Readiness and Willingness Under Section 16(c) Is Not a Ritualistic Phrase — Plaintiff Must Prove It With Substance, Not Just Words: Karnataka High Court FIR in Disproportionate Assets Case Quashed: Patna High Court Slams SP for 'Non-Application of Mind' and 'Absence of Credible Source Information' Ownership of Vehicle Linked to Commercial Quantity of Heroin – Custodial Interrogation Necessary: Punjab & Haryana High Court Denies Anticipatory Bail under Section 482 BNSS Death Caused by Rash Driving Is Not a Private Dispute — No FIR Quashing on Basis of Compromise in Section 106 BNS Cases: Punjab & Haryana High Court No Bank Can Override Court Orders: Rajasthan High Court Slams Axis Bank for Unauthorized Withdrawal from Court-Ordered FD" No Work No Pay Is Not a Universal Rule: Punjab & Haryana High Court Dock Identification Without Prior TIP Is Absolutely Useless: P&H High Court Upholds Acquittal in Attempt to Murder Case Filing Forged Court Pleadings in Union Government’s Name is Criminal Contempt: Karnataka High Court Sentences Litigant to Jail Execution of Will Proved, But Probate Justly Denied Due to Concealment of Property Sale: Delhi High Court Mere Designation Doesn’t Establish Criminal Liability: Bombay High Court Quashes Proceedings Against ICICI Officials in Octroi Evasion Case Fraud on Power Voids the Order: Supreme Court Quashes FIR Against Karnataka BJP Leader R. Ashoka, Slams Politically Motivated Prosecution Cause of Fire Is Immaterial If Fire Itself Is Insured Peril: Supreme Court Rebukes Insurer’s Repudiation Dragging a Trained Army Officer Up 20 Steps Without Resistance? The Story Lacks Credence: Supreme Court Upholds Acquittal in Army Officer’s Murder Semen Stains Alone Do Not Prove Rape: Supreme Court Acquits Doctor Accused of Rape No Mortgage, No SARFAESI: Supreme Court Rules Against NEDFi, Says Recovery Action in Nagaland Without Security Agreement Was Illegal Parity Cannot Be Denied by Geography: Supreme Court Holds Jharkhand Bound by Patna HC's Judgment, Orders Pay Revision for Industries Officer Once Power Flows Continuously from a Synchronized Turbine, It Is No Longer Infirm: Supreme Court Orders TANGEDCO to Pay Fixed Charges to Penna Electricity

Force Majeure Cannot Be Invoked Without Timely Notice: Madras High Court

26 September 2024 8:21 PM

By: Deepak Kumar


On September 23, 2024, the Madras High Court, in M/s. Saravana Global Energy Limited v. Tamil Nadu Transmission Corporation Limited (TANTRANSCO), C.S. No. 810 of 2012, dismissed a civil suit for the recovery of ₹1,38,35,732 plus interest. The plaintiff, Saravana Global Energy, sought recovery for unpaid invoices and contested the defendant’s imposition of liquidated damages for delayed delivery. The Court held that the force majeure defense raised by the plaintiff was invalid as they failed to provide timely notice under the contract. Additionally, the Court ruled the suit was barred by limitation, as it was filed beyond the three-year statutory period under the Limitation Act, 1963.

The plaintiff, M/s. Saravana Global Energy Limited, supplied electrical insulators to TANTRANSCO under three purchase orders between 2007 and 2008. Due to delays in delivery, TANTRANSCO withheld payments and imposed liquidated damages, amounting to ₹73,45,827, under the purchase order terms. Saravana Global Energy claimed the delay resulted from force majeure events such as floods and labor strikes, arguing that the damages imposed were excessive and violated Sections 73 and 74 of the Indian Contract Act, 1872. Additionally, the plaintiff sought interest on delayed payments, despite no contractual provision for interest.

The plaintiff cited floods and labor issues as force majeure events to justify the delayed delivery. However, the Court observed that under the purchase order, notice of such events had to be given within 15 days of occurrence. The plaintiff failed to provide timely notice. The Court emphasized that the pattern of deliveries remained consistent during the alleged force majeure period, weakening the plaintiff's defense.

“The defense of force majeure cannot be invoked retrospectively without adhering to contractual obligations, including the stipulation for timely notice.”

The plaintiff argued that a 30-day payment practice was followed by the defendant and sought interest on delayed payments. The defendant countered that no specific time for payment or interest on delayed payments was included in the contract. The Court agreed with the defendant, ruling that the claim for interest was unsustainable as the contract did not stipulate any provision for interest. The Court referenced Section 14 of the Limitation Act, which excludes the possibility of implied terms regarding payment timelines.

The defendant argued that the cause of action arose in 2009 when the liquidated damages were imposed, but the suit was only filed in 2012, beyond the three-year limitation period. The Court held that the suit was indeed barred by limitation, as the plaintiff failed to file within the prescribed time.

"Where the cause of action arises, limitation runs. Delay in seeking recovery of dues cannot be excused, especially where the suit is time-barred by statute."

The Court, presided by Justice A.A. Nakkiran, dismissed the plaintiff's suit, holding that:

Force Majeure Defense Rejected: The plaintiff's failure to notify the defendant within the stipulated time frame rendered the force majeure claim ineffective.

No Entitlement to Interest: The absence of any contractual provision for interest on delayed payments meant that the plaintiff could not claim it.

Suit Time-Barred: The suit, filed beyond the three-year limitation period, was barred under Section 14 of the Limitation Act.

The Court upheld TANTRANSCO's imposition of liquidated damages for the delayed supply of goods and dismissed the plaintiff’s claim for recovery of the withheld amount as well as interest.

The Madras High Court's ruling reinforces the importance of adhering to contractual provisions, particularly concerning force majeure claims and timely notices. The judgment underscores that claims for interest and payment recovery must be based on clear contractual terms and filed within the prescribed limitation period.

Date of decision: September 23, 2024

M/s. Saravana Global Energy Limited v. Tamil Nadu Transmission Corporation Limited (TANTRANSCO)

Latest Legal News