-
by Admin
07 May 2024 2:49 AM
On November 8, 2024, the Supreme Court of India, comprising Chief Justice Dr. D.Y. Chandrachud and Justice Manoj Misra, delivered a significant ruling. The Court allowed the petition to refer the dispute to arbitration but declined to address substantive issues regarding the assignment of contract rights and privity of contract at the preliminary stage of appointing an arbitrator.
The dispute arose between Lifeforce Cryobank Sciences Inc (petitioner), a U.S.-based company, and Cryoviva Biotech Pvt. Ltd. along with other respondents (RJ Corp and associated entities). The petitioner claimed that it had acquired all assets, including contractual rights, of Cryobank International, Inc. through a public auction in the United States. This acquisition, the petitioner argued, entitled it to enforce arbitration agreements in a 2009 License Agreement and a 2010 Share Subscription and Shareholders Agreement initially executed by Cryobank International, Inc. and the respondents.
The respondents contested this claim, arguing that the agreements were non-assignable without consent, which had not been given. They contended that there was no privity of contract between themselves and the petitioner, rendering the arbitration clause unenforceable by the petitioner.
The core legal question involved the assignability of contractual rights and obligations without the consent of the other contracting party. The respondents argued that the contracts in question could not be assigned to the petitioner without their approval, a principle reinforced by the Supreme Court in Khardah Company Ltd. v. Raymon & Co (India) Pvt. Ltd., where it was held that obligations cannot be assigned without consent, while rights may be assigned unless restricted by law or contract.
The petitioner, however, maintained that it had stepped into the shoes of Cryobank International, Inc. following the asset acquisition and argued that the respondents had implicitly acknowledged this in various correspondences.
The Court cited DLF Power Ltd. v. Mangalore Refinery & Petrochemicals Ltd., emphasizing that under Section 11(6A) of the Arbitration and Conciliation Act, 1996, the Court’s role at the appointment stage is limited to verifying the "existence of an arbitration agreement." This restriction precludes the Court from making determinations on substantive issues, such as the validity of the assignment or privity concerns, which could only be decided by the arbitrator upon a full hearing of the merits.
"At the stage of considering an application for appointment of an arbitrator the Court is required to examine whether there exists an arbitration agreement between the parties… it would not be appropriate for us to delve deep into the issue as it could well be considered by the arbitrator on the basis of evidence led by the parties." [Paras 7, 11]
The Court held that since the existence of an arbitration clause in the agreements was undisputed, the matter was appropriate for referral to arbitration. It observed that any issues regarding the validity of the assignment or privity of contract could be raised and adjudicated by the arbitrator. This approach aligns with the legislative intent of Section 11(6A), which limits judicial intervention at the appointment stage.
The Court directed the matter to the Delhi International Arbitration Centre to appoint a sole arbitrator to adjudicate the dispute. Importantly, it clarified that the referral to arbitration did not imply any opinion on the merits of the claims, including the petitioner’s standing to enforce the agreements or the arbitrability of the dispute.
"It is made clear that we have not expressed any opinion on the merits of the claim of either party including with regard to the arbitrability of the dispute. All contentions and pleas are kept open for the parties to raise before the arbitral tribunal." [Para 13]
The Supreme Court’s decision underscores the limited scope of judicial inquiry at the stage of appointing an arbitrator under Section 11(6A) of the Arbitration and Conciliation Act. By focusing strictly on the existence of an arbitration agreement, the Court refrained from examining deeper contractual issues of privity and assignment, leaving those to the arbitral tribunal.
This ruling reinforces the autonomy of arbitration proceedings by deferring complex questions about contractual rights and obligations to the arbitrator, thereby upholding the pro-arbitration approach embodied in the Act.
Date of Decision: November 8, 2024