Police Have No Power To Probe Or File Chargesheet Under PCPNDT Act: Supreme Court Rules Cognizance Bar Absolute 'Cannot Claim Pension Scheme Post-Retirement After Accepting CPF Benefits': Supreme Court Rules Regularisation Doesn't Relate Back To Initial Appointment 'Offence Within Four Corners Of Room Not In Public View': Supreme Court Quashes SCST Act Charges Against School Manager Give A Dog A Bad Name And Hang Him: Supreme Court Quashes UP Gangsters Act Cases; Rules Punishing Mere Status Violates Article 20(1) Child Of Tender Age Easy Prey To Tutoring: Supreme Court Quashes Double Murder Conviction Based On Solitary Child Witness 'State Cannot Supplant PSC's Role By Conducting Exhaustive Eligibility Enquiry': Supreme Court Limits Executive Power In Post-Selection Document Verification Revenue Entry Neither Creates Nor Extinguishes Title: Supreme Court Holds Limitation Against Co-Owner Cannot Run Without Open And Unequivocal Ouster 125 CrPC | Obligation To Maintain Children Cannot Be Divided By Arithmetic Alone': Supreme Court Rules Mother's Income No Ground To Halve Father's Liability 'Scramble For Possession': Supreme Court Directs Appointment Of Advocate Receiver Amid Clash Between Consent Decree Execution & Gujarat Tenancy Act Claims 'Enmity Is A Double-Edged Weapon': Allahabad High Court Acquits Murder Convicts After Medical Evidence Flaws Expose 'Eye-Witness' Lies Andhra Pradesh High Court Quashes Remand Extension Granted Without Notice To Accused, Grants Default Bail 167(2) CRPC No Violation Of Natural Justice If Borrower Fails To Produce Records Or Seek Personal Hearing: Calcutta High Court Upholds Bank's 'Fraud' Account Classification Cannot Exploit Entire Land's FAR For New Tower Once OC Is Issued Without Flat Owners' Consent: Karnataka High Court Mandates TDR Purchase Brethren Assembly Hall Is A 'Church' Under Foreign Liquor Rules, Bar Hotel Cannot Function Within Prohibited Distance: Kerala High Court Fence-Sitters Cannot Claim Arrears After Inordinate Delay, But Entitled To Notional Fixation For Pension: Madhya Pradesh High Court Strikes At The Foundation Of Institutional Integrity: Punjab And Haryana High Court Denies Anticipatory Bail In Medical PG Admission Fraud Case Foreign Law Degree Taken Directly After School Cannot Be Treated As 'First Degree' For Admission To 3-Year LL.B. In India: Bombay High Court

“Force Majeure Not Just a Shield, But a Sword for Fairness”: Supreme Court Upholds Solar Project Extension, Rejects Tariff Reduction

28 August 2024 11:46 AM

By: sayum


The Supreme Court has upheld the decision of the Appellate Tribunal for Electricity (APTEL) in a dispute involving Bangalore Electricity Supply Company Limited (BESCOM) and Hirehalli Solar Power Project LLP. The Court affirmed that the delays in commissioning the solar power project were justified under the force majeure clause of the Power Purchase Agreement (PPA), thereby rejecting BESCOM’s claims for liquidated damages and reduced tariff rates.

The dispute arose from a solar power project in Karnataka, where Hirehalli Solar Power Project LLP (Respondent) faced delays in securing land conversion and grid evacuation approvals, which led to a delay in the project’s commissioning. The project was part of a state policy to promote solar energy among farmers, with a scheduled commissioning date (SCD) of February 28, 2017, under the PPA signed with BESCOM.

Due to various delays, including slow governmental processes and administrative hurdles, the respondents sought an extension of the SCD under the force majeure clause of the PPA. While BESCOM initially granted a six-month extension, the Karnataka Electricity Regulatory Commission (KERC) later imposed liquidated damages and reduced the tariff, rejecting the force majeure claim. The APTEL, however, reversed KERC’s decision, siding with the respondents, which led BESCOM to appeal to the Supreme Court.

The Supreme Court’s judgment focused on whether the delays experienced by the respondents were covered under the force majeure clause of the PPA. The Court noted that the delays in obtaining necessary governmental approvals, such as land conversion and grid evacuation, were beyond the control of the respondents and were not caused by any negligence on their part. The Court observed that “the time taken by government authorities to provide approvals was not within [the respondents’] control,” which justified the invocation of the force majeure clause.

The Court found that the respondents acted with due diligence in pursuing the necessary approvals. It highlighted the fact that similar delays were faced by multiple solar power developers under the same policy, indicating systemic issues rather than individual fault. The Court endorsed APTEL’s findings that the delays were primarily due to the slow governmental processes and the cumbersome nature of the approval procedures, which should not penalize the respondents.

The Supreme Court extensively discussed the principles governing force majeure clauses, particularly in the context of power purchase agreements. It reiterated that such clauses should be interpreted narrowly, yet they must be applied fairly when the conditions are met, as in this case. The Court concluded that the respondents were entitled to an extension of time under the force majeure clause, which negated the need for liquidated damages and a reduction in the tariff.

Justice Pamidighantam Sri Narasimha remarked, “The delay was not caused by the respondents but by the government bodies and relevant authorities…the respondents acted diligently and with care and caution to secure approvals.”

The Supreme Court’s judgment underscores the importance of fair application of force majeure clauses in contracts, particularly in sectors like renewable energy where projects are often subject to administrative delays. By upholding APTEL’s decision, the Court has set a significant precedent, ensuring that developers are not unjustly penalized for delays beyond their control. This ruling will likely influence future disputes in the renewable energy sector, reinforcing the protection afforded by force majeure provisions in PPAs.

Date of Decision: August 27, 2024

Bangalore Electricity Supply Company Limited vs. Hirehalli Solar Power Project LLP & Others

Latest Legal News