Bail | Right to Speedy Trial is a Fundamental Right Under Article 21: PH High Court    |     Postal Department’s Power to Enhance Penalties Time-Barred, Rules Allahabad High Court    |     Tenants Cannot Cross-Examine Landlords Unless Relationship is Disputed: Madras High Court    |     NDPS | Conscious Possession Extends to Vehicle Drivers: Telangana High Court Upholds 10-Year Sentence in Ganja Trafficking Case    |     Aid Reduction Of Without Due Process Unlawful: Rajasthan High Court Restores Full Grants for Educational Institutions    |     Assessment of Notional Income in Absence of Proof Cannot Be 'Mathematically Precise,' Says Patna High Court    |     NCLT's Resolution Plan Overrides State Tax Claims: Andhra Pradesh High Court Quashes Demands Against Patanjali Foods    |     An Agreement is Not Voidable if the Party Could Discover the Truth with Ordinary Diligence: Calcutta High Court Quashes Termination of LPG Distributorship License    |     Independent Witnesses Contradict Prosecution's Story: Chhattisgarh High Court Acquit Accused in Arson Case    |     Merely Being a Joint Account Holder Does Not Attract Liability Under Section 138 of NI Act:  Gujarat High Court    |     Higher Court Cannot Reappreciate Evidence Unless Perversity is Found: Himachal Pradesh High Court Refused to Enhance Maintenance    |     Perpetual Lease Allows Division of Property: Delhi High Court Affirms Partition and Validity of Purdah Wall    |     "Party Autonomy is the Backbone of Arbitration: Bombay High Court Upholds Sole Arbitrator Appointment Despite Party’s Attempts to Frustrate Arbitration Proceedings    |     Videography in Temple Premises Limited to Religious Functions: Kerala High Court Orders to Restrict Non-Religious Activities on Temple Premises    |     Past Service Must Be Counted for Pension Benefits: Jharkhand High Court Affirms Pension Rights for Daily Wage Employees    |     'Beyond Reasonable Doubt’ Does Not Mean Beyond All Doubt: Madras High Court Upholds Life Imprisonment for Man Convicted of Murdering Mother-in-Law    |    

In the Absence of a Written Statement, Participation Is Confined to Cross Examination and Legal Arguments: Supreme Court

18 September 2024 4:40 PM

By: sayum


In a significant judgment, the Supreme Court of India has modified the compensation formula prescribed by the National Consumer Disputes Redressal Commission (NCDRC) for delayed possession of flats. The Court, addressing the appeal in Kaushik Narsinhbhai Patel & Ors. v. M/s. S.J.R. Prime Corporation Private Limited & Ors., underscored the necessity of adhering strictly to contractual agreements, particularly in real estate transactions where delays can cause considerable distress to homebuyers.

The appellants, numbering 46, along with several proforma respondents, filed Consumer Case No. 945 of 2019 against M/s. S.J.R. Prime Corporation Private Limited, alleging deficiencies in the completion and possession of flats in the project 'Fiesta Homes by SJR Prime'. According to the construction agreement dated March 31, 2012, the possession was to be handed over by March 2014, with a grace period of six months. However, the possession was delayed by about four years, leading the complainants to seek redressal for this inordinate delay.

The Supreme Court highlighted that the NCDRC had erroneously considered new facts and defenses introduced by the builder in written submissions, despite the builder forfeiting its right to file a written statement due to non-compliance with earlier court orders. The Supreme Court ruled that these submissions should not have been taken into account, as per the principle that one cannot indirectly do what is prohibited directly​​.

A pivotal issue was the method used by NCDRC to determine the due date for possession. The NCDRC linked this date to the payment schedule, particularly the 11th installment, rather than the specific contractual agreement date. The Supreme Court asserted that the correct due date must be as per Clause 6.1 of the Construction Agreement, which clearly states March 2014, plus a six-month grace period. This contractual adherence ensures predictability and fairness in real estate dealings​​.

The Court modified the NCDRC's decision by ruling that the developer must pay interest at the rate of 6% per annum from the revised due date (September 2014) until the actual possession date. This aligns with precedents like R.V. Prasannakumaar v. Mantri Castles Private Limited, ensuring consistency in judicial approaches to similar disputes​​.

Justice C.T. Ravikumar emphasized, "In the absence of a written statement, the right to participate in proceedings is confined to legal arguments and cross-examination. The introduction of new facts through written submissions cannot be permitted." This reinforces the importance of procedural compliance and upholding contractual obligations in consumer disputes​​.

This landmark judgment reinforces the necessity for strict adherence to contractual terms in real estate transactions. By revising the compensation formula and stressing the limitations on written submissions after forfeiture, the Supreme Court has clarified and strengthened consumer rights against delays in possession. This decision is expected to have significant implications for future real estate disputes, promoting timely project completions and adherence to agreed terms.

Date of Decision: July 22, 2024

Kaushik Narsinhbhai Patel & Ors. v. M/s. S.J.R. Prime Corporation Private Limited & Ors.

Similar News