MACT | A Minor Cannot Be Treated as a Non-Earner: Punjab & Haryana High Court Consensual Love Affair Not Cheating Under IPC Section 417: Madras High Court Acquits Man Despite Paternity Confirmation Review Jurisdiction is an Ant-Hole in a Pigeon-Hol: Madras High Court Dismisses Review Plea Against Order Upholding Arbitral Award on Liquidated Damages Bank Can Freeze Guarantor’s Salary Account to Recover Loan Dues: Kerala High Court Clarifies CPC Exemption Does Not Apply to Banker’s Right Revenue Entry Calling Property ‘Ancestral’ Does Not Create Title: Gujarat High Court Upholds Registered Will in Second Appeal Licensee Cannot Resist Resumption Of Railway Land: Gauhati High Court Upholds Eviction For Amrit Bharat Station Scheme Mere Non-Payment of Business Dues Is Not Cheating: Calcutta High Court Protects Traders from Criminal Prosecution in Purely Civil Dispute Prosecution’s Failure to Prove Age of Prosecutrix Beyond Reasonable Doubt Fatal to POCSO Conviction: Rajasthan High Court No Title, No Right, No Equity: Bombay High Court Demolishes Claim Over Footpath Stall, Imposes ₹5 Lakh Costs for Abuse of Process Section 155(2) Cr.P.C. Does Not Bar Complainant From Seeking Magistrate’s Permission: Allahabad High Court Clarifies Law on Non-Cognizable Investigations Un-Retracted Section 108 Statement Is Binding: Delhi High Court Declines to Reopen ₹3.5 Crore Cigarette Smuggling Valuation Section 34 Is Not an Appeal in Disguise: Delhi High Court Upholds 484-Day Extension in IRCON–Afcons Tunnel Arbitration Section 432(2) Cannot Be Rendered Fatuous: Calcutta High Court Reasserts Balance Between Judicial Opinion and Executive Discretion in Remission Matters Termination of Mandate Is Not Termination of Arbitration: Bombay High Court Revives Reference and Appoints Substitute Arbitrator CBI Can’t Prosecute When Bank Suffers No Loss: Andhra Pradesh High Court Discharges Bhimavaram Hospitals Directors in ₹1.5 Crore SBI Case Section 256 CrPC Cannot Be A Shield For An Accused Who Never Faced Trial: Allahabad High Court Restores 8 Cheque Bounce Complaints

In the Absence of a Written Statement, Participation Is Confined to Cross Examination and Legal Arguments: Supreme Court

18 September 2024 4:40 PM

By: sayum


In a significant judgment, the Supreme Court of India has modified the compensation formula prescribed by the National Consumer Disputes Redressal Commission (NCDRC) for delayed possession of flats. The Court, addressing the appeal in Kaushik Narsinhbhai Patel & Ors. v. M/s. S.J.R. Prime Corporation Private Limited & Ors., underscored the necessity of adhering strictly to contractual agreements, particularly in real estate transactions where delays can cause considerable distress to homebuyers.

The appellants, numbering 46, along with several proforma respondents, filed Consumer Case No. 945 of 2019 against M/s. S.J.R. Prime Corporation Private Limited, alleging deficiencies in the completion and possession of flats in the project 'Fiesta Homes by SJR Prime'. According to the construction agreement dated March 31, 2012, the possession was to be handed over by March 2014, with a grace period of six months. However, the possession was delayed by about four years, leading the complainants to seek redressal for this inordinate delay.

The Supreme Court highlighted that the NCDRC had erroneously considered new facts and defenses introduced by the builder in written submissions, despite the builder forfeiting its right to file a written statement due to non-compliance with earlier court orders. The Supreme Court ruled that these submissions should not have been taken into account, as per the principle that one cannot indirectly do what is prohibited directly​​.

A pivotal issue was the method used by NCDRC to determine the due date for possession. The NCDRC linked this date to the payment schedule, particularly the 11th installment, rather than the specific contractual agreement date. The Supreme Court asserted that the correct due date must be as per Clause 6.1 of the Construction Agreement, which clearly states March 2014, plus a six-month grace period. This contractual adherence ensures predictability and fairness in real estate dealings​​.

The Court modified the NCDRC's decision by ruling that the developer must pay interest at the rate of 6% per annum from the revised due date (September 2014) until the actual possession date. This aligns with precedents like R.V. Prasannakumaar v. Mantri Castles Private Limited, ensuring consistency in judicial approaches to similar disputes​​.

Justice C.T. Ravikumar emphasized, "In the absence of a written statement, the right to participate in proceedings is confined to legal arguments and cross-examination. The introduction of new facts through written submissions cannot be permitted." This reinforces the importance of procedural compliance and upholding contractual obligations in consumer disputes​​.

This landmark judgment reinforces the necessity for strict adherence to contractual terms in real estate transactions. By revising the compensation formula and stressing the limitations on written submissions after forfeiture, the Supreme Court has clarified and strengthened consumer rights against delays in possession. This decision is expected to have significant implications for future real estate disputes, promoting timely project completions and adherence to agreed terms.

Date of Decision: July 22, 2024

Kaushik Narsinhbhai Patel & Ors. v. M/s. S.J.R. Prime Corporation Private Limited & Ors.

Latest Legal News