Supreme Court Lays Down Comprehensive Guidelines To Prevent Misuse Of POCSO Act In Matrimonial Disputes Land Reforms Act | Joint Application For Pre-Emption By Adjoining Landowners Is Maintainable: Calcutta High Court Ocular Evidence In Conflict With Medical Findings Or Withholding Of Natural Witnesses Vitiates Prosecution Case: Allahabad High Court Compassionate Appointment Claim Must Be Decided Based On Policy Prevalent At Time Of Death: Bombay High Court Section 376 IPC | Failure To Prove Initial Dishonest Intent In Marriage Promise Renders Sexual Relationship Consensual: Allahabad High Court Prolonged Incarceration And Delay In Trial Are Valid Grounds To Invoke Constitutional Right To Speedy Trial Under Article 21 In UAPA Cases: Delhi High Court Motor Vehicles Act | Insurer Liable To Pay And Recover Compensation For Gratuitous Passengers In Goods Vehicles: Gujarat High Court Proof Of Demand And Acceptance Under PC Act Must Be Evaluated Based On Preponderance Of Probabilities In Rebuttal: Kerala High Court Tenancy Claim | Mere Possession Without Lawful Foundation Or Identification Of Tenanted Land Cannot Confer Occupancy Rights: Karnataka High Court 125 CrPC | Maintenance Cannot Be Evaded By Claiming Physical Disability If Conduct Indicates Concealment Of Financial Means: Kerala High Court M.P. Municipal Corporation Act | Locus Standi Under Section 307(5) Limited To Residents Of The Municipal Area: Madhya Pradesh High Court Writ Jurisdiction | Belated Challenge To Disciplinary Action After Superannuation Amounts To Laches; Petition Dismissed: Punjab & Haryana High Court Order 39 Rule 1 & 2 CPC | Mere Pendency Of Partition Suit Does Not Entitle Plaintiff To Injunction Restraining Reconstruction Of Residential Building: Kerala High Court Not A Mere Breach Of Contract: Telangana High Court Refuses To Quash FIR In ₹73 Crore Garment Investment Fraud Section 482 CrPC | High Court Quashes FIR Following Private Compromise In Non-Heinous Dispute Arising From Civil Conflict Mere Involvement In Criminal Case Does Not Constitute Moral Turpitude To Deny Public Appointment: Telangana High Court Pendency Of Investigation Cannot Be A Blanket Ground To Deny Permission For Foreign Travel: Rajasthan High Court Fraudulent Representation By Counsel Vitiates Ex Parte Decree: Punjab & Haryana High Court Holds Professional Misconduct As Evidence Of Fraud Writ Jurisdiction | Suppression Of Material Facts Regarding Pending Criminal And Departmental Proceedings Renders Petition Liable To Dismissal: Orissa High Court Banking Fraud | Failure Of Bank Official To Conduct Physical Inspection Of Collateral Property Constitutes Criminal Conspiracy And Abuse Of Official Position: Madras High Court Fraud Vitiates Judicial Proceedings: Judgment Obtained Through Misrepresentation And Conflict Of Interest Cannot Be Sustained, Holds Punjab And Haryana High Court Discovery Under Section 27 Evidence Act From Publicly Accessible Place Requires Caution: Supreme Court Mere Recovery Of Articles At Instance Of Accused Without Independent Corroboration Cannot Sustain Conviction: Supreme Court DNA Profile Must Be Supported By Other Conclusive Evidence To Prove Guilt: Supreme Court

“Force Majeure Not Just a Shield, But a Sword for Fairness”: Supreme Court Upholds Solar Project Extension, Rejects Tariff Reduction

28 August 2024 11:46 AM

By: sayum


The Supreme Court has upheld the decision of the Appellate Tribunal for Electricity (APTEL) in a dispute involving Bangalore Electricity Supply Company Limited (BESCOM) and Hirehalli Solar Power Project LLP. The Court affirmed that the delays in commissioning the solar power project were justified under the force majeure clause of the Power Purchase Agreement (PPA), thereby rejecting BESCOM’s claims for liquidated damages and reduced tariff rates.

The dispute arose from a solar power project in Karnataka, where Hirehalli Solar Power Project LLP (Respondent) faced delays in securing land conversion and grid evacuation approvals, which led to a delay in the project’s commissioning. The project was part of a state policy to promote solar energy among farmers, with a scheduled commissioning date (SCD) of February 28, 2017, under the PPA signed with BESCOM.

Due to various delays, including slow governmental processes and administrative hurdles, the respondents sought an extension of the SCD under the force majeure clause of the PPA. While BESCOM initially granted a six-month extension, the Karnataka Electricity Regulatory Commission (KERC) later imposed liquidated damages and reduced the tariff, rejecting the force majeure claim. The APTEL, however, reversed KERC’s decision, siding with the respondents, which led BESCOM to appeal to the Supreme Court.

The Supreme Court’s judgment focused on whether the delays experienced by the respondents were covered under the force majeure clause of the PPA. The Court noted that the delays in obtaining necessary governmental approvals, such as land conversion and grid evacuation, were beyond the control of the respondents and were not caused by any negligence on their part. The Court observed that “the time taken by government authorities to provide approvals was not within [the respondents’] control,” which justified the invocation of the force majeure clause.

The Court found that the respondents acted with due diligence in pursuing the necessary approvals. It highlighted the fact that similar delays were faced by multiple solar power developers under the same policy, indicating systemic issues rather than individual fault. The Court endorsed APTEL’s findings that the delays were primarily due to the slow governmental processes and the cumbersome nature of the approval procedures, which should not penalize the respondents.

The Supreme Court extensively discussed the principles governing force majeure clauses, particularly in the context of power purchase agreements. It reiterated that such clauses should be interpreted narrowly, yet they must be applied fairly when the conditions are met, as in this case. The Court concluded that the respondents were entitled to an extension of time under the force majeure clause, which negated the need for liquidated damages and a reduction in the tariff.

Justice Pamidighantam Sri Narasimha remarked, “The delay was not caused by the respondents but by the government bodies and relevant authorities…the respondents acted diligently and with care and caution to secure approvals.”

The Supreme Court’s judgment underscores the importance of fair application of force majeure clauses in contracts, particularly in sectors like renewable energy where projects are often subject to administrative delays. By upholding APTEL’s decision, the Court has set a significant precedent, ensuring that developers are not unjustly penalized for delays beyond their control. This ruling will likely influence future disputes in the renewable energy sector, reinforcing the protection afforded by force majeure provisions in PPAs.

Date of Decision: August 27, 2024

Bangalore Electricity Supply Company Limited vs. Hirehalli Solar Power Project LLP & Others

Latest Legal News