Seniority Must Be Calculated From the Date of Initial Appointment, Not Regularization: Madras High Court Rules Section 319 Cr.P.C. | Mere Association Not Enough for Criminal Liability: Karnataka HC Himachal Pradesh High Court Upholds ₹25,000 Per Kanal Compensation for Land Acquired for Nangal-Talwara Railway Line, Dismisses Railway’s Appeal No Work No Pay Principle Not Applicable: Orissa High Court Orders Reinstatement and Full Back Wages for Wrongfully Terminated Lecturer No Assault, No Obstruction, Only Words Exchanged: Bombay High Court Quashes Charges of Obstruction Against Advocates Under Section 353 IPC Matrimonial Offences Can Be Quashed Even if Non-Compoundable, When Genuine Compromise Is Reached: J&K HC Plaintiff Entitled to Partition, But Must Contribute Redemption Share to Defendant: Delhi High Court Clarifies Subrogation Rights in Mortgage Redemption Labeling Someone A 'Rowdy' Without Convictions Infringes Personal Liberty And Reputation: Kerala High Court P&H High Court Denies Pensionary Benefits for Work-Charged Employee's Widow; Declares Work-Charged Service Not Eligible for ACP or Pension Benefits Acquittal is Acquittal: Rajasthan High Court Orders Appointment of Candidate Denied Job Over Past FIR At The Bail Stage, Culpability Is Not To Be Decided; Allegations Must Be Tested During Trial: Andhra Pradesh High Court Grants Bail in SCST Supreme Court Dismisses Challenge to "Secular" and "Socialist" Additions in Constitution Preamble Supreme Court Rejects Res Judicata in Land Allotment Case: Fresh Cause of Action Validates Public Interest Litigation Public Resources Are Not Privileges for the Few: Supreme Court Declares Preferential Land Allotments to Elites Unconstitutional Past antecedents alone cannot justify denial of bail: Kerala High Court Grants Bail Revenue Records Alone Cannot Prove Ownership: Madras High Court Dismisses Temple's Appeal for Injunction Humanitarian Grounds Cannot Undermine Investigation: Himachal Pradesh High Court Grants Interim Bail in ₹200 Crore Scholarship Scam The Power Under Order XXXVIII, Rule 5 CPC is Drastic and Extraordinary; Should Not Be Exercised Mechanically or Merely for the Asking: Calcutta High Court

Arbitrators Must Adhere to Contractual Terms, Sets Aside Award for Ignoring Key Evidence: Calcutta High Court

13 September 2024 9:43 AM

By: sayum


"The fundamental policy of Indian law mandates that relevant evidence must guide arbitral decisions, not extraneous considerations." – Justice Sabyasachi Bhattacharyya

The Calcutta High Court, presided by Justice Sabyasachi Bhattacharyya, set aside portions of an arbitral award favoring M/s. Jay Bharat Construction, following a dispute with the South Eastern Railways. The court upheld the Railways' challenge under Section 34 of the Arbitration and Conciliation Act, 1996, reversing the award of a security deposit refund and partially granting the "risk and cost" claim in favor of the Railways. The case stemmed from a terminated contract for incomplete construction work and led to a contentious arbitration.

The Union of India, through the South Eastern Railways, contracted M/s. Jay Bharat Construction for construction work, which was extended multiple times due to delays. When the contractor failed to complete the work, the Railways terminated the contract under Clause 62 of the General Conditions of Contract (GCC). Following the termination, Jay Bharat initiated arbitration, claiming a refund of its security deposit, while the Railways counterclaimed under the "risk and cost" provision for the expenses incurred to complete the unfinished work through a third party.

The court examined whether the Arbitral Tribunal acted outside the terms of the contract by awarding the refund of the security deposit and partially denying the "risk and cost" claim of the Railways. Specifically, the court focused on whether the Tribunal's conclusions were based on irrelevant factors and contrary to the contract's provisions, particularly Clause 62 of the GCC.

The Railways, represented by Ms. Aparna Banerjee, contended that the Arbitral Tribunal ignored the contract’s explicit terms. According to the contract, the security deposit should have been forfeited following the valid termination of the agreement due to the contractor’s failure to complete the work. Additionally, the Railways argued that the Tribunal miscalculated the "risk and cost" claim, relying on an irrelevant document (Annexure 'C') while ignoring crucial evidence (Annexures 'A' and 'B') that detailed the expenses incurred for completing the remaining work.

The respondent, Jay Bharat Construction, represented by Ms. Swapna Paul, defended the Tribunal’s decision, asserting that the arbitration award should not be interfered with, given the limited scope of judicial review under Section 34 of the Arbitration and Conciliation Act.

Justice Bhattacharyya highlighted several fundamental errors in the Tribunal's reasoning. First, the Tribunal directed a refund of the security deposit despite the valid termination of the contract, which was contrary to Clause 62 of the GCC. The court emphasized that the Railways had followed the contractual procedure of giving notice, making the forfeiture of the security deposit automatic. The non-imposition of Liquidated Damages (LD) during earlier contract extensions was irrelevant to the forfeiture decision.

Second, on the "risk and cost" issue, the court criticized the Tribunal’s reliance on Annexure 'C', which only reflected work completed for which drawings were provided. The Tribunal overlooked Annexures 'A' and 'B', which detailed the work that could be completed without the drawings and the associated costs. The court found this reliance on irrelevant documents to be "perverse" and a violation of the basic principles of arbitral jurisprudence.

The court held that the arbitral award, in its reliance on extraneous materials and failure to consider relevant evidence, violated the "fundamental policy of Indian law." It concluded that the award was not only contrary to the contract but also conflicted with basic notions of justice, thus falling within the grounds for judicial intervention under Section 34 of the Arbitration and Conciliation Act.

This judgment reinforces the principle that arbitrators must strictly adhere to the terms of the contract and relevant evidence when making awards. The court’s intervention sets a precedent that arbitral awards deviating from the contract or relying on irrelevant factors are vulnerable to challenge under Section 34. The decision underscores the balance between party autonomy in arbitration and the need for arbitral tribunals to respect contractual obligations.

Date of Judgment: September 10, 2024

Union of India vs. M/s. Jay Bharat Construction

Similar News