The Power Under Order XXXVIII, Rule 5 CPC is Drastic and Extraordinary; Should Not Be Exercised Mechanically or Merely for the Asking: Calcutta High Court Telangana High Court Strikes Down Section 10-A: Upholds Transparency in Public Employment Absence of Homogeneous Mixing and Procedural Deficiencies Vitiate NDPS Conviction: Punjab and Haryana High Court Business Disputes Cannot Be Given Criminal Color: Patna High Court Quashes Complaint in Trademark Agreement Case Gujarat High Court Appoints Wife as Guardian of Comatose Husband, Calls for Legislative Framework Standard of Proof in Professional Misconduct Requires 'Higher Threshold' but Below 'Beyond Reasonable Doubt: Delhi High Court Imprisonment Cannot Bar Education: Bombay HC Allows UAPA Accused to Pursue LL.B. High Court Acquits Accused in Double Murder Case, Asserts ‘Suspicion Cannot Replace Proof’ Long separation and irreparable breakdown of marriage must be read as cruelty under Section 13(1)(ia) of the Hindu Marriage Act: Andhra Pradesh High Court Regulation 101 Applies to All Aided Institutions, Including Minority Ones, Says Allahabad High Court Fraud Unravels All Judicial Acts : Jharkhand High Court Orders Demolition of Unauthorized Constructions in Ratan Heights Case Suspicious Circumstances Cannot Validate a Will: Himachal Pradesh High Court Upholds 1997 Will Over 2000 Will Calcutta High Court Allows Amendment of Pleadings Post-Trial: Necessary for Determining Real Questions in Controversy Exaggerated Allegations in Matrimonial Disputes Cause Irreparable Suffering, Even Acquittal Can't Erase Scars: Supreme Court Quashes FIR Against Relatives in Matrimonial Dispute Consent Requires Active Deliberation; False Promise of Marriage Must Be Proximate Cause for Sexual Relations: Supreme Court Urgency Clause in Land Acquisition for Yamuna Expressway Upheld: Supreme Court Affirms Public Interest in Integrated Development Interest Rate of 24% Compounded Annually Held Excessive; Adjusted to Ensure Fairness in Loan Transactions: AP HC Prosecution Under IPC After Factories Act Conviction Violates Article 20(2): Bombay High Court Join Our Exclusive Lawyer E News WhatsApp Group! Conversion for Reservation Benefits Is a Fraud on the Constitution: Supreme Court Rejects SC Certificate for Reconverted Christian Patent Office Guidelines Must Be Followed for Consistency in Decisions: Madras High Court Limitation Cannot Obstruct Justice When Parties Consent to Extensions: Madhya Pradesh High Court Additional Fees Are Incentives, Not Penalties: Orissa High Court Upholds Central Motor Vehicles Rules Amendment Interpretation of Tender Eligibility Criteria Lies with Tendering Authority: Gujrat High Court Upholds Discharge of Tender Complaints Were Contradictory and Did Not Establish Prima Facie Case for SC/ST Act Charges: J&K HC Insurance Cover Notes Hold Policy Validity Unless Proven Otherwise: Kerala High Court Upholds Compensation in Fatal Accident Case Article 21 Of Constitution Applies Irrespective Of Nature Of Crime. Prolonged Incarceration Without Trial Amounts To Punishment Without Adjudication: Calcutta HC Concept Of 'Liberal Approach' Cannot Be Used To Jettison The Substantive Law Of Limitation: Delhi High Court Limitation is Not Always a Mixed Question of Fact and Law: Bombay High Court Dismisses 31-Year-Old Specific Performance Suit as Time-Barred

“Force Majeure Not Just a Shield, But a Sword for Fairness”: Supreme Court Upholds Solar Project Extension, Rejects Tariff Reduction

28 August 2024 11:46 AM

By: sayum


The Supreme Court has upheld the decision of the Appellate Tribunal for Electricity (APTEL) in a dispute involving Bangalore Electricity Supply Company Limited (BESCOM) and Hirehalli Solar Power Project LLP. The Court affirmed that the delays in commissioning the solar power project were justified under the force majeure clause of the Power Purchase Agreement (PPA), thereby rejecting BESCOM’s claims for liquidated damages and reduced tariff rates.

The dispute arose from a solar power project in Karnataka, where Hirehalli Solar Power Project LLP (Respondent) faced delays in securing land conversion and grid evacuation approvals, which led to a delay in the project’s commissioning. The project was part of a state policy to promote solar energy among farmers, with a scheduled commissioning date (SCD) of February 28, 2017, under the PPA signed with BESCOM.

Due to various delays, including slow governmental processes and administrative hurdles, the respondents sought an extension of the SCD under the force majeure clause of the PPA. While BESCOM initially granted a six-month extension, the Karnataka Electricity Regulatory Commission (KERC) later imposed liquidated damages and reduced the tariff, rejecting the force majeure claim. The APTEL, however, reversed KERC’s decision, siding with the respondents, which led BESCOM to appeal to the Supreme Court.

The Supreme Court’s judgment focused on whether the delays experienced by the respondents were covered under the force majeure clause of the PPA. The Court noted that the delays in obtaining necessary governmental approvals, such as land conversion and grid evacuation, were beyond the control of the respondents and were not caused by any negligence on their part. The Court observed that “the time taken by government authorities to provide approvals was not within [the respondents’] control,” which justified the invocation of the force majeure clause.

The Court found that the respondents acted with due diligence in pursuing the necessary approvals. It highlighted the fact that similar delays were faced by multiple solar power developers under the same policy, indicating systemic issues rather than individual fault. The Court endorsed APTEL’s findings that the delays were primarily due to the slow governmental processes and the cumbersome nature of the approval procedures, which should not penalize the respondents.

The Supreme Court extensively discussed the principles governing force majeure clauses, particularly in the context of power purchase agreements. It reiterated that such clauses should be interpreted narrowly, yet they must be applied fairly when the conditions are met, as in this case. The Court concluded that the respondents were entitled to an extension of time under the force majeure clause, which negated the need for liquidated damages and a reduction in the tariff.

Justice Pamidighantam Sri Narasimha remarked, “The delay was not caused by the respondents but by the government bodies and relevant authorities…the respondents acted diligently and with care and caution to secure approvals.”

The Supreme Court’s judgment underscores the importance of fair application of force majeure clauses in contracts, particularly in sectors like renewable energy where projects are often subject to administrative delays. By upholding APTEL’s decision, the Court has set a significant precedent, ensuring that developers are not unjustly penalized for delays beyond their control. This ruling will likely influence future disputes in the renewable energy sector, reinforcing the protection afforded by force majeure provisions in PPAs.

Date of Decision: August 27, 2024

Bangalore Electricity Supply Company Limited vs. Hirehalli Solar Power Project LLP & Others

Similar News