts From Expired 2022 Recruitment Cycle Land Acquisition Act | Interest On Solatium Payable Only From September 19, 2001, Even If Appellate Court Order Passed Later: Punjab & Haryana High Court Joint Tenants Cannot File Successive Applications Under Section 7(1) & 7(2) Of West Bengal Premises Tenancy Act Once Initial Plea Is Rejected: Calcutta High Court Order VI Rule 17 CPC | Amendment Of Plaint Seeking Partition Of Assets Subject To Pending NCLT Proceedings Regarding Title Is Impermissible: Delhi High Court

Right Of Way | Electricity Transmission Projects Do Not Require Prior Consent Of Landowner; Prior Intimation And Statutory Compensation Suffice: Telangana High Court

26 September 2026 12:08 PM

By: sayum


"The petitioner, except claiming compensation as per law, cannot hinder or obstruct the work of transmission lines, in light of the settled law as per Kalpataru." Telangana High Court, in a ruling, held that a landowner cannot obstruct the execution of a public infrastructure project for electrical transmission lines, provided the authorities adhere to statutory safeguards and provide adequate compensation for damages.

A single bench of Justice Nagesh Bheemapaka observed that the right of user for laying transmission lines is a statutory power and that the owner's prior consent is not a mandatory condition precedent for the commencement of work.

Dispute Over Transmission Line Construction

The petitioner, a landowner in Vikarabad District, challenged the actions of the Power Grid Corporation, alleging that his land was entered and excavated for a 765 KV transmission line without prior notice. He further contended that uncontrolled blasting activities were conducted on his property, violating his constitutional rights and provisions of the Indian Telegraph Act, 1885. The respondent corporation maintained that the project is a government-approved infrastructure initiative and that the petitioner had suppressed facts regarding existing title disputes over the subject property.

The court was primarily called upon to determine whether the lack of individual prior notice to the petitioner rendered the transmission project illegal and whether the petitioner could seek a writ of mandamus to stop the construction. It also examined the interplay between the statutory rights of the Power Grid Corporation to enter land under the Electricity Act, 2003, and the landowner’s right to compensation and procedural fairness under the Telegraph Act, 1885.

Power Grid's Right Of User Under Statute

The court noted that the respondents are empowered under Section 164 of the Electricity Act, 2003, and the Indian Telegraph Act, 1885, to enter upon land and erect towers for public utility projects. Relying on the Supreme Court's precedent in Kalpataru Power Transmission Ltd. v. Vinod, the bench clarified that the project’s public purpose overrides the individual’s right to stall critical infrastructure. The court emphasized that the landowner’s remedy lies in seeking adequate compensation rather than obstructing the execution of the project.

No Absolute Right To Prior Individual Notice

The court further observed that the respondent, being a public corporation, is not required to adjudicate title disputes before initiating transmission works. Since the respondents agreed to deposit the due compensation before the competent authority for eventual disbursal to the rightful titleholder, the court found no procedural infirmity. The bench held that the petitioner could not invoke general principles of natural justice to hinder the larger public interest involved in the 113.28 km transmission project.

"This Court is inclined to observe that respondent being a Corporation cannot be expected to delve into and deliberate upon the aspect as to whether the recorded owner is the actual owner."

Statutory Compensation For Actual Damages

The court reiterated that the Power Grid Corporation is bound to pay compensation for the actual damage caused to crops, trees, or structures, in accordance with the 2015 Government Guidelines. By directing that the compensation be deposited with the competent authority to be paid to the lawful owner once the title dispute is resolved, the court ensured the petitioner’s pecuniary interests remained protected. Finding no evidence of mala fides or illegality, the writ petition was disposed of with the observation that the essential grievances stood addressed.

Date of Decision: 22 September 2026

 

 

Latest Legal News