Readiness and Willingness Under Section 16(c) Is Not a Ritualistic Phrase — Plaintiff Must Prove It With Substance, Not Just Words: Karnataka High Court FIR in Disproportionate Assets Case Quashed: Patna High Court Slams SP for 'Non-Application of Mind' and 'Absence of Credible Source Information' Ownership of Vehicle Linked to Commercial Quantity of Heroin – Custodial Interrogation Necessary: Punjab & Haryana High Court Denies Anticipatory Bail under Section 482 BNSS Death Caused by Rash Driving Is Not a Private Dispute — No FIR Quashing on Basis of Compromise in Section 106 BNS Cases: Punjab & Haryana High Court No Bank Can Override Court Orders: Rajasthan High Court Slams Axis Bank for Unauthorized Withdrawal from Court-Ordered FD" Indian Courts Cannot Invalidate Foreign Arbitral Awards Passed Under Foreign Law: Madhya Pradesh High Court Enforces Texas-Based Award Despite Commercial Court’s Contrary Decree Sudden Quarrel over Mound of Earth — Not Murder but Culpable Homicide: Allahabad High Court Eligibility Flows from Birth, Not a Certificate Date: Delhi High Court Strikes Down Rule Fixing Arbitrary Cut-Off for OBC-NCL Certificates in CAPF (AC) Recruitment Bar Under Order II Rule 2 CPC Cannot Be Invoked Where Specific Performance Was Legally Premature Due To Statutory Impediments: P&H High Court Once a Court Declares a Department an Industry Under Section 2(j), State Cannot Raise the Same Objection Again: Gujarat High Court Slams Repetitive Litigation by Irrigation Department “How Could Cheques Issued in 2020 Be Mentioned in a 2019 Contract?”: Delhi High Court Grants Injunction in Forged MOA Case, Slams Prima Facie Fabrication Calling Wife by Her Caste Name in Public Just Before Suicide is Immediate Cause of Self-Immolation: Madras High Court Upholds Husband’s Conviction Under Section 306 IPC Sole Testimony of Prosecutrix, If Credible, Is Enough to Convict: Delhi High Court Upholds Rape Conviction Cheque Issued as Security Still Attracts Section 138 NI Act If Liability Exists on Date of Presentation: Himachal Pradesh High Court No Work No Pay Is Not a Universal Rule: Punjab & Haryana High Court Dock Identification Without Prior TIP Is Absolutely Useless: P&H High Court Upholds Acquittal in Attempt to Murder Case Filing Forged Court Pleadings in Union Government’s Name is Criminal Contempt: Karnataka High Court Sentences Litigant to Jail Execution of Will Proved, But Probate Justly Denied Due to Concealment of Property Sale: Delhi High Court Mere Designation Doesn’t Establish Criminal Liability: Bombay High Court Quashes Proceedings Against ICICI Officials in Octroi Evasion Case Fraud on Power Voids the Order: Supreme Court Quashes FIR Against Karnataka BJP Leader R. Ashoka, Slams Politically Motivated Prosecution Cause of Fire Is Immaterial If Fire Itself Is Insured Peril: Supreme Court Rebukes Insurer’s Repudiation Dragging a Trained Army Officer Up 20 Steps Without Resistance? The Story Lacks Credence: Supreme Court Upholds Acquittal in Army Officer’s Murder Semen Stains Alone Do Not Prove Rape: Supreme Court Acquits Doctor Accused of Rape No Mortgage, No SARFAESI: Supreme Court Rules Against NEDFi, Says Recovery Action in Nagaland Without Security Agreement Was Illegal Parity Cannot Be Denied by Geography: Supreme Court Holds Jharkhand Bound by Patna HC's Judgment, Orders Pay Revision for Industries Officer Once Power Flows Continuously from a Synchronized Turbine, It Is No Longer Infirm: Supreme Court Orders TANGEDCO to Pay Fixed Charges to Penna Electricity

Contractor Bound by Contractual Terms, No Right to Claim Damages After Accepting Extensions: Supreme Court

05 February 2025 4:58 PM

By: sayum


Supreme Court has dismissed a contractor’s appeal seeking damages for employer-caused delays, holding that the limitation of liability clause (Clause 49.5) in the General Conditions of Contract (GCC) was enforceable. The Court ruled that the contractor, having repeatedly invoked Clause 49.5 to obtain extensions of time without protest and having expressly waived claims beyond escalation, was estopped from challenging its validity.

