-
by sayum
19 December 2025 10:48 AM
"Petitioner Entitled to Infancy Benefit under Section 16(1)(d); EPF Authorities Acted Without Proper Legal Basis", Calcutta High Court struck down a series of penal orders issued under the Employees’ Provident Fund and Miscellaneous Provisions Act, 1952, holding that the petitioner’s establishment was a new and independent unit entitled to exemption under Section 16(1)(d) of the Act (as it stood before omission in 1997).
Justice Shampa Dutt (Paul) ruled that the authorities had acted without legal justification, based on “irrelevant judicial precedents”, and without appreciation of the independent legal and functional identity of M/s Durga Engineering Works. The Court further held that the Appellate Tribunal's dismissal order dated 30.09.2014 was passed “without any independent findings and has been made on general observations”, constituting a “violation of natural justice”.
“The Tribunal’s Order Was Passed Without the Matter Being Listed or the Parties Being Heard”: Court Condemns Violation of Natural Justice
The case arose when M/s. Durga Engineering Works challenged an order of the EPF Appellate Tribunal dated 30th September 2014 in ATA No. 497(15)2004, by which its statutory appeal against a damages order under Section 14B was dismissed. The High Court found that:
“The appeal was not listed on 30th September 2014. The matter was neither heard nor were the parties present. Yet, the Tribunal passed an order dismissing the appeal. This is clearly a breach of natural justice.”
The Court summoned the Tribunal’s records and noted that while an unsigned order sheet suggested the matter was heard and reserved in July 2014, no signed record supported the same, and the dismissal on 30th September occurred when the appeal was not even on the cause list.
“Durga Engineering Works is a Newly Established, Functionally Independent Unit—Not a Continuation of Punjab Engineering Works”
The principal issue revolved around whether the petitioner’s firm—set up on 1st April 1994—was entitled to a three-year exemption under Section 16(1)(d) of the EPF Act, which, prior to its omission in 1997, exempted new establishments from coverage for three years.
The Court held that the EPFO’s attempt to treat the petitioner’s firm as a mere extension or “partitioned unit” of M/s Punjab Engineering Works was unsustainable. The petitioner had clearly demonstrated that:
“M/s. Durga Engineering Works is a new separate entity since 3.5.94. The two units have their own machineries, manufacture different products and are still functioning independently.”
Rejecting the authorities' reliance on various judgments involving disguised continuations of older firms, the Court clarified that:
“The judgments relied upon by the authority concerned are not applicable to the present case, as the two units are totally independent of each other and both are functional.”
The EPFO had argued that Durga Engineering Works was a “partition unit” of the parent establishment because one of the partners from the old firm, Bimal Kumar Gupta, later became a partner in the new entity. The Court decisively held that such commonality of personnel did not amount to legal or operational continuity.
“Non-Allotment of Code Number Not a Valid Excuse”—But Tribunal Gave Contradictory Reasons for Rejecting the Appeal
The authorities, while levying damages under Section 14B, reasoned that the delay in contributions between April 1997 and May 1999 was not justified by the firm’s claim of non-allotment of code number. They cited the Madras High Court’s decision in Ujwal Transport Agency v. Union of India (1998) to argue that:
“In the instant case, non-allotment of a specific code number is not a valid excuse for default in payment of contribution… The employer is obliged to make stipulated payments within time.”
However, the Appellate Tribunal, in dismissing the appeal, rejected the petitioner’s defense not on these grounds but on entirely different and generalised reasons, stating:
“Financial constraints and shortage of raw material etc. are not considered mitigating factors in determination of damages under Section 14B of the Act.”
The Court observed a glaring legal inconsistency:
“The reasons given by the authority passing the order under Section 14B and the reasons given by the Tribunal in its order under challenge dated 30th September, 2014 are entirely different.”
The divergence indicated a lack of judicial application of mind and further vitiated the dismissal.
“Eligibility for Section 16(1)(d) Must Be Determined on Functional and Structural Independence, Not on Assumptions of Continuity”
The High Court undertook a detailed comparison of both firms. It noted that Durga Engineering Works was engaged in manufacturing cold drawn bright steel bars, while Punjab Engineering Works produced oil mill machinery and its spares. The firms had separate licenses, excise registrations, tax numbers, profit-loss accounts, production supervisors, and locations.
The Court noted: “Being a newly set up establishment w.e.f. 1st April 1994, the partnership firm was eligible for exemption for a period of three years from the said date under Section 16(1)(d) of the Act.”
The Court also found that the APFC’s findings under Section 7A were incorrect in clubbing the two firms, and that merely forming a new firm with different partners and using part of the premises of the old firm does not imply legal continuity.
Quoting the legal standard from Lakshmi Rattan Engineering Works v. RPFC, the Court observed that:
“A mere change in ownership, change of location and even change of line of business does not necessarily affect the continuity of the establishment… But only when the business continues as usual.”
That test, the Court found, was not satisfied in this case, as both businesses were independently functional and distinct in nature.
“Orders under Sections 7A, 14B and 7Q Not Sustainable in Law”—All Set Aside
Justice Shampa Dutt (Paul) categorically held that the initial order under Section 7A—which wrongly determined the petitioner’s unit to be a continuation of the parent unit—and the damages order under Section 14B and interest under Section 7Q were not in accordance with law.
“Accordingly, as this Court holds that the petitioner is entitled to the benefit under Section 16(1)(d) of the Act (then in force), the orders under Sections 7A, 14B and 7Q of the Act, being not in accordance with law, are set aside.”
"Tribunal Order Dismissed Without Application of Mind"—Writ Petition Allowed
The Court allowed the writ petition, noting that the Tribunal had failed to provide any reasoned order, and had dismissed the appeal without proper hearing. It also allowed the petitioner to withdraw the deposited amount along with interest from the Registrar General's office, in compliance with the Court’s prior order dated 16.03.2016.
“The order dated 30.09.2014 passed by the Employees’ Provident Fund Appellate Tribunal, New Delhi in ATA NO. 497(15)2004, also being not in accordance with law is also set aside.”
Date of Decision: 11th September 2025