Cheque Bounce Cases Should Ordinarily Be Sent To Mediation: Punjab & Haryana High Court Calls For Mediation In NI Act Matters 138 NI Act | Belated Plea Of Forged Signatures Cannot Be Used To Delay Trial: Punjab & Haryana High Court Refuses Handwriting Expert Sections 332 & 333 IPC | Lawful Discharge Of Duty Must Be Proved, Mere Status As Public Servant Not Enough: Allahabad High Court Bus Conductor Accused of Assaulting Traffic Inspectors Custody With Biological Mother Cannot Ordinarily Be Treated As Illegal Detention: Delhi High Court Refuses Habeas Corpus For Return Of Child To Canada Foreign Custody Orders Must Yield To Welfare Of Child: Delhi High Court Refuses To Enforce Canadian Return Order Through Habeas Corpus Possible Criminal Racket Luring Young Girls Through Self-Proclaimed Peers And Tantriks Must Be Examined: J&K High Court Orders Wider Judicial Scrutiny Nomenclature Cannot Determine Constitutional Entitlement: Supreme Court Strikes Down Exclusion Of ‘Academic Arrangement’ Employees From Regularisation Testimony Of Related Witnesses Cannot Be Discarded Merely For Relationship: Supreme Court Upholds Murder Conviction 149 IPC | Presence In Unlawful Assembly Is Enough For Murder Liability”: Supreme Court Upholds Conviction Directly Recruited Engineers Entitled To Seniority From Date Of Initial Appointment Including Training Period: Supreme Court Section 32 Evidence Act | If There Is Even An Iota Of Suspicion, Dying Declaration Cannot Sustain Conviction: Supreme Court Framing A Case On Public Perceptions And Personal Predilections Ends Up In A Mess: Supreme Court Upholds Acquittal In Alleged Parricide Arson Case When Oppression Petition Is Pending, Courts Must Ensure The Subject Matter Does Not Disappear Before Adjudication: Supreme Court Orders Status Quo In ₹1000 Crore Redevelopment Dispute Parties Cannot Participate In Arbitration And Later Challenge The Process Only After An Unfavourable Outcome : Supreme Court ICSID Clause Is Only A Fail-Safe Mechanism, Not A Restriction: Supreme Court Upholds Arbitral Tribunal’s Constitution In MCGM Dispute Passive Euthanasia | 'Right To Die With Dignity Is An Intrinsic Facet Of Article 21': Supreme Court Permits Withdrawal Of Life Support Medical Board Must Record Reasons Before Denying Disability Pension To Armed Forces Personnel: Kerala High Court Grants Disability Pension To Air Force Corporal 138 NI Act | Directors Cannot Be Prosecuted If Company Is Not Made Accused: Allahabad High Court Quashes Cheque Bounce Cases Broad Daylight Removal of Goods by Known Creditors Is Not Theft: Andhra Pradesh High Court Rejects Shopkeeper’s Insurance Claim Reservation Cannot Freeze Private Land Forever – Lapse Under Section 127 MRTP Act Operates Automatically: Bombay High Court Dismisses PIL Transfer On Marriage Cannot Defeat Helper’s First Right To Promotion: Himachal Pradesh High Court Upholds Anganwadi Helper’s Promotion Where Accusations Are Prima Facie True, Statutory Bar Under Section 43D(5) UAPA Operates; Bail Cannot Be Granted: Jharkhand High Court Bomb Hurled At Head Of Victim Shows Clear Intention To Kill: Kerala High Court Upholds Life Sentence In Kannur Political Murder Case Registrar Has No Power To Cancel Registered Sale Deeds: Madras High Court Reaffirms Civil Court’s Exclusive Jurisdiction MP High Court Refuses to Quash FIR Against Principal of Sacred Heart Convent High School in Forced Conversion Case Employees Of Registered Societies Cannot Claim Article 311 Protection: Delhi High Court Clarifies Limits Of Constitutional Safeguards In Private Employment

“Force Majeure Not Just a Shield, But a Sword for Fairness”: Supreme Court Upholds Solar Project Extension, Rejects Tariff Reduction

28 August 2024 11:46 AM

By: sayum


The Supreme Court has upheld the decision of the Appellate Tribunal for Electricity (APTEL) in a dispute involving Bangalore Electricity Supply Company Limited (BESCOM) and Hirehalli Solar Power Project LLP. The Court affirmed that the delays in commissioning the solar power project were justified under the force majeure clause of the Power Purchase Agreement (PPA), thereby rejecting BESCOM’s claims for liquidated damages and reduced tariff rates.

The dispute arose from a solar power project in Karnataka, where Hirehalli Solar Power Project LLP (Respondent) faced delays in securing land conversion and grid evacuation approvals, which led to a delay in the project’s commissioning. The project was part of a state policy to promote solar energy among farmers, with a scheduled commissioning date (SCD) of February 28, 2017, under the PPA signed with BESCOM.

Due to various delays, including slow governmental processes and administrative hurdles, the respondents sought an extension of the SCD under the force majeure clause of the PPA. While BESCOM initially granted a six-month extension, the Karnataka Electricity Regulatory Commission (KERC) later imposed liquidated damages and reduced the tariff, rejecting the force majeure claim. The APTEL, however, reversed KERC’s decision, siding with the respondents, which led BESCOM to appeal to the Supreme Court.

The Supreme Court’s judgment focused on whether the delays experienced by the respondents were covered under the force majeure clause of the PPA. The Court noted that the delays in obtaining necessary governmental approvals, such as land conversion and grid evacuation, were beyond the control of the respondents and were not caused by any negligence on their part. The Court observed that “the time taken by government authorities to provide approvals was not within [the respondents’] control,” which justified the invocation of the force majeure clause.

The Court found that the respondents acted with due diligence in pursuing the necessary approvals. It highlighted the fact that similar delays were faced by multiple solar power developers under the same policy, indicating systemic issues rather than individual fault. The Court endorsed APTEL’s findings that the delays were primarily due to the slow governmental processes and the cumbersome nature of the approval procedures, which should not penalize the respondents.

The Supreme Court extensively discussed the principles governing force majeure clauses, particularly in the context of power purchase agreements. It reiterated that such clauses should be interpreted narrowly, yet they must be applied fairly when the conditions are met, as in this case. The Court concluded that the respondents were entitled to an extension of time under the force majeure clause, which negated the need for liquidated damages and a reduction in the tariff.

Justice Pamidighantam Sri Narasimha remarked, “The delay was not caused by the respondents but by the government bodies and relevant authorities…the respondents acted diligently and with care and caution to secure approvals.”

The Supreme Court’s judgment underscores the importance of fair application of force majeure clauses in contracts, particularly in sectors like renewable energy where projects are often subject to administrative delays. By upholding APTEL’s decision, the Court has set a significant precedent, ensuring that developers are not unjustly penalized for delays beyond their control. This ruling will likely influence future disputes in the renewable energy sector, reinforcing the protection afforded by force majeure provisions in PPAs.

Date of Decision: August 27, 2024

Bangalore Electricity Supply Company Limited vs. Hirehalli Solar Power Project LLP & Others

Latest Legal News