Justice Abhay S. Oka, delivering the judgment, observed: "The appellant acted upon Clause 49.5 and sought extensions of time on multiple occasions. Having accepted the stipulation, it cannot later claim damages for delay. By its conduct, the appellant is estopped from challenging the validity of Clause 49.5."

An agreement dated June 28, 2012, was entered into between M/s. C & C Constructions Ltd. (appellant) and IRCON International Ltd. (respondent) for constructing five Road Over Bridges (ROBs) in Rajasthan. Due to alleged delays attributable to IRCON, the appellant sought extensions of time, which were granted under Clause 49.5 of the GCC. However, the contractor later sought damages for delays, which IRCON rejected, citing the limitation of liability clause.

The arbitral tribunal rejected the claims summarily under Section 16(2) of the Arbitration and Conciliation Act, 1996, on the ground that Clause 49.5 explicitly barred such claims. The Delhi High Court upheld this decision under Sections 34 and 37 of the Arbitration Act. The present appeal before the Supreme Court challenged the High Court's ruling.

Enforceability of Clause 49.5

The Supreme Court examined Clause 49.5 of the GCC, which provided: "In the event of any failure or delay by the Employer/Engineer in fulfilling his obligations under the contract, then such failure or delay shall in no way affect or vitiate the contract or alter the character thereof; or entitle the Contractor to damages or compensation thereof but in any such case, the Engineer shall grant such extension or extensions of time to complete the work, as in his opinion is/are reasonable."

The Court ruled that the appellant had accepted this clause when seeking extensions of time and had even submitted written undertakings that it would not claim anything beyond escalation. The Court noted: "The appellant explicitly undertook on January 14, 2015, that it would not make any claim other than escalation for delays in completion. Two years later, it sought damages, contradicting its own solemn undertaking. Such conduct estops the appellant from challenging Clause 49.5."

Public Policy and Contractual Freedom

The appellant argued that Clause 49.5 violated Sections 23 and 28 of the Indian Contract Act, 1872, by restricting legal recourse and being against public policy. The Supreme Court rejected this contention, stating:

"Limitation of liability clauses are recognized under Indian law and have been upheld in previous rulings of this Court. Such clauses do not violate public policy unless they completely oust the jurisdiction of courts, which is not the case here."

Further, the Court pointed out that the appellant had not raised this argument before the Single Judge or the Division Bench of the High Court. Hence, it could not be raised for the first time in the Supreme Court.

Scope of Judicial Review Under Section 37 of the Arbitration Act The Supreme Court reaffirmed the limited scope of judicial review in arbitration matters, citing Larsen Air Conditioning and Refrigeration Co. v. Union of India, (2023) 15 SCC 472 and Konkan Railway Corp. Ltd. v. Chenab Bridge Project Undertaking, (2023) 9 SCC 85. The Court held:

"Interference under Section 37 of the Arbitration Act is even narrower than under Section 34. Courts cannot undertake an independent assessment of the merits of an award but must only ascertain whether the arbitral tribunal exceeded its jurisdiction."

Since Clause 49.5 unambiguously barred the claims, the arbitral tribunal was correct in rejecting them at the threshold under Section 16(2) of the Arbitration Act. The Delhi High Court, in upholding this view, did not exceed its jurisdiction under Section 37.

Dismissing the appeal, the Court concluded: "Considering the limited scope of interference, as laid down by this Court, we find absolutely no merit in the appeal, and the same is accordingly dismissed."

Date of Decision: January 31, 2025

Latest Legal News