-
by Admin
07 May 2024 2:49 AM
Delhi High Court dismissed an appeal by M/s Progressive Construction Ltd. for being filed 4486 days after the prescribed limitation period. The court, presided over by Justice Girish Kathpalia, declined to condone the extraordinary delay, holding the appellant's explanations inadequate and unsupported by evidence. The judgment reinforces the principle that legal remedies must be pursued with vigilance and within the statutory timeframe.
M/s Progressive Construction Ltd. sought to challenge a money recovery decree issued on September 18, 2012. The company claimed the delay stemmed from professional misconduct by its former counsel and disruptions due to internal organizational changes. According to the appellant, their counsel ceased representing them during the trial without notice, and the company only became aware of the decree in September 2019 upon receiving a demand notice under the Insolvency and Bankruptcy Code (IBC).
Following this realization, the appellant pursued a remedy under Order IX Rule 13 of the Code of Civil Procedure (CPC) to set aside the decree, but this application was dismissed in May 2024. They eventually filed the appeal on October 8, 2024, seeking condonation of the delay under Sections 5 and 14 of the Limitation Act.
The appellant attributed part of the delay to professional misconduct by its counsel but admitted to taking no action against the advocate. The court emphasized:
"Believing the appellant’s version without any evidence would mean condemning the counsel unheard, that too on judicial record."
Further, the court clarified that corporate entities, unlike illiterate or lay individuals, are expected to exercise vigilance over ongoing legal matters.
Section 5 allows courts to condone delays if a party demonstrates sufficient cause. However, the court noted that:
"The sufficiency of cause must be construed liberally in favor of the applicant, but negligence or inaction cannot be condoned, especially when the delay is significant."
Citing Ramlal vs. Rewa Coalfields Ltd., the judgment stressed that limitation laws are based on public policy to provide finality to judicial decrees and ensure legal certainty.
The appellant also sought exclusion of time under Section 14, which provides relief for proceedings pursued bona fide in a forum without jurisdiction. Justice Kathpalia rejected this claim, observing:
"Complete lack of due care and attention is writ large on the face of the record. The appellant first pursued a remedy under Order IX Rule 13 CPC despite the decree not being ex parte, prolonging the litigation without diligence."
Concluding that the appellant failed to show sufficient cause under Section 5 and lacked bona fides for claiming Section 14 benefits, the court dismissed the application for condonation of delay. The appeal, along with related applications, was rejected as time-barred.
Justice Kathpalia remarked: "Justice must be done to both parties equally. A party thoroughly negligent in pursuing its rights cannot deprive the other party of a valuable right accrued under the law."
The ruling reinforces the fundamental principle that statutes of limitation must be strictly adhered to, except in genuinely exceptional circumstances. It underscores that corporate litigants, in particular, are held to a higher standard of diligence. The judgment serves as a cautionary tale against attributing delays to professional misconduct without substantiation and highlights the importance of pursuing legal remedies promptly.
Date of Decision: November 26, 2024