-
by Admin
19 December 2025 4:21 PM
“The order is devoid of any independent finding regarding the nature and character of the land as it existed on 12.08.2008. Such a decision, passed without inspection or satellite imagery, is arbitrary and unsustainable” — Kerala High Court -- Justice C.S. Dias set aside the summary rejection of a landowner’s application to remove her land from the notified paddy land data bank, citing blatant non-compliance with mandatory statutory obligations under the Kerala Conservation of Paddy Land and Wetland Act, 2008 and its allied Rules.
The petitioner, Rincy Avarachan, owner of a converted plot measuring 2.83 Ares in Pananchery Village, Thrissur, approached the Court after her Form 5 application seeking removal of her land from the paddy data bank was summarily dismissed by the RDO without any inspection or satellite imagery, which are obligatory under Rule 4(4f) of the Rules framed under the Act.
Calling the rejection order arbitrary, mechanical, and a product of non-application of mind, the Court quashed it and directed the RDO to reconsider the application afresh in strict adherence to law.
“Paper Records Cannot Override the Ground Reality”: High Court Slams RDO’s Blind Reliance on Agricultural Officer’s Report Without Site Verification
The judgment was sharply critical of the manner in which the RDO, acting as the Authorised Officer, passed the rejection order (Ext.P5). Despite the petitioner clearly pleading that her land was not cultivable paddy but a converted plot, the RDO neither visited the land nor called for satellite images, as required under the law.
Justice C.S. Dias categorically observed: “The authorised officer has failed to comply with the statutory requirements. There is no indication in the order that he has personally inspected the property or called for satellite pictures. The order is devoid of any independent finding.”
Referring to previous rulings including Muraleedharan Nair R v. RDO, Sudheesh U v. RDO, Palakkad, and Joy K.K. v. RDO/Sub Collector, Ernakulam, the Court reinforced that a proper assessment of land condition as on 12.08.2008 — the date on which the Act came into force — is the cornerstone for any decision under the Act.
“Inclusion in Data Bank Must Follow the Soil, Not the Stamp”: Court Says Officials Can’t Use Notification as a Substitute for Field Reality
While the official data bank of the Panchayat listed the petitioner’s land as ‘paddy land’, the Court underscored that such inclusion must not be treated as irrefutable or immune to challenge.
The Court held: “Despite the property being unsuitable for paddy cultivation, it continues to be erroneously retained in the data bank. This persistence, in absence of investigation, reflects both non-application of mind and procedural irregularity.”
The Court made it clear that once a Form 5 application is submitted, the officer is bound to undertake either a physical inspection or procure satellite imagery, and cannot base the decision merely on pre-existing labels or vague departmental reports.
“Rule 4(4f) Is Not Decorative — It’s Mandatory”: High Court Orders Reconsideration Within Strict Timeframe
In quashing the impugned order, the Court laid down a specific compliance mechanism. The RDO must now re-examine the Form 5 application either by personally inspecting the land or by calling for satellite images — both procedures explicitly mandated under Rule 4(4f) of the Rules.
The judgment directed: “If satellite pictures are called for, the application shall be disposed of within three months from the date of receipt of such pictures. If the authorised officer opts to inspect the property personally, the application shall be disposed of within two months from the date of production of a copy of this judgment by the petitioner.”
Additionally, the cost of obtaining satellite pictures shall be borne by the petitioner, as required under the Rules.
“Legal Procedures Cannot Be Sacrificed at the Altar of Convenience”: High Court Reasserts Role of Procedural Fairness in Land Use Governance
Ultimately, the Court allowed the writ petition, setting a strong precedent that quasi-judicial orders concerning land rights and usage must be rooted in factual verification, not assumptions or administrative convenience.
Justice C.S. Dias concluded: “The impugned order is vitiated due to errors of law and non-application of mind. It deserves to be quashed.”
The verdict reinforces the principle that converted lands cannot be trapped indefinitely in the regulatory label of ‘paddy field’, especially when the State’s own procedures for exclusion are not being properly followed.
Date of decision: 8th September 2025