Multiple NDPS Cases Without Conviction Cannot Justify Indefinite Pre-Trial Custody: Himachal Pradesh HC Grants Bail in Heroin Case Departmental Findings Based On Witnesses Discredited By Criminal Court Constitute 'No Evidence': Orissa High Court Upheld Constable's Reinstatement When Pension Rules Are Capable of More Than One Interpretation, Courts Must Lean in Favour of the Employee: MP High Court Wife Left Voluntarily — But Minor Children Cannot Be Taken Away: Madras High Court Intervenes in Habeas Corpus for Two Toddlers Where Consideration Does Not Pass in Terms of the Sale Deed, the Sale Deed Is Null and Void, a Nullity and Dead Letter in the Eyes of Law: Jharkhand High Court National Award-Winning Director's Script Was Registered Two Years Before Complainant Even Wrote His — Supreme Court Quashes Copyright Infringement Case Against 'Kahaani-2' Director IBC Clean Slate Does Not Wipe Out Right of Set-Off as Defence: Supreme Court Draws Critical Distinction Between Counterclaim and Defensive Plea GST Assessment Challenged on Natural Justice Grounds Tagged to Criminal Writ in Supreme Court Railway Cannot Escape Compensation by Crying 'Trespass' Without Eyewitness: Bombay High Court Reverses Tribunal, Awards Rs. 4 Lakh to Widow of Rolex Employee Master Plan Cannot Be Held Hostage to Subsequent Vegetation Growth — Supreme Court Settles Deemed Forest vs. Statutory Planning Conflict Contempt | Sold Property Despite Court's Restraint Order: Andhra Pradesh High Court Sentences One Month's Imprisonment Tractor-Run-Over Death Was An Accident, Not Murder: Allahabad High Court Acquits Three Accused Fast-Tracking Cannot Bury Justice: Supreme Court Sets Aside 21-Year-Delayed Appeal Decided Without Informing Convict Panchayat Act's Demolition Powers Cease Once Plot Falls Under Development Authority's Planning Area: Calcutta High Court Actual Date Of Woman Director's Appointment A Triable Issue; Prosecution Can't Be Quashed Merely On Claims Of Compliance: Calcutta High Court A Website Cannot Whisper and Then Punish: Delhi High Court Reins in DSSSB Over E-Dossier Rejections Mutual Consent Alone Ends the Marriage: Gujarat High Court Affirms Mubarat Divorce Without Formalities State Cannot Hide Behind "Oral Consent" or Delay When It Builds Roads Through Citizens' Land Without Due Process: Himachal Pradesh HC Show Cause Notice Alone Cannot Cut a Retired Engineer's Pension: Jharkhand High Court Bovine Smuggling Is a Law and Order Problem, Not a Public Order Threat: J&K High Court Quashes PSA Detention Article 22(2) Constitution | Production Beyond 24 Hours Not Fatal If Delay Explained And Travel Time Excluded: Karnataka High Court Article 227 Is Not an Appellate Power: High Court Refuses to Reassess Tribunal Findings on Pension Claim: Kerala High Court High Court Cannot Call A Complaint "False And Malicious" Without First Finding It Discloses No Cognizable Offence: Supreme Court When Jurisdiction Fails, Remand Cannot Cure It: Supreme Court Sets Aside Order Sending MSME Award Dispute Back to Functus Officio Facilitation Council Selling Inferior Pipes as 'Jain' or 'Jindal Gold' Brand Is Not Just a Civil Wrong — It's Cheating: MP High Court Refuses to Quash FIR Went to Collect Chit Fund Money, Got Arrested in Prostitution Raid: Telangana High Court Grants Bail to Woman Accused of Being Sub-Organiser Axe Blow During Sudden Quarrel Falls Under Exception 4 To Section 300 IPC, Not Murder: Orissa High Court Modifies Conviction To Culpable Homicide

Himachal High Court Warns Arbitrator Over Delays, Extends Deadline in National Highway-21 Compensation Case

11 October 2024 3:54 PM

By: sayum


Himachal Pradesh High Court, in Nand Lal vs. The Land Acquisition Collector, National Highway & Ors., addressed delays in arbitration proceedings concerning the acquisition of land for National Highway 21 in District Mandi. The court extended the mandate of the arbitrator until March 25, 2025, criticizing the arbitral process for breaches of statutory timelines under the Arbitration and Conciliation Act, 1996.

The dispute arises from the acquisition of land under the National Highways Act, 1956, for the widening and maintenance of National Highway-21. The petitioner, Nand Lal, contested the compensation awarded by the Land Acquisition Collector and initiated arbitral proceedings. The arbitration related to Award No. 1/3 dated April 26, 2018, but the case faced repeated adjournments, and the arbitrator's mandate expired without concluding the proceedings.

The petitioner filed for an extension under Section 29-A of the Arbitration and Conciliation Act, 1996, which sets strict timelines for concluding arbitration but allows for extensions by court order.

The core issue before the court was whether the arbitrator had violated the statutory time limits under Sections 23 and 29-A of the Arbitration and Conciliation Act. Section 29-A mandates that an arbitral award be rendered within twelve months from the completion of pleadings, with a possible six-month extension if agreed upon by the parties.

Justice Bipin Chander Negi highlighted how the arbitrator repeatedly delayed the proceedings, stating:

"The proceedings have been conducted by the learned Arbitrator by observing statutory provisions… more in their breach rather than in their observance."

The court emphasized that statutory timelines must be adhered to, adding that any further breaches could result in the termination of the arbitrator’s mandate under Section 29-A(6). Nonetheless, the court extended the timeline to avoid prejudice to the petitioner, whose compensation claim had been pending for years.

The court granted an extension for the arbitrator to conclude the proceedings by March 25, 2025. While extending the mandate, the court warned that continued delays would not be tolerated:

"If the Court finds the Arbitrator to be remiss in his duties… it shall not hesitate in invoking its powers… to terminate the mandate of the Arbitrator."

Additionally, the court referenced the 2022 Supreme Court decision in Cognizance for Extension of Limitation, which allowed for the exclusion of time periods impacted by the COVID-19 pandemic. The court applied this principle to grant additional time for the arbitration process.

In this ruling, the Himachal Pradesh High Court extended the arbitrator’s mandate while underscoring the importance of adhering to statutory timelines. The court directed the arbitrator to adhere to a strict timetable and finalize the proceedings by March 2025 to ensure the petitioner receives timely compensation.

Date of Decision: September 25, 2024

Nand Lal vs. The Land Acquisition Collector, National Highway & Ors.​.

Latest Legal News