Delhi High Court, in a ruling dated 17th September 2026, dismissed an appeal challenging the rejection of a recovery suit, holding that a plaintiff is strictly burdened with the duty to prove the extent and value of work executed through cogent, authenticated documentation.
A bench of Justice Neena Bansal Krishna observed that unilateral site records, which remain unverified by the contracting party or the relevant government authority, cannot form the basis of a decree for recovery of money.
Failure To Prove Quantum Of Work
The Appellant, M/s Hi-Tech Geosynthetics Pvt. Ltd., sought to recover over Rs. 7.5 lakh from the Respondent, M/s Shubh Construction Co., alleging that its work under a PWD project was delayed due to the Respondent's failures. While acknowledging the contractual relationship, the Court noted that the Appellant failed to produce the Measurement Book or any authenticated Daily Progress Reports (DPRs) that could substantiate the specific quantum of work performed. The Court remarked that the burden of proving entitlement to the claimed amount lies squarely on the plaintiff, particularly when the work value is contested.
Requirement Of Authenticated Evidence
The Court highlighted that the DPRs relied upon by the Appellant were internal documents that lacked the necessary countersignatures of the Defendant or the concerned PWD officials. The High Court affirmed that in commercial litigation, internal records maintained unilaterally by the claimant, without independent verification or authentication by the opposing party or the project owner, are insufficient to discharge the initial burden of proof under the Indian Evidence Act.
Contractual Obligations And Performance Guarantee
Addressing the appellant's failure to furnish a Corporate Performance Guarantee—a mandatory requirement under the work order—the Court observed that the appellant’s own testimony admitted that the project had not been "satisfactorily completed" in accordance with the specified requirements. The Court rejected the argument that the non-performance of the Respondent justified the Appellant's breach of contractual obligations, especially in the absence of evidence proving that the Respondent had prevented the Appellant from completing the work or fulfilling the guarantee.
Court Rejects Speculative Financial Claims
The Court further observed that the appellant’s allegations regarding additional expenses, such as costs incurred due to non-provision of 'Form-38' (road permits) and the cost of idle labor, remained unsubstantiated. Justice Neena Bansal Krishna emphasized that mere oral assertions or unilateral correspondence from the claimant do not equate to evidence, particularly when the facts in issue are capable of being verified by documentary evidence such as site logs, formal complaints to government authorities, or corroborated financial records.
Absence Of Corroborative Records Fatal To Claim
The High Court noted that the appellant's failure to examine key personnel who maintained the site records, combined with the absence of any contemporaneous technical or PWD inspection reports, left the court with no reliable basis to compute the alleged outstanding balance. The court concluded that the trial court correctly drew an adverse inference regarding the appellant's inability to reconcile the total project value of Rs. 14,28,800 against the admitted advance payment of Rs. 10,00,000, ultimately leading to the dismissal of the suit.
Date of Decision: 17 September 2